DIVISION I - EARTHWORK (Items 100 to 193)

Table of Contents

100 PREPARING RIGHT OF WAY
103 DISPOSAL OF WELLS
104 REMOVING CONCRETE
105 REMOVING STABILIZED BASE AND ASPHALT PAVEMENT
106 OBLITERATING ABANDONED ROAD
110 EXCAVATION
112 SUBGRADE WIDENING
132 EMBANKMENT
134 BACKFILLING PAVEMENT EDGES
150 BLADING
152 ROAD GRADER WORK
154 SCRAPER WORK
156 BULLDOZER WORK
158 SPECIALIZED EXCAVATION WORK
160 TOPSOIL
161 COMPOST
162 SODDING FOR EROSION CONTROL
164 SEEDING FOR EROSION CONTROL
166 FERTILIZER
168 VEGETATIVE WATERING
169 SOIL RETENTION BLANKER
170 IRRIGATION SYSTEM
180 WILDFLOWER SEEDING
192 LANDSCAPE PLANTING
193 LANDSCAPE ESTABLISHMENT

NO. TITLE AND REQUIREMENTS

100 - PREPARING RIGHT OF WAY

SPECIFICATION REQUIREMENTS
1) Limits must be shown on plans.
2) Trees, shrubs and other landscape features specified for preservation should be clearly shown on plans.
3) When removing trees is paid as a separate Pay Item, must specify the diameter of the trees being removed.
4) Wells shall be removed under the Item 103, “Disposal of Wells”.
5) Show on the plans when tree wound dressing is required.

PAYMENT DESCRIPTION UNITS
1) "Preparing Right of Way" AC, STA
2) "Preparing Right of Way (Trees) (Diameter Specified)" EA

REFERENCE ITEMS
(103)

Go to Top

103 - DISPOSAL OF WELLS

SPECIFICATION REQUIREMENTS
1) Location and type of well(s) must be shown on the plans.
2) Areas to be restored must be shown on the plans.

PAYMENT DESCRIPTION UNITS
1) "Disposal of Water Well" EA
2) "Disposal of Petroleum or Sulfur Well" EA

REFERENCE ITEMS
(100)

Go to Top

104 - REMOVING CONCRETE

SPECIFICATION REQUIREMENTS
1) Specify if you want to salvage the removed concrete.
2) Indicate if you will allow the use of explosives.
3) Limits and/or locations of removal must be shown on the plans.
4) Removal of monolithic curbs and/or dowelled concrete curbs on concrete pavements is considered part of the concrete pavement and will not be measured separately for payment.
5) This is a plans quantity measurement item.
6) Removal of stabilized base of asphaltic concrete will be paid for by the applicable bid items unless otherwise shown on the plans.
7) Removal of retaining wall footings will be subsidiary to this item.
8) Stockpile locations, maximum size, steel removal and other details must be specified when shown to be salvaged.
9) Show saw cut lines when required.

PAYMENT DESCRIPTION UNITS
1) "Removing Concrete (Type Specified)" LF, SY, CY

REFERENCE ITEMS
None

Go to Top

105 - REMOVING STABILIZED BASE AND ASPHALT PAVEMENT

SPECIFICATION REQUIREMENTS
1) Locations and depths must be shown on plans.
2) Stockpile locations must be shown on plans.
3) Placement of salvaged material in stockpiles will conform to the dimensions and requirements shown on plans.
4) This is no longer a plans quantity measurement item.  Square yard and cubic yard measurements will be established by the widths and depths shown in the plans and the lengths measured in the field.
5) When measuring by the square yard, the limits of measurement will be as shown on the plans.

PAYMENT DESCRIPTION UNITS
1) "Removing Stabilized Base and Asphalt Pavement" STA, SY, CY

REFERENCE ITEMS
None

Go to Top

106 - OBLITERATING ABANDONED ROAD

SPECIFICATION REQUIREMENTS
1) Limits must be shown on plans.
2) Removal of abandoned structures will be considered subsidiary to this item, unless otherwise shown on the plans.
3) Removal of any asphaltic material will be paid for in conformance with applicable bid items and can be stockpiled at locations shown on the plans or as directed by the Engineer.

PAYMENT DESCRIPTION UNITS
1) "Obliterating Abandoned Road" STA

REFERENCE ITEMS
None

Go to Top

110 - EXCAVATION

SPECIFICATION REQUIREMENTS
1) This is a plans quantity measurement item.
2)  Excavation Roadway, channel and/or special excavation areas must be shown on plans.
3) Backfill areas of retaining walls will not be measured for payment.  Limits of measurement for excavation in retaining wall areas will be as shown on the following Statewide Standard Details Sheet as shown on the plans.
4) Shrinkage or swelling factors will not be considered in determining the calculated quantities.
5) Compaction method must be shown on plans if Item 132 is not used as a pay Item.

PAYMENT DESCRIPTION UNITS
1) "Excavation (Roadway)" CY
2) "Excavation (Channel)" CY
3) "Excavation (Special)" CY
4) "Excavation (Roadway and Channel)" CY

REFERENCE ITEMS
(132)

Go to Top

112 - SUBGRADE WIDENING

SPECIFICATION REQUIREMENTS
1) This is a plans quantity measurement item.
2) Limits must be shown on the plans.
3) Show areas to be widened on the typical section(s).
4) Type of compaction must be specified on the plans.
5) Additional embankment needed to build the section other than that generated from widening operations should be shown as a separate bid Item.

PAYMENT DESCRIPTION UNITS
1) "Subgrade Widening (Ordinary Compaction)" STA
2) "Subgrade Widening (Density Control)" STA

REFERENCE ITEMS
(132), (204)

Go to Top

132 - EMBANKMENT

SPECIFICATION REQUIREMENTS
1) Embankment areas must be shown on plans.
2) Shrinkage or swelling factors will not be considered in determining the calculated quantities.
3) Backfill areas of retaining walls embankment will be measured for payment, unless otherwise shown on the plans.  Limits of measurement for embankment in retaining wall areas will be as shown on the following Statewide Standard Details Sheet as shown on the plans.
4) Type of Material must be shown on plans.  For Type C,  material meeting the specification requirements shown on the plans.  For Type D, material from required excavation areas shown on the plans.
5) Compaction method must be shown on plans.

PAYMENT DESCRIPTION UNITS
1) “Embankment (Final) (Ordinary Compaction) (Type Specified)” CY
2) “Embankment (Final) (Density Control) (Type Specified)”  CY
3) “Embankment (Original) (Ordinary Compaction) (Type Specified)”  CY
4) “Embankment (Original) (Density Control) (Type Specified)”  CY
5) “Embankment (Vehicle) (Ordinary Compaction) (Type Specified)”    CY
6) “Embankment (Vehicle) (Density Control) (Type Specified)”    CY

REFERENCE ITEMS
(100), (204), (210), (216), (400)

Go to Top

134 - BACKFILLING PAVEMENT EDGES

SPECIFICATION REQUIREMENTS
1) Limits must be shown on the plans.
2) Show areas to be backfilled on typical section(s).
3)  Type A requirements must be shown on the plans.
4) When emulsified asphalt is to be applied, the rate of application and type must be shown on the plans.
5) When fertilizer is designated on the plans, the type of fertilizer analysis and rate of application must be shown on the plans.

PAYMENT DESCRIPTION UNITS
1) "Backfill (Type Specified)" STA

REFERENCE ITEMS
(Required)(168)
(Optional)
(162) When Type C backfill is specified on the plans.
(166) When fertilizer is specified on the plans.
(300) When emulsified asphalt is specified on the plans.
(314) When emulsified asphalt is specified on the plans.

Go to Top

150 - BLADING

SPECIFICATION REQUIREMENTS
1) Limits of work can be shown on plans or can be directed by the Engineer.

PAYMENT DESCRIPTION UNITS
1) "Blading" STA, HR

REFERENCE ITEMS
None

Go to Top

152 -ROAD GRADER WORK

SPECIFICATION REQUIREMENTS
1) Limits must be shown on plans.
2) Minimum length of “Road Grader Work” section is not less than five consecutive 100-foot stations, with exception of bridge replacement projects.
3) Type of compaction must be specified on plans.
4) If “Scraper Work” and/or “Bulldozer Work” is specified on the plans, this work will be paid for in accordance with those items, respectively.
5) When “Ordinary Compaction” is specified, “Sprinkling” and “Rolling” will not be paid for directly, but shall be considered as subsidiary work pertaining to this item, unless otherwise specified on the plans.
6) When “Density Control” is specified, “Sprinkling” and “Rolling” will not be paid for directly, but shall be considered as subsidiary work pertaining to this Item.

PAYMENT DESCRIPTION UNITS
1) "Road Grader Work (Ordinary Compaction)" STA,  SY
2) "Road Grader Work (Density Control)" STA,  SY

REFERENCE ITEMS
(110), (132), (150)

Go to Top

154 - SCRAPER WORK

SPECIFICATION REQUIREMENTS
1) Limits of work can be shown on plans or can be as directed by the Engineer.
2) Type of compaction must be specified on plans.
3) If “Blading” and/or “Road Grader Work” is specified on the plans this work will be paid for in accordance with those items, respectively.
4) When “Ordinary Compaction” is specified, “Sprinkling” and “Rolling” will not be paid for directly, but shall be considered as subsidiary work pertaining to this Item, unless otherwise specified on the plans.
5) When the “Density Control” is specified, “Sprinkling” and “Rolling” will not be paid for directly, but shall be considered as subsidiary work pertaining to this Item.

PAYMENT DESCRIPTION UNITS
1) "Scraper Work (Ordinary Compaction)" YH
2) "Scraper Work (Density Control)" YH

REFERENCE ITEMS
(132)

Go to Top

156 - BULLDOZER WORK

SPECIFICATION REQUIREMENTS
1) Limits of work can be shown on plans or can be as directed by the Engineer.
2) Specify type of bulldozer to be used on plans.
3) Type of compaction must be specified on plans, especially if not ordinary compaction.
4) If “Blading” and/or “Road Grader Work” is specified on the plans, this work will be paid for in accordance with those items, respectively.
5) “Sprinkling” and “Rolling” will not be paid for directly, but shall be considered as subsidiary work pertaining to this Item.

PAYMENT DESCRIPTION UNITS
1) "Bulldozer Work" HR

REFERENCE ITEMS
(132)

Go to Top

158 - SPECIALIZED EXCAVATION WORK

SPECIFICATION REQUIREMENTS
1) “Sprinkling” and “Rolling” will not be paid for directly, but will be subsidiary to this Item.
2) Locations/Limits of work can be shown on plans or can be as directed by the Engineer.
3) Ordinary Compaction, unless otherwise shown on the plans.
4) Specify type of equipment to be used on plans.
5) Specify measurement class on the plans.
6) Stockpile locations need to be specified on the plans.

PAYMENT DESCRIPTION UNITS
1) "Specialized Excavation Work (Equipment Type Specified)" HR
2) "Specialized Excavation Work (Original)" CY
3) "Specialized Excavation Work (Vehicle)" CY

REFERENCE ITEMS
(132)

Go to Top

160 - TOPSOIL

SPECIFICATION REQUIREMENTS
1) Location and depth of topsoil to be placed must be shown on the plans.
2) The approximately quantity and locations of the acceptable salvaged topsoil must be shown on the plans.
3) Designated areas for stockpile locations may be shown on the plans.

PAYMENT DESCRIPTION UNITS
1) "Furnishing and Placing Topsoil (Depth Specified)" STA, SY, CY 

REFERENCE ITEMS
None

Go to Top

161 - COMPOST

SPECIFICATION REQUIREMENTS
1) Specify type of compost to be used on plans (Compost Manufactured Topsoil, Erosion Control Compost, or General Use Compost).
2) Specify the type of Compost Manufactured Topsoil to be used on the plans (Blended On-site, Blended In-Place, or Pre-Blended).
3) Define the depth of material for Compost Manufactured Topsoil and General Use Compost.
4) Specify when rolling is required.

PAYMENT DESCRIPTION UNITS
1) “Compost Manufactured Topsoil (BOS)”    STA, SY, CY 
2) “Compost Manufactured Topsoil (BIP)”   STA, SY, CY
3) “Compost Manufactured Topsoil (PB)”  STA, SY, CY 
4) “Erosion Control Compost”  STA, SY, CY
5) “General Use Compost“   STA, SY, CY

REFERENCE ITEMS
(160)

Go to Top

162 - SODDING FOR EROSION CONTROL

SPECIFICATION REQUIREMENTS
1) Areas to receive sodding can be shown on plans or can be as directed by the Engineer.
2) Specify type of sodding to be used on plans.
3) The rate of application of water can be shown on plans or can be as directed by the Engineer and will be paid for in accordance with Item 168, unless otherwise specified on the plans.
4) Fertilizer must conform to Item 166.
5) Tracking methods may be specified on the plans.

PAYMENT DESCRIPTION UNIT
1) "Spot Sodding" SY
2) "Block Sodding" SY
3) "Straw or Hay Mulch" SY
4) "Mulch Sodding" SY, CY

REFERENCE ITEMS
(166), (168)

Go to Top

164 - SEEDING FOR EROSION CONTROL

SPECIFICATION REQUIREMENTS
1) Seeding will be distributed over the areas shown on the plans or where directed.
2) The rate of application of water can be shown on the plans or can be as directed and will be paid for in accordance with Item 168.
3) Fertilizer will be applied in accordance with Item 166 and be considered subsidiary to this Item.
4) Nonstandard seed and rates need to be shown on the plans.

PAYMENT DESCRIPTION UNITS
1) "Broadcast Seeding (Temporary) (Warm or Cool)" SY, AC
2) "Broadcast Seeding (Permanent) (Urban or Rural) (Clay or Sand)" SY, AC
3) "Cellulose Fiber Mulch Seeding (Temporary) (Warm or Cool)" SY, AC
4) "Cellulose Fiber Mulch Seeding (Permanent) (Urban or Rural) (Clay or Sand)" SY, AC
5) "Straw or Hay Mulch Seeding (Temporary) (Warm or Cool)" SY, AC
6) "Straw or Hay Mulch Seeding (Permanent) (Urban or Rural) (Clay or Sand)" SY, AC
7) "Drill Seeding (Temporary) (Warm or Cool)" SY, AC
8) "Drill Seeding (Permanent) (Urban or Rural) (Clay or Sand)" SY, AC
9) "Straw or Hay Mulching" SY, AC

REFERENCE ITEMS
(162), (166), (168)

Go to Top

166 - FERTILIZER

SPECIFICATION REQUIREMENTS
1) Areas to be fertilized must be shown on the plans.
2) Use a complete fertilizer containing nitrogen (N), phosphoric acid (P), and potash (K) nutrients, unless otherwise specified on the plans.  If you don’t default to the 100LBS/AC ENG, include the analysis and the rate of N on the plans.
3) Bid Item only when specified.

PAYMENT DESCRIPTION UNITS
1) "Fertilizer" TON, AC

REFERENCE ITEMS
None

Go to Top

168 - VEGETATIVE WATERING

SPECIFICATION REQUIREMENTS
1) Areas to be watered must be shown on plans or as directed by the Engineer.
2) The rate of application can be shown on plans or can be as directed by the Engineer.
PAYMENT DESCRIPTION UNITS
1) "Vegetative Watering" MG

REFERENCE ITEMS
None

Go to Top

169 - SOIL RETENTION BLANKETS

SPECIFICATION REQUIREMENTS
1) Areas of placement can be shown on the plans or as directed by the Engineer.

PAYMENT DESCRIPTION UNITS
1) "Soil Retention Blankets (Class Specified) (Type Specified)" SY

REFERENCE ITEMS
None

Go to Top

170 - IRRIGATION SYSTEM

SPECIFICATION REQUIREMENTS
1) Requirements for miscellaneous accessories must be shown on plans.
2) Limits and/or locations of work must be shown on plans.
3) Size of pipe and fittings as well as type/material of fittings must be shown on plans.
4) Location and details of sprinkler heads must be shown on plans.
5) All boring locations (if needed) must be shown on the plans.
6) When allowed on plans, all jetting operation locations must be shown.
7) Locations for pipe encasement (if needed) must be shown on plans.
8) Protection methods for excavations 5 feet or greater in depth will be paid for as required under “Trench Excavation Protection” or “Temporary Special Shoring”.
9) Electrical details must be shown on plans when greater then 100 volts.

PAYMENT DESCRIPTION UNITS
1) "Irrigation System" LS

REFERENCE ITEMS
(402), (403)

Go to Top

180 - WILDFLOWER SEEDING

SPECIFICATION REQUIREMENTS
1) Type of seed must be shown on the plans.
2) Rate of application of the seed must be shown on the plans.
3) If special equipment is required to sow the seed, it must be specified on the plans.
4) Seed will be sown in rates based on pure live seed (PLS) per acre as shown on the plans and will be distributed over the areas shown on the plans or as

PAYMENT DESCRIPTION UNITS
1) "Wildflower Seeding" AC

REFERENCE ITEMS
None

Go to Top

192 - LANDSCAPE PLANTING

SPECIFICATION REQUIREMENTS
1) Limits and locations of plants and related materials must be shown on the plans.
2) Plan types, size, root conditions, and additional plant requirements must be shown on the plans.
3) Follow the latest plant standards, unless otherwise shown on the plans.
4) Plants are to be nursery-grown, unless otherwise shown on the plans.
5) Backfill and plant soil mix options: 1) A soil mix must be specified on the plans. 2) Compost must conform to Item 161 and must be specified on the plans.  The default is existing soil from plant pits and beds.
6) Mulch other than organic types must be shown on the plans.
7) Fertilizer will conform to Article 166.2, “Materials”, unless otherwise shown on the plans and will be applied according to the plans.
8) Antitranspirants, tree trunk protection guards, and additional incidental materials and their requirements for landscape planting must be shown on the plans.
9) Plant pit depth must be shown on the plans or default to this specification.
10) Top of root ball grade after final settlement must be shown on the plans.
11) Plant basins other than the default in this specification must be shown on the plans.
12) Watering requirements other than the default in this specification must be shown on the plans.
13) Pruning requirements other than the default in this specification must be shown on the plans or directed.
14) Wound dressing for plants other than oaks (Quercus) species must be shown on the plans.
15) Staking, guying, and bracing supports must be shown on the plans.
16) Landscape edging must be shown on the plans.
17) Plant bed preparation must be shown on the plans.
18) Mulch depth requirements other than the default in this specification must be shown on the plans.
19) The maintenance work schedule and frequencies must be shown on the plans or default to this specification.

PAYMENT DESCRIPTION UNITS
1) "Plants (Type Specified) (Size Specified)" EA
2) "Mulch" SY, CY
3) "Plant Soil Mix" CY
4) Landscape Edge LF
5) Plant Bed Preparation SY
6) Vegetation Barrier SY

REFERENCE ITEMS
(161), (166)

Go to Top

193 - LANDSCAPE ESTABLISHMENT

SPECIFICATION REQUIREMENTS
1) Locations and/or areas for landscape establishment must be shown on the plans.
2) Pesticide types, including herbicides, can be shown on the plans or can be recommended by the Contractor.
3) The plans must show if herbicide applications will be required.
4) Type of fertilizer analysis, frequency and rate of application must be shown on the plans.
5) Areas to be mowed and trimmed, edged, mowing heights and mowing frequency must be shown on the plans.
6) Anticipated pruning should be shown on the plans.  Special pruning must be shown on the plans.
7) Plant supports will be of the type originally installed (if this Item follows Item 192), shown on the plans, or approved.
8) Bid Item Codes for replacement plants to be paid for must be included in the plans.  Include additional plant specifications (plant height, width, ….) and planting details in the plans.
9) Areas to be watered and rates of application must be shown on the plans when an irrigation system has not been installed.

PAYMENT DESCRIPTION UNITS
1) "Plant Maintenance" MO, CYC
2) "Plant Replacement (Plant Size Specified)" EA
3) "Plant Replacement (Plant Size and Type Specified)" EA
4) "Plant Replacement (Group[ Specified)" EA
5) "Vegetative Watering" MG
6) "Irrigation System Operation and Maintenance" MO

REFERENCE ITEMS
(166), (192)