|
||||
|
||||
![]() |
IH 635 ( LBJ Freeway ) Corridor Study - Frequently Asked Questions |
|
LBJ Home Page | Now News | Project Update | Project Information | Implementation Approach | Meetings | Newsletters | Contact List | Frequently Asked Questions | Texas Turnpike Authority | Dallas District Home Page | |
| Frequently Asked Questions |
| 1. (Question) Can you tell me what the vision of TXDOT's out-sourcing schedule for the IH 635 (LBJ) Freeway West Section Project (Tunnel and Managed lanes with direct connectors to IH 35 and LP 12) will be? [2/4/2003] |
| 1. (Answer) We are considering two project delivery systems, the design bid build and the EDA approaches. First, we will provide guidance on our chosen approach. Second, a selection process schedule needs to be timed around TxDOT's ability to obtain environmental clearance for the project (target date of August 2003), and other project related work activities. [2/15/2003] |
| 2. (Question) Can you tell me the order of magnitude for construction in $ for the project that the initial RFP or RFQ would be for? [2/4/2003] |
| 2. (Answer) The estimated construction cost for the entire West Section is shown on the web site. We have not yet determined what portion of the West Section would be phased in as part of this from a construction standpoint. Some of the other project related work items to be undertaken this year will help define the construction and design scope for the project. There is a strong focus on developing a project that will permit the opening of the West Section Managed Lanes soon after the completion of the Dallas High Five (IH 635 / US 75) Interchange. [2/15/2003] |
| 3. (Question) What is the availability of the following items? [4/2/2003] One - An electronic copy of the design schematic for the LBJ Corridor Improvements. Two - If the schematic is not available; An electronic copy of the topography mapping used to develop the schematic. |
3. (Answer) We are still in the process of determining the best method to provide or make available current project information. Until we hold the public hearing we may be reluctant to release or make available much of the current information. The following is a partial list of the information that is being considered for availability. When we decide, the information will be placed on the Internet in a printable document format or be made available on a CD for a nominal fee from the TxDOT Dallas District Library.
|
| 4. (Question) When will the project be scheduled for a Public Hearing, and how soon will the design process begin after that? [4/6/03] |
4. (Answer) There are several concurrent activities that are underway at this time. The most important component is to complete the planning process and receive environmental clearance for the West Section. We have targeted May 29th or June 5th as possible public hearing dates. We will know more for sure in a week. It takes just under 2 months to schedule, advertise, plan and hold a public hearing. Depending on the number and content of the inquiries at the public hearing that will determine when the final documentation can be forwarded for approval. Another item is to be organized and plan for what might happen after a successful Public Hearing. That is briefly outlined in bullet format below under the outsource process section.
|
| 5. (Question) Will TxDOT use an Owner Controlled Insurance Program (OCIP) for the West Section, LBJ Freeway Project? [June 26, 2003] |
| 5. (Answer) The OCIP question is unresolved at this time. We will provide the developers information regarding our position later in the process so they can account for it in their proposals. [07/01/03] |
| 6. (Question) What is the potential scope of the West Section, LBJ Freeway Project, for design and construction as a Comprehensive Development Agreement (CDA)? [Multiple] |
6. (Answer) The West Section for IH 635 (LBJ Freeway), from a planning perspective, includes the entire project from Luna Road to the US 75/IH 635 (Dallas High Five) interchange project. This includes the complete limits of the IH 35E/IH 635 interchange reconstruction from Royal Lane to Valwood Parkway. The focus of a CDA will be to design, construct and begin the operation of the LBJ Freeway Managed Lanes. To do this a major portion of the West Section improvements will need to be designed and constructed. The project generally can be broken into three parts. [07/01/03]
|
| 7. (Question) What is the updated timeline on when selection of the Procurement Engineer / Program Manager (PcE/PM) will begin? [Multiple] |
| The notification of interest (NOI) for the Procurement Engineer / Program Manager (PcE/PM) is being prepared at this time. It may be possible that it will be “out” within the month or not long after that. The complete process for notification, interest, evaluation, selection and negotiation could take 4 to 8 months. [07/01/03] |
| 8. (Question) When will a request for qualification (RFQ) of the CDA Developers be due? [Multiple] |
| TxDOT first needs to solicit, select and begin working with PcE/PM for the project. The PcE/PM’s initial responsibility will be the development of the LBJ Freeway Managed Lanes CDA procurement process. However, TxDOT may be in a position to “put out” the RFQ in advance of completing that selection process in an attempt to streamline the process. It is possible that the RFQ could be timed to be ready for publication soon after receiving environmental clearance this fall. [07/01/03] |
| 9. (Question) Could you provide an update of the LBJ schedule. Specifically: 1. Date for issuance of RFQ, 2. Expected date due for SOQ, 3. Expected date of issuance of RFP for industry comment, 3. Expected due date on industry comments on RFP, 4. Expected date of notification of shortlisted (SOQ) firms, 5. Anticipated date of issuance of RFP, 6. Anticipated date of notification of selection of firm for project, and 7. Expected NTP for project. [1/2/2004] |
| TxDOT is completing the selection process for the Procurement Engineer. One of the key tasks for the Procurement Engineer is to assist TxDOT in completing the process for securing the CDA Team. We anticipate being in position to put out the Request for Qualifications (RFQ) early this year. The end result of securing the CDA Team is the Notice to Proceed (NTP). We are targeting Mid 2005 for that to occur. We are not yet in a position to answer any of the in between dates you are requesting at this time. [1/6/2004] |
| 10. How might a potential CDA Proposer be able to schedule a time to view the core logs form the Phase I or Phase 2 Geotechical Investigation Programs? |
| Potential CDA Proposers may view the Phase I and Phase II cores as follows: |
|
| Disclaimer |
THE REPORTS, DATA, PLANS, SPECIFICATIONS, MATERIALS, ANALYSES AND INFORMATION PROVIDED ON THIS WEBSITE ARE FOR INFORMATION AND REFERENCE PURPOSES ONLY AND ARE PROVIDED AS AN ACCOMMODATION TO THOSE INDIVIDUALS AND PARTIES INTERESTED IN THE PROJECT AND ITS PROGRESS. THE DEPARTMENT EXPRESSLY DISCLAIMS ANY REPRESENTATIONS AND WARRANTIES CONCERNING THE ACCURACY OR COMPLETENESS OF SUCH ITEMS AND RECIPIENTS AND VIEWERS OF THESE ITEMS SHALL NOT BE ENTITLED TO RELY UPON SUCH ITEMS FOR ANY PURPOSE. IF AND TO THE EXTENT THE DEPARTMENT INITIATES A PROCUREMENT CONCERNING THE PROJECT, THE DEPARTMENT WILL SPECIFICALLY IDENTIFY IN THE PROCUREMENT DOCUMENTS AND SOLICITATION MATERIALS WHICH ITEMS, IF ANY, MAY BE RELIED UPON BY INTERESTED PARTIES (AS WELL AS THE EXTENT OF SUCH PERMITTED RELIANCE). |
|
© Copyright 2012, TxDOT All Rights Reserved. |
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts |