1995 Statewide Special Specifications
(Items 6001 to 6607)
Last Update (01/30/2003)
Click here to return to Index Page
Table Of Contents
ITEM NO. - TITLE AND REQUIREMENTS
6001 - DIGITAL LOOP VEHICLE DETECTOR
UNIT
SPECIFICATION REQUIREMENTS
1) The locations for installing Digital Loop Detector Units shall be of the
various types
shown on the plans.
2) Unless otherwise shown on the plans, loop detector units shall be single
channel units.
3) Unless otherwise shown on the plans, the loop detector unit shall be supplied
with the
delay and extend output features included in this
specification. Unless otherwise shown
on the plans, the delay and extended features shall not be
required to function simultaneously.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the Various bid items
REFERENCE ITEMS
None
Go to Top
6002 - FLASHER CONTROLLER ASSEMBLY
SPECIFICATION REQUIREMENTS
1) The locations for Flasher Controller Assembly shall be as specified on the
plans.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the various bid items
REFERENCE ITEMS
None
Go to Top
6003 - VEHICLE LOOP WIRE
SEALANT
SPECIFICATION REQUIREMENTS
1) The locations for installation of Vehicle Wire Sealant shall be as shown on
the plans.
2) Unless otherwise shown on the plans, the Contractor shall apply the sealant
using his
own equipment.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the various bid items
REFERENCE ITEMS
None
Go to Top
6004 - THREE CONDUCTOR NEUTRAL SUPPORTED
SECONDARY CABLE (TRIPLEX)
SPECIFICATION REQUIREMENTS
1) The locations for installation of three conductor neutral supported secondary
cable
(Triplex) shall be as specified on the plans.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to Item 680
REFERENCE ITEMS
(680)
Go to Top
6005 - PROGRAMMABLE SIGNAL
HEADS
SPECIFICATION REQUIREMENTS
1) The locations for Programmable Signal Heads shall be as shown on the plans.
2) The head shall mount to standard 38 millimeter fittings as a single section,
multiple sections
or in combination with other faces. The fittings shall be
provided with the head and shall
be mounted as shown on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Programmable Signal Section" |
EA |
REFERENCE ITEMS
None
Go to Top
6007 - ROADSIDE FLASHING BEACON
ASSEMBLIES
SPECIFICATION REQUIREMENTS
1) The locations for Roadside Flashing Beacon Assemblies shall be as shown on
the plans.
2) Roadside flashing beacon assemblies shall be fabricated, assembled and
installed in accordance
with the details and dimensions shown on the plans or as
approved by the Engineer in writing
and shall meet the requirements of the TMUTCD.
3) Unless otherwise shown on the plans, the Contractor shall stake and the
Engineer will verify
all roadside flashing beacon assembly locations.
4) When shown on the plans, line (ungrounded conductor) connector shall be
fused.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Roadside Flashing Beacon Assemblies" |
EA |
REFERENCE ITEMS
(441, 442, 445, 446, 447, 449, 618, 620)
Go to Top
6008 - SALVAGING TRAFFIC
SIGNALS
SPECIFICATION REQUIREMENTS
1) The locations for Salvaging Traffic Signals shall be in accordance with the
plans or as
directed by the Engineer.
2) Unless otherwise shown on the plans, existing concrete foundations that are
to be abandoned
shall be removed to 610 millimeters below finish grade.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Salvaging Traffic Signals" |
EA |
REFERENCE ITEMS
None
Go to Top
6009 - TEMPORARY LIGHTING
SYSTEM
SPECIFICATION REQUIREMENTS
1) The locations for installing Temporary Lighting System shall be as shown on
the plans.
2) The Contractor shall furnish all material except, when shown on the plans,
the State
may furnish part of the Material.
3) Unless otherwise shown on the plans, luminaires shall be installed on bracket
arms mounted on
timber poles. Unless otherwise shown on the plans, conductors
may be installed either underground
or overhead at the option of the Contractor and with approval
of the Engineer.
4) Poles on an existing highway lighting system will not be used to support
overhead wiring unless
approved by the Engineer or shown on the plans.
5) The Contractor shall pay all connection charges required by the utility
company. Unless otherwise
shown on the plans, the State will pay all monthly utility
service and energy charges. Unless otherwise
shown on the plans, the Contractor shall be responsible for
maintaining the temporary lighting system.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Temporary Lighting System" |
LS |
REFERENCE ITEMS
(618, 620, 622, 624, 627, 628)
Go to Top
6010 - REMOVING AND REPLACING ROADWAY LUMINAIRES
SPECIFICATION REQUIREMENTS
1) The locations for removing and replacing Roadway Luminaires shall be as shown
on the plans.
2) All materials and construction methods shall be in accordance with the
details shown on the plans.
3) The Contractor shall replace existing luminaires with new luminaires of the
types and wattages
shown on the plans.
4) Unless otherwise noted on the plans, existing luminaires will remain the
property of the State and
the Contractor shall stockpile luminaires at a location
designated by the Engineer.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Removing and Replacing Roadway Luminaires" |
EA |
REFERENCE ITEMS
(610, 616, 618, 620)
Go to Top
6011 - STEEL MAST ARM POLE ASSEMBLIES FOR
SIGNS
SPECIFICATION REQUIREMENTS
1) The locations for Furnishing Steel Mast Arm Pole Assemblies shall be as shown
on the plans.
2) Unless otherwise specified on the plans, these assemblies shall conform to
the requirements
of Item 686, except for measurement and payment.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Steel Mast Arm Pole Assemblies for Signs" |
EA |
REFERENCE ITEMS
(686)
Go to Top
6012 - REMOVAL, TEMPORARY RELOCATION AND PERMANENT REINSTALLATION OF SIGN
ASSEMBLIES
SPECIFICATION REQUIREMENTS
1) The locations for removal, temporary relocation and permanent reinstallation
of sign
assemblies shall be as shown on the plans or as directed by the
Engineer.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Removal and Reinstallation of Sign Assembly with |
|
|
305 millimeter Foundations" |
EA |
2) |
"Removal and Reinstallation of Sign Assembly with |
|
|
610 millimeter Foundations" |
EA |
REFERENCE ITEMS
(646, 647, 656)
Go to Top
6013 - REMOVING OVERHEAD
SIGNS
SPECIFICATION REQUIREMENTS
1) The locations for removing overhead signs shall be as shown on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Removing Overhead Signs" |
EA |
REFERENCE ITEMS
None
Go to Top
6014 - REMOVING OVERHEAD SIGN LIGHTING
FIXTURES
SPECIFICATION REQUIREMENTS
1) The locations for removing overhead sign lighting fixtures shall be as shown
on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Removing Overhead Sign Lighting Fixtures" |
EA |
REFERENCE ITEMS
None
Go to Top
6015 - REMOVING AND RELOCATING OVERHEAD SIGN
BRIDGES
SPECIFICATION REQUIREMENTS
1) The locations for Removing and Relocating Overhead Sign Bridges shall be as
shown
on the plans or as directed by the Engineer.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Removing and Relocating Overhead Sign Bridges" |
EA |
REFERENCE ITEMS
(416)
Go to Top
6016 - STRENGTHENING OVERHEAD SIGN SUPPORT
STRUCTURES
SPECIFICATION REQUIREMENTS
1) The locations for Strengthening Overhead Sign Support Structures shall be as
shown on the plans.
2) All steel, bolts, nuts, washers, plates and shapes will be as shown on the
plans and shall conform
to the requirements of Item 442, "Metal for
Structures", except for measurement and payment.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Strengthening Overhead Sign Support
Structures" |
EA |
REFERENCE ITEMS
(441, 442)
Go to Top
6017 - REMOVE AND INSTALL EXISTING SIGN PANELS
(OVERHEAD)
SPECIFICATION REQUIREMENTS
1) The locations for removal and installation of Existing Overhead Sign Panels
shall be in conformance
to the lines, grade, details and dimensions as shown on the
plans.
2) Existing sign panel materials shall be reused as shown on the plans.
3) Items to be retained by the State shall be stockpiled within the project
limits as directed by the
Engineer or at a location designated on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Remove and Install Existing Sign Panels
(Overhead)" |
EA |
REFERENCE ITEMS
(634, 636, 642, 654)
Go to Top
6018 - HORIZONTAL SIGN
LIGHT
SPECIFICATION REQUIREMENTS
1) The locations for Horizontal Sign Lights shall be as shown on the plans.
2) Horizontal sign light shall be fabricated and installed in accordance with
the details and dimensions
shown on the plans or as approved by the Engineer.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the various bid items.
REFERENCE ITEMS
(616)
Go to Top
6019 - INTERNALLY LIGHTED STREET NAME
SIGNS
SPECIFICATION REQUIREMENTS
1) The locations for Internally Lighted Street Name Signs shall be as shown on
the plans.
2) Signs and sign messages shall conform to the dimensions and details shown on
the plans. Signs
shall have single side message or double side message as
shown on the plans. Unless otherwise
shown on the plans or required in this specification, all
fasteners and screws in or on the fixture
shall be stainless steel Type 302 or 305, brass or aluminum.
Clamp on street name sign mast arms,
when required, shall be in accordance with the details shown
on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Internally Lighted Street Name Signs (Size and Type
Specified)" |
EA |
REFERENCE ITEMS
None
Go to Top
6021 - TESTING, TRAINING, DOCUMENTATION AND
WARRANTY
SPECIFICATION REQUIREMENTS
1) When needed, Testing, Training, Documentation and Warranty will be as
directed by the Engineer.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the various bid items.
REFERENCE ITEMS
None
Go to Top
6022 - SURVEILLANCE SYSTEM LOOP
DETECTORS
SPECIFICATION REQUIREMENTS
1) The locations for Surveillance System Loop Detectors shall be as shown on the
plans.
2) Pavement cuts shall be made to a depth of 50 millimeters unless otherwise
shown on the plans
or directed by the Engineer.
3) Unless otherwise shown on the plans, splices of detector leads to lead-in
cable shall be made only
in the ground box or station ground box adjacent to the
detector loop location. The size and location
of each detector loop shall be as shown on the plans, unless
otherwise directed by the Engineer.
The wire configuration and number of
turns for each detector loop shall conform to the manufacturers
recommendation unless otherwise shown on the plans. Terminals
back panel receiving system loop
detector lead-ins shall be labeled according to the format shown on
the plans, unless otherwise directed
by the Engineer.
4) Cable placement in parallel conduit shall be as shown on the plans or as
directed by the Engineer.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Detector Loop
(Size Specified)" |
EA |
REFERENCE ITEMS
(684, 688)
Go to Top
6024 - DIGITAL CARD RACK DETECTOR ASSEMBLY (8 SLOT
RACK)
SPECIFICATION REQUIREMENTS
1) The locations for Digital Card Rack Detector Assembly shall be as shown on
the plans and
as detailed in the Special Specifications.
2) Loop detector units provided under this item shall meet or exceed the
requirements of
NEMA TS-1, unless otherwise specified in this specification.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Detector Unit" |
EA |
2) |
"Detector Card Rack (8 Slot)" |
EA |
3) |
"Power Supply" |
EA |
REFERENCE ITEMS
None
Go to Top
6025 - REFLECTORIZED PROFILE PAVEMENT MARKINGS
SPECIFICATION REQUIREMENTS
1) The locations for Reflectorized Profile Pavement Markings shall be of the
type, color, shape, size,
width and thickness shown on the plans.
2) Traffic Control shall be as shown on the plans or as approved by the Engineer
in Writing.
3) Guides to mark the lateral location of pavement markings shall be established
as shown on the plans
or as directed by the Engineer. Unless otherwise shown on the
plans, pavement markings may be a
applied by any method that will yield markings meeting the
requirements of this specification.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Reflectorized Profile Pavement Markings |
|
|
(Type, Color, Shape, Size, Width Specified)" |
M |
REFERENCE ITEMS
(666, 678)
Go to Top
6056 - PORTABLE CHANGEABLE MESSAGE
SIGN
SPECIFICATION REQUIREMENTS
1) The locations for Portable Changeable Message Signs shall be as indicated
under the provisions
for traffic handling provided in the contract, as shown on
the plan details, or as directed by the Engineer.
2) The sign control circuitry shall provide for the permanent storage of a
minimum of 15
pre-programmed messages, the text of which shall be shown on
the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Portable Changeable Message Sign (Type Specified)" |
DAY |
REFERENCE ITEMS
None
Go to Top
6058 - COMMUNICATION
CABLE
SPECIFICATION REQUIREMENTS
1) The locations for Communication Cable shall be as shown on the plans.
2) The Contractor is responsible for installing at least the number of pairs of
wires shown on the plans.
The Contractor will not be compensated for any pairs of wires
over the number shown on the plans.
3) If specified in the plans, plug-in telephone hand sets shall be provided for
use in communicating
between the central master controller and the intersection
controllers.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Communication Cable (Type and
Size Specified)" |
M |
REFERENCE ITEMS
(625)
Go to Top
6065 - CLOSED LOOP TRAFFIC SIGNAL SYSTEM
SPECIFICATION REQUIREMENTS
1) The locations for the Closed Loop System shall be as shown on the plans.
2) The location for the Central Control will be shown on the plans.
OPTIONAL REQUIREMENTS
None
DESCRIPTION AND PAYMENT |
Subsidiary to the various bid items. |
REFERENCE ITEMS
None
Go to Top
6298 - 300 MM LED TRAFFIC SIGNAL LAMP UNIT
SPECIFICATION REQUIREMENTS
1) 300 MM Lamp Units will be placed at the locations shown on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"300 MM LED Traffic Signal Lamp Unit (Color and Type
Specified)" |
M |
REFERENCE ITEMS
None
Go to Top
6449 - PREFABRICATED PAVEMENT MARKINGS WITH
WARRANTY
SPECIFICATION REQUIREMENTS
1) The locations for Prefabricated Pavement Markings shall be as shown on the
plans.
2) Pavement markings shall be in accordance with the color (daytime and
nighttime reflected), length,
width, shape, and configuration shown on the plans. The
alignment and location shall be as shown
on the plans or as directed by the Engineer.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Pavement Markings with Warranty (Type,
Color, Shape, Size Specified)" |
M |
REFERENCE ITEMS
(677)
Go to Top
6535 - ELECTRIC
COMPONENTS
SPECIFICATION REQUIREMENTS
1) The locations for Electronic Components shall be as shown on the plans.
OPTIONAL REQUIREMENTS
None
MEASUREMENT AND PAYMENT
Subsidiary to the various bid items.
REFERENCE ITEMS
None
Go to Top
6554 - LED PEDESTRIAN SIGNAL LAMP UNIT
(SYMBOLIC)
SPECIFICATION REQUIREMENTS
1) The locations for LED Pedestrian Signal Lamp Units shall be as shown on the
plans.
2) The color of the lamp unit and whether it is a "Hand" (Dont
Walk) or "Walking Person" (Walk)
indication shall be as specified on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"LED Pedestrian Signal Lamp Unit (Symbolic)
(Type Specified)" |
EA |
REFERENCE ITEMS
None
Go to Top
6557 - SPREAD SPECTRUM RADIO FOR TRAFFIC
SIGNALS
SPECIFICATION REQUIREMENTS
1) The locations for spread Spectrum Radio shall be as shown on the plans.
2) Radio Antenna shall consist of furnishing spread spectrum radio antennas,
drop cable, connectors
and mounting hardware. This shall include all materials,
labor and procedures required to completely
install in place as shown on the plans.
3) Cable shall be installed as shown on the plans.
OPTIONAL REQUIREMENTS
None
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Spread Spectrum Radio (Type Specified)" |
EA |
2) |
"Antenna (Type Specified)" |
EA |
3) |
"Coaxial" |
M |
4) |
"Heliax Cable" |
M |
REFERENCE ITEMS
None
Go to Top
6607 - PEDESTAL POLE
ASSEMBLIES
SPECIFICATION REQUIREMENTS
1) The locations for furnishing and installing Pedestal Pole Assemblies shall be
as shown on the plans.
2) All pedestal pole assemblies shall conform to the detailed drawings and
requirements shown on
the plans as to height, general design and finish.
OPTIONAL REQUIREMENTS
1) When painting is required by the plans, the pedestal pole shall receive
System II aluminum in
accordance with Item 446, "Cleaning, Paint and
Painting", unless otherwise shown on the plans.
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Pedestal Pole Assemblies" |
EA |
REFERENCE ITEMS
None
Go to Top
|