DIVISION II - SUBBASE AND BASE COURSES

Table Of Contents

204 Sprinkling
210 Rolling (Flat Wheel)
211 Rolling (Tamping)
212 Rolling (Heavy Tamping)
213 Rolling (Pneumatic Tire)
214 Rolling (Heavy Pneumatic Tire)
215 Rolling (Grid)
216 Rolling (Proof)
217 Rolling (Vibratory)
247 Flexible Base
251 Reworking Base Material
260 Lime Treatment for Materials used as Subgrade (Road Mixed)
262 Lime Treatment for Base Courses (Road Mixed)
263 Lime Treated Base (Plant Mixed)
264 Lime and Lime Slurry
265 Lime-fly Ash (LFA) Treatment for Materials used as Subgrade
266 Lime-fly Ash (LFA) Treatment for Base Courses (Road Mixed)
275 Portland Cement Treated Materials (Road Mixed)
276 Portland Cement Treated Base (Plant Mixed)

ITEM NO. TITLE AND REQUIREMENTS

204 - SPRINKLING

SPECIFICATION REQUIREMENTS
1) The rate of application can be shown on the plans or as directed by the Engineer.
2) Specify on plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Sprinkling (Base)" KL
2) "Sprinkling (Earthwork)" KL
3) "Sprinkling (Dust Control)" KL

REFERENCE ITEMS
None

Go to Top

210 - ROLLING (FLAT WHEEL)

SPECIFICATION REQUIREMENTS
1) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Flat Wheel)" H

REFERENCE ITEMS
None

Go to Top

211 - ROLLING (TAMPING)

SPECIFICATION REQUIREMENTS
1) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Tamping)" H

REFERENCE ITEMS
(212)

Go to Top

212 - ROLLING (HEAVY TAMPING)

SPECIFICATION REQUIREMENTS
1) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Heavy Tamping)" H

REFERENCE ITEMS
None

Go to Top

213 - ROLLING (PNEUMATIC TIRE)

SPECIFICATION REQUIREMENTS
1) Specify type of pneumatic tire roller to be used on the plans.
2) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Light Pneumatic Tire)" H
2) "Rolling (Medium Pneumatic Tire) (Type A)" H
3) "Rolling (Medium Pneumatic Tire) (Type B)" H

REFERENCE ITEMS
None

Go to Top

214 - ROLLING (HEAVY PNEUMATIC TIRE)

SPECIFICATION REQUIREMENTS
1) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Heavy Pneumatic Tire)" H

REFERENCE ITEMS
None

Go to Top

215 - ROLLING (GRID)

SPECIFICATION REQUIREMENTS
1) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Grid)" H

REFERENCE ITEMS
None

Go to Top

216 - ROLLING (PROOF)

SPECIFICATION REQUIREMENTS
None

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Proof)" H

REFERENCE ITEMS
None

Go to Top

217 - ROLLING (VIBRATORY)

SPECIFICATION REQUIREMENTS
1) Specify type of roller to be used on the plans.
2) For Type C roller, the static mass, vibratory drum width and drum surface configuration must
    be shown on the plans.
3) Specify on the plans if it is a pay Item.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Rolling (Vibratory) (Type Specified)" H

REFERENCE ITEMS
None

Go to Top

247 - FLEXIBLE BASE

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the typical section(s).
3) Must specify type and grade of flexible base on the plans.
4) Type D material requirements must be shown on the plans.
5) Grade 6 requirements must be shown on the plans.
6) Show the measurement Class on the plans.
7) Measurement Class 4 and 5 are plans quantity measurement Items.
8) Must specify the depth for measurement Class 5.

OPTIONAL REQUIREMENTS
1) When measurement Class 2 is required, it will be paid for in accordance with Item 520.
2) When proof rolling is required, it will be paid for in accordance with Item 216.
3) When lightweight aggregates are used, the wet ball mill requirements will not apply and the lightweight
    aggregate shall meet the Los Angeles Abrasion, Pressure Slaking and Freeze Thaw requirements of Item
    303, "Aggregate for Surface Treatment (Lightweight)".

PAYMENT DESCRIPTION UNITS
1) "Flexible Base (Complete in Place) (Type Specified) M3 (Class 1, 3 or 4),
(Grade Specified) (Measurement Class Specified) MGR (Class 2),
(Depth Specified for Measurement Class 5)" M2 (Class 5)
2) "Flexible Base (Roadway Delivery) (Type Specified) M3 (Class 1),
(Grade Specified) (Measurement Class Specified)" MGR (Class 2)
3) "Flexible Base (Stockpile Delivery) (Type Specified) M3 (Class 1, 3),
(Grade Specified) (Measurement Class Specified)" MGR (Class 2)

REFERENCE ITEMS
(204)

Go to Top

251 - REWORKING BASE MATERIAL

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width and depth must be shown on the typical section(s).
3) Specify type of work for reworking base material on the plans.
4) The type and grade of the new flexible base must be shown on the plans.  Furnishing and delivery of new
    base will be paid for as "Flexible Base (Roadway Delivery)" in accordance with subarticle 247.5.
5) Show type of compaction on the plans.
6) Measurement Class 2 and 5 are plans quantity measurement Items.

OPTIONAL REQUIREMENTS
1) When measurement Class 6 is required, it will be paid for in accordance with Item 520.
2) When proof rolling is required, it will be paid for in accordance with Item 216.
3) When new base is required, it shall be in accordance with Item 247.

PAYMENT DESCRIPTION UNITS
1) "Reworking Base Material (Type A) (Class 1 or 2) KM (Class 1),
(Scarified Depth) (Compaction Method)" M2 (Class 2)
2) "Reworking Base Material (Type B) (Class 1, 2 or 5) KM (Class 1),
(Scarified Depth) (Compaction Method)" M2 (Class 2),
M3 (Class 5)
3) "Reworking Base Material (Type C) (Class Specified) KM (Class 1),
(Scarified Depth) (Compaction Method)" M2 (Class 2),
M3 (Class 3, 4, 5)
MGR (Class 6)
4) "Reworking Base Material (Type D) (Class 1, 2 or 5) KM (Class 1),
(Scarified Depth) (Compaction Method)" M2 (Class 2),
M3 (Class 5)

REFERENCE ITEMS
(204)

Go to Top

260 - LIME TREATMENT FOR MATERIALS USED AS SUBGRADE (ROAD MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the typical section(s).
3) Specify the type or types of lime to be used on the plans.
4) The percentage by mass or kilograms per square meter of lime to be added must be shown on the plans.
5) Type of compaction must be specified on the plans.
6) The completed section will be moist cured or prevented from drying by the addition of an
    asphalt material.  This material will be of the type shown on the plans.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
1) "Lime (Type Specified)" MGR
2) "Lime Treated Subgrade (Ordinary Compaction) (Depth Specified)" M2
3) "Lime Treated Subgrade (Density Control) (Depth Specified)" M3

REFERENCE ITEMS
(132, 204, 264, 300, 520)

Go to Top

262 - LIME TREATMENT FOR BASE COURSES (ROAD MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the plans.
3) Specify the type or types of lime to be used on the plans.
4) The percentage by mass or kilograms per square meter of lime to be added must
    be shown on the plans.
5) Type of compaction must be specified on the plans.
6) The type and grade of the new flexible base must be shown on the plans.  Furnishing and delivery
    of new base will be paid for as "Flexible Base (Roadway Delivery)" in accordance with
    subarticle 247.5.
7) The completed section will be moist cured or prevented from drying by the addition of an
    asphalt material.  This material will be of the type shown on the plans.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
1) "Lime (Type Specified)" MGR
2) "Lime Treatment for Base Courses (Existing Base)
(Compaction Method) (Depth Specified)" M2
3) "Lime Treatment for Base Courses (New Base) (Compaction Method)
(Depth Specified)" M2
4) "Lime Treatment for Base Courses (New and Existing Base)
(Compaction Method) (Depth Specified)" M2

REFERENCE ITEMS
(204, 247, 260, 264, 300, 520)

Go to Top

263 - LIME TREATED BASE (PLANT MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the typical section(s).
3) The percentage by mass of lime to be added must be shown on the plans.
4) The type and grade of the new flexible base must be shown on the plans.
5) The completed section will be moist cured or prevented from drying by the addition of an
    asphalt material.  This material will be of the type shown on the plans.
6) This is a plans quantity measurement Item when the lime treated base is measured by the square
    meter of completed work or by the cubic meter in its completed and accepted final position.

OPTIONAL REQUIREMENTS
None

PAYMENT DESCRIPTION UNITS
1) "Lime Treated Base (Plant Mix) (Density Control)
(Depth Specified)" MGR, M2, M3

REFERENCE ITEMS
(204, 247, 264, 300, 340, 520)

Go to Top

264 - LIME AND LIME SLURRY

SPECIFICATION REQUIREMENTS
None

OPTIONAL REQUIREMENTS
None

PAYMENT AND MEASUREMENT
Lime will be measured and paid for in accordance with the governing specifications for the
items of construction in which lime is used.

REFERENCE ITEMS
None

Go to Top

265 - LIME-FLY ASH (LFA) TREATMENT FOR MATERIALS USED AS SUBGRADE

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the typical section(s).
3) Specify the type or types of lime to be used on the plans.
4) The percentages by mass or kilograms per square meter of lime and fly ash to be added must be
    shown on the plans.
5) Type of compaction must be specified on the plans.
6) The completed section will be moist cured or prevented from drying by the addition of an asphalt
     material.  This material will be of the type shown on the plans.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
1) "Lime (Type Specified)" MGR
2) "Fly Ash" MGR
3) "LFA Treated Subgrade (Compaction Method) (Depth Specified)" M2

REFERENCE ITEMS
(132, 204, 264, 300, 520)

Go to Top

266 - LIME-FLY ASH (LFA) TREATMENT FOR BASE COURSES (ROAD MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width, depth and number of courses must be shown on the typical section(s).
3) Specify the type or types of lime to be used on the plans.
4) The percentages by mass or kilograms per square meter of lime and fly ash to be added must be
    shown on the plans.
5) Type of compaction must be specified on the plans.
6) The type and grade of the new flexible base must be shown on the plans.  Furnishing and delivery of
    new base will be paid for as "Flexible Base (Roadway Delivery)" in accordance with subarticle 247.5.
7) The completed section will be moist cured or prevented from drying by the addition of an asphalt
    material.  This material will be of the type shown on the plans.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
1) "Lime (Type Specified)" MGR
2) "Fly Ash" MGR
3) "LFA Treatment for Base Courses (Existing Base)
(Compaction Method) (Depth Specified)" M2
4) "LFA Treatment for Base Courses (New Base) (Compaction Method)
(Depth Specified)" M2
5) "LFA Treatment for Base Courses (New and Existing Base)
(Compaction Method) (Depth Specified)" M2

REFERENCE ITEMS
(204, 247, 264, 265, 300)

Go to Top

275 - PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width and depth of courses must be shown on the typical section(s).
3) The strength must be shown on the plans.
4) When Strength N is specified, must show the minimum design compressive strength on the plans.
5) When Strength O is specified, must show the allowable cement content percentage on the plans.
6) Type of compaction must be specified on the plans.
7) The type and grade of the new flexible base must be shown on the plans.  Furnishing and delivery of
    new base will be paid for as "Flexible Base (Roadway Delivery)" in accordance with subarticle 247.5.
8) The completed section will be moist cured or prevented from drying by the addition of an asphalt
    material.  This material will be of the type shown on the plans.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
1) "Cement Treatment (Existing Material) (Strength Specified)
(Depth Specified) (Compaction Method)" M2
2) "Cement Treatment (New Base) (Strength Specified) (Depth Specified)
(Compaction Method)" M2
3) "Cement Treatment (Mixing Existing Material and New Base)
(Strength Specified) (Depth Specified) (Compaction Method)" M2
4) "Cement" MGR

REFERENCE ITEMS
(247, 300, 421, 520, 524)

Go to Top

276 - PORTLAND CEMENT TREATED BASE (PLANT MIXED)

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Width and depth of courses must be shown on the typical section(s).
3) The strength must be shown on the plans.
4) When Strength N is specified, must show the minimum design compressive strength on the plans.
5) When Strength O is specified, must show the allowable cement content percentage on the plans.
6) The type and grade of the new flexible base must be shown on the plans.  Furnishing and delivery of
    new base will be paid for as "Flexible Base (Roadway Delivery)" in accordance with subarticle 247.5.
7) The completed section will be moist cured or prevented from drying by the addition of an asphalt
    material.  This material will be of the type shown on the plans.
8) Measurement Class 4 and 5 are plans quantity measurement Items.

OPTIONAL REQUIREMENTS
1) When proof rolling is required, it will be paid for in accordance with Item 216.

PAYMENT DESCRIPTION UNITS
  1) "Cement Treated Base (Strength Specified)
(Flexible Base Type and Grade Specified)" M3 (Class 1)
  2) "Cement Treated Base (Strength Specified)
(Flexible Base Type and Grade Specified)" MGR (Class 2)
3a) "Flexible Base (Strength Specified) MGR (Class 3)
(Flexible Base Type and Grade Specified)"
  b) "Cement" MGR (Class 3)
4a) "Flexible Base (Strength Specified) (Flexible Base Type and
Grade Specified) (Depth Specified)" M2 (Class 4)
  b) "Cement" MGR (Class 4)
  5) "Cement Treated Base (Strength Specified)
(Flexible Base Type and Grade Specified) (Depth Specified)" M2 (Class 5)

REFERENCE ITEMS
(247, 300, 340, 421, 520, 524)