|
||||
|
||||
![]() |
IH 635 ( LBJ Freeway ) Corridor Study - Project Update |
|
LBJ Home Page | Now News | Project Update | Project Information | Implementation Approach | Meetings | Newsletters | Contact List | Frequently Asked Questions | Texas Turnpike Authority | Dallas District Home Page | |
|
General Information Who: Since April of 1993 the Texas Department of Transportation (TxDOT) has coordinated the study efforts for the corridor. This study has been accomplished with the cooperation and involvement of the North Central Texas Council of Governments (NCTCOG), Dallas Area Rapid Transit (DART), and the North Texas Toll Authority (NTTA). The community and local governments have made valuable and key contributions to the completed Major Investment Study (MIS) and current configuration of the schematic designs for each section. What: (General) The LBJ Corridor Study has been broken into four basic sections. These are shown on the inset map on this page; 1) I.H. 635 & U.S 75 Interchange, 2) Mesquite, 3) East, and 4) West. Each of these sections is at various stages of project development. Specific project status is indicated in the table below. What: (Specific) Improvements for each section are generally listed below. Contact the LBJ Project Office for additional details. Improvements will include bicycle, pedestrian, urban (aesthetic) design and noise mitigation features.
When: (Schedule) The general approach to implementing the entire corridor work effort was to start with the Dallas High Five first then progress to a combination of these improvements; the Mesquite Section, East Section frontage roads, including various intersection, ramp and auxiliary lane improvements. Parallel to this effort will be a focus on completing the necessary projects to open and operate the West Section tunnels soon after completing the Dallas High Five (Estimated Completion Jan 2007). Future mainlane, HOV/Toll and major interchange work at I.H. 35E and I.H. 30 to follow, as funding becomes available. A current assessment of where the LBJ projects are in the project development process is shown below.
* Hold Public Hearing, ** Open bids with construction to follow, *** Construction Only in Millions, TBD – To Be Determined Where: The I.H. 635 (LBJ) Freeway is located in the Dallas-Fort Worth metropolitan area. The corridor is approximately 21 miles long from west of I.H. 35E to U.S. 80. Belt Line Road and Loop 12 bound the corridor study. Municipalities located adjacent to the freeway include Dallas, Farmers Branch, Garland and Mesquite.
Key Issues and How can you help: Projects of this size are very difficult to fund and implement. They require a great amount of coordination between the adjacent communities. For the LBJ Corridor project this effort has been tremendous, and has carried as almost through the planning process. As the group works toward the design phase continued energy is needed to focus on completing the most critical aspects of the project. Two key issues will be to secure design funding and the necessary approvals to begin the design effort for both the East Section and the West Section. | |||||||||||||||||||||||||||||||||||||||||||||
|
© Copyright 2012, TxDOT All Rights Reserved. |
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts |