DIVISION IV - STRUCTURES (Items 400 to 426)
Table of Contents
ITEM NO. - TITLE AND REQUIREMENTS
400 - EXCAVATION AND BACKFILL FOR STRUCTURES
SPECIFICATION REQUIREMENTS
1) Excavation
for structures shall conform to the lines and grades shown on the plans or as
directed by the Engineer.
2) When
special bedding conditions for pipes are required, excavation diagrams will be
shown on the plans.
3) When
existing pavement and base are to be cut and restored, the type and thickness of
the replaced materials will be as shown on the plans.
4) Bedding
will be in accordance with Class C bedding unless otherwise shown on the plans.
5) When
cement stabilized backfill is required, the excavation shall be backfilled with
cement stabilized backfill to the elevations shown on the plans and measured in
accordance with the excavation diagram shown on the plans.
6) The type
of aggregate used for cement stabilized backfill will be as shown on the plans
or as approved by the Engineer.
7) Structural
Excavation may be set up as either a pay item, or as subsidiary.
8) If Structural Excavation is a pay item, quantities for
structural excavation of culvert extensions greater than 15 feet and for all
other types of structures not listed in Article 400.5. will be shown on the
plans.
9) This is a
plans quantity measurement Item.
OPTIONAL REQUIREMENTS
1) When
flowable backfill is used, it will be measured and paid for as required under
Item 401, Flowable Backfill.
2) When
protection methods for excavation are greater than five (5) feet in depth, they
shall be measured and paid for as required under Item 402, "Trench
Excavation Protection" or Item 403, "Temporary Special Shoring".
3) When
used, concrete seal shall be placed in accordance with Item 420.
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Structural Excavation" |
CY |
2) |
"Structural Excavation (Bridge)" |
CY |
3) |
"Structural Excavation (Box)" |
CY |
4) |
"Structural Excavation (Pipes)" |
CY |
5) |
"Cement Stabilized Backfill" |
CY |
6) |
"Cutting and Restoring Pavement" |
SY |
REFERENCE ITEMS
(132), (401), (420), (421)
Go to Top
401 - FLOWABLE BACKFILL
SPECIFICATION REQUIREMENTS
1) Specify
the mix design type on plans.
2) Locations
and/or areas using flowable backfill must be shown on plans.
PAYMENT DESCRIPTION |
UNITS |
1) "Flowable Backfill" |
CY |
REFERENCE ITEMS
(421)
Go to Top
402 - TRENCH EXCAVATION PROTECTION
SPECIFICATION REQUIREMENTS
1) This Item
governs for the excavation protection required for trenches in excess of 5 feet
deep.
2) This Item
should be utilized for placement of storm drain and other buried, linear
structures.
3) Use Item
403 for walls, footings, and other more complex excavation protection.
4) Construction
methods are as required by OSHA's Standards and Interpretations.
PAYMENT DESCRIPTION |
UNITS |
1) "Trench Excavation Protection" |
LF |
REFERENCE ITEMS
None
Go to Top
403 - TEMPORARY SPECIAL SHORING
SPECIFICATION REQUIREMENTS
1) This
Item governs for the protection of excavations in excess of 5 feet deep.
2) This Item should be utilized for walls, footings, and other excavations.
3) Use Item 402 for storm drain and other buried linear structures.
4) The
plans will show a layout of the shoring, including top of shoring and the minimum protection grade
line.
5) The
contractor will submit details and design calculations to the Engineer prior to
construction.
PAYMENT DESCRIPTION |
UNITS |
1) "Temporary Special Shoring" |
SF |
REFERENCE ITEMS
(423)
Go to Top
404 - DRIVING PILING
SPECIFICATION REQUIREMENTS
1) Required
bearing resistance for piling must be shown on the plans.
2) Embankment
at bridge ends will be completed prior to driving of piling.
3) Test
piling locations and details for sizes must be shown on the plans.
OPTIONAL REQUIREMENTS
1) When
required by the plans, designated piling shall be driven and test-loaded in
accordance with Item 405, Foundation Test Load.
2) Piling
passing through the structural volume of retaining walls shall be subject to the
provisions of Item 423, Retaining Walls.
PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.
REFERENCE ITEMS
None
Go to Top
405 - FOUNDATION TEST LOAD
SPECIFICATION REQUIREMENTS
1) Piling
or drilled shafts to be test loaded will be specified on the plans.
2) The
Department will furnish jacking equipment, beams, and displacement indicators
unless otherwise specified.
OPTIONAL REQUIREMENTS
1) When
piling is used, it shall be in accordance with Item 407 (Steel Piling) or 409
(Concrete Piling).
2) When
drilled shafts are used, they shall be in accordance with Item 416.
PAYMENT DESCRIPTION |
UNITS |
1) "Foundation Test Load" |
EA |
REFERENCE ITEMS
Required
None
Optional
(404) When driving anchor and test piling is specified.
(416) When construction of anchor and test shafts is specified.
Go to Top
406 - TIMBER PILING
SPECIFICATION REQUIREMENTS
1) Size,
type, length, and details of the timber piling must be shown on the plans.
2) Splices
shall be made in accordance with the details shown on the plans.
PAYMENT DESCRIPTION |
UNITS |
1) "Treated Timber Piling" |
LF |
2) "Untreated Timber Piling" |
LF |
REFERENCE ITEMS
(404), (492)
Go to Top
407 - STEEL PILING
SPECIFICATION REQUIREMENTS
1) Type and
weight, locations, and lengths of steel piling must be shown on the plans.
2) Need
paint note in the General Notes and Specification Data if any painting done is
other than that called for in the standard specification.
OPTIONAL REQUIREMENTS
1) When test
loading is required, it will be in accordance with Item 405.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Steel H-Piling (Size and Weight)" |
LF |
2) |
"Steel H-Test Piling (Size and Weight)" |
LF |
3) |
"Sheet Piling (Type
Specified)" |
SF |
REFERENCE ITEMS
Required
(404), (441), (448)
Optional
(446) When Protection System III or IV painting of piling is required.
Go to Top
409 - PRESTRESSED CONCRETE PILING
SPECIFICATION REQUIREMENTS
1) Size, locations and lengths must be shown on the plans.
2) When test piling is required, locations must be shown on the plans.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Prestressed Concrete Piling
(Size Specified)" |
LF |
2) |
"Prestressed Concrete Test Piling
(Size Specified)" |
LF |
REFERENCE ITEMS
(404), (420), (421), (424), (425), (426), (440), (780)
Go to Top
416 - DRILLED SHAFT FOUNDATIONS
SPECIFICATION REQUIREMENTS
1) Details,
sizes, and dimensions must be shown on the plans.
2) When a
specific bearing is required, plans should indicate the expected depths and
elevations where satisfactory bearing materials will be encountered.
3) Size and
shape of bell footings must be shown on the plans, when required.
4) Unless
otherwise shown on the plans, drilled shafts may be constructed by the Slurry
Displacement Method.
5) The
quantity of concrete for bell footings must be shown on the plans and is a plans
quantity measurement Item.
OPTIONAL REQUIREMENTS
1) When test loading is required it will be in accordance with Item 405.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Drilled Shaft (Diameter
Specified)" |
LF |
2) |
"Drilled Shaft (Nonreinforced)
(Diameter Specified)" |
LF |
3) |
"Drilled Shaft (Sign Mounts) (Diameter
Specified)" |
LF |
4) |
"Drilled Shaft (High Mast Pole) (Diameter
Specified)" |
LF |
5) |
"Bell Footings" |
CY |
REFERENCE ITEMS
(420), (421), (440), (448)
Go to Top
420 - CONCRETE STRUCTURES
SPECIFICATION REQUIREMENTS
1) Class of
concrete for each type of structure or unit if not specified by pertinent
governing specifications must be shown on plans.
2) Dimensions
for expansion joint material or asphalt board material and joint types.
3) Class of
silicone joint sealant
4) Strength
requirements for staged application of post-tensioning
5) Location
of required or permissible construction joints.
6) Indicate
requirements for bonding agent (epoxy or grout) for placing concrete against
existing concrete.
7) Requirements
for re-vibration.
8) Quantities
for mass concrete and members designated as mass concrete.
9) Indicate
type of bridge deck overlay (asphalt or concrete)
OPTIONAL REQUIREMENTS
1) Mass
concrete may be designated on the plans.
2) Any
specific construction sequence requirements.
3) Placing
sequence, if required, for slabs on continuous steel units.
4) Construction
schedule restrictions different from those in the Item.
5) Rate of
concrete placement if different from that in the specifications.
6) Concrete
placing sequence.
7) Indicate
bearing pedestal reinforcing if different from the specifications
8) Indicate
type of membrane curing compound, if allowed.
9) Indicate
if mass concrete is a plans quantity item or measured in place
10)
Indicate
design strength requirements if different from the Specifications.
11) Waterstop
requirements that differ from the specs.
12)
Indicate
if TxDOT will perform testing for schedule restriction (Contractor-performed
testing is the default).
13)
Indicate
where welding of reinforcing supports is not allowed.
14)
Indicate
depth of holes for dowels if different from this Item.
15)
Indicate
if specific type of binding material (e.g., epoxy) is necessary.
16)
Indicate
if in-water placement will be allowed.
17)
Indicate
texture depth for finish if different from this Item, where a concrete overlay
will be placed on the slab.
18)
Indicate
if other structural elements not listed in Table 2 are to be a Plans
Quantity Item.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Class ___ Concrete
(Structure Type Specified)" |
CY, EA, SF, SY, LF |
2) |
"Class ___ Concrete
(Structure Type Specified) (Mass)" |
CY |
3) |
"Class S Concrete (Bridge Approach Slabs)" |
CY |
REFERENCE ITEMS
Required
(400), (421), (427), (438), (440), (448)
Optional
(404) When temporary piling are required to support shoring or falsework.
(426) When constructing post-tensioned structures.
(441) When construction steel structures.
Go to Top
421 - HYDRAULIC CEMENT CONCRETE (with
required SP 421---024)
SPECIFICATION REQUIREMENTS
1) The following will need to be shown
on the plans or require a plan note:
-
A coarse aggregate magnesium sulfate soundness
loss other than a maximum of 18% (optional)
-
If a value less than 1.0% will be used for the
maximum decantation for coarse aggregate (optional)
-
For all concrete subject to direct traffic if an
acid insoluble value less than 60% will be used (optional)
-
If blending of fine aggregates to meet the acid
insoluble requirement will not be allowed (optional)
-
If a sand equivalent of less than 80 will be used
(optional)
-
For Class K concrete if fineness modulus values
outside the range of 2.60 and 2.80 will be allowed (optional)
-
If mortar and grout will be used in the project
(required)
-
Strength requirements for concrete Classes F, H,
K, and HES if used (required)
-
Coarse aggregate grade for Class K and HES if
used (required)
-
If the responsibility of the contractor is waived
regarding furnishing and maintaining: (optional)
-
test molds
-
curing
facilities
-
maturity meters
if used,
-
wheelbarrow or
other container acceptable for the sampling of concrete
-
strength-testing equipment in accordance with the controlling
test (ie., compression machine or flexural beam breakers)
-
If the controlling strength test will not be
compressive (optional)
-
If the contractor will not be responsible for the
handling and transportation of test specimens and the cleaning of
molds, if needed (optional)
-
When sulfate resistant concrete is required
(required)
-
TxDOT plant/truck inspection/certification in
lieu of NRMCA/professional engineer certification for NON-STRUCTURAL
CONCRETE ONLY (optional)
-
To allow the use of volumetric mixers for
structural concrete (optional)
-
To designate the use of high performance concrete
classes: C(HPC), F(HPC), H(HPC), and S(HPC) (required)
-
Designate an alternate strength over-design
requirement other than what is in the specification only for Class
K, non-structural concrete and Class C concrete not used for bridge
class structures (optional)
-
Designate dosage rate of corrosion inhibiting
admixture if used (required)
-
To waive air entrainment requirements for all
concrete classes or individual concrete classes (already waived for
Class B and drilled shaft concrete) (optional refer to Bridge and
Pavement Design Manuals)
-
To alter target air contents
(currently set at 4.0% for pavements and 5.5% for structural
concrete) (optional)
PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.
REFERENCE ITEMS
None
Go to Top
422 - REINFORCED CONCRETE SLAB
SPECIFICATION REQUIREMENTS
1) The
design and details of the reinforced concrete slab will be as shown on plans.
2) Unless
otherwise noted, the Contractor has the option of using conventional forms,
permanent metal deck forms (PMDF) or prestressed precast concrete panels (PCP)
for forms for constructing a cast-in-place slab.
3) Reinforcing
steel to be epoxy coated will be shown on plans when required.
4) This is a
plans quantity measurement item.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Reinforced Concrete Slab" |
SF |
2) |
"Reinforced Concrete Slab (Extend Slab)" |
SF |
REFERENCE ITEMS
Required
(420), (421), (440)
Optional
(424) When prestressed precast concrete panels (PCP) are allowed.
(426) When prestressed units are used.
(430) When extending structures are shown.
Go to Top
423 - RETAINING WALLS
SPECIFICATION REQUIREMENTS
1) Type B
backfill will be used for permanent MSE walls unless otherwise shown on the
plans.
2) Temporary
walls should be designated as such on both the wall layouts and in the bid
codes.
3) If a
leveling pad embedment of greater than 1 foot is required, it should be clearly
required on the retaining wall layout, and the quantity of the wall should be
based on the increased embedment.
4) The
required surface finish for the walls should be called out in general notes, or
on a specific plan sheet.
5) This is a
plans quantity measurement Item.
6) Type of
wall will be shown on the plans.
7) If MSE or
Concrete Block walls are specified, the general notes should include a list of
approved systems.
8) If a wall
is subject to inundation, the wall layout should show the maximum water level or
100 year flood elevation. This will
set the limits of the Type D backfill.
9) When pipe
underdrains are required, they should be shown clearly on the wall layouts, and
will be in accordance with Item 556.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Retaining Wall (Type and/or Special Surface Finish
Specified)" |
SF |
REFERENCE ITEMS
Required
(110), (132), (400), (420), (421), (440), (445)
Optional
(424) When formed precast elements are required.
(458) When waterproofing is required.
(556) When pipe underdrains are required.
Go to Top
424 - PRECAST CONCRETE STRUCTURES (FABRICATION)
SPECIFICATION REQUIREMENTS
1) If shop drawings for nonstressed
members are desired, note accordingly on the plans.
2) Designate the class of concrete on
the plans.
3) If air entrained concrete is
necessary, note accordingly on the plans.
4) Note if any concrete performance
tests other than compressive strength cylinders (if not already included in a
special provision) are required. i.e.
concrete permeability.
5) Designate desired chamfers or radii
on the plans.
6) Designate any unique surface
finishes on the plans.
7) Note any finished product
tolerances that are not listed in this Item.
8) Reference Item 424 for fabrication
on wall panel plans if 424 is the preferred fabrication specification.
9) Note that an inspection laboratory
and laboratory equipment are required unless otherwise directed by the
Department.
10)
This is a plans quantity
measurement Item.
PAYMENT AND MEASUREMENT
Subsidiary to the various bid items in the contract.
REFERENCE ITEMS
(420), (421), (425), (426), (440), (504)
Go to Top
425 - PRECAST PRESTRESSED CONCRETE STRUCTURAL MEMBERS
SPECIFICATION REQUIREMENTS
1) Dimensions for panel bedding strips
will be shown on the plans
2) This is a plans quantity
measurement Item
3) Include the following in General Notes when Texas Girders are
used;
For bridges with Type Tx28, Tx34, Tx40, Tx46, Tx54, Tx62 and/or Tx70
prestressed concrete girders, the contractor can submit an alternate
design for approval using other TxDOT prestressed concrete girder shapes
. Alternate designs must be signed, sealed, and dated by a Licensed
Professional Engineer and submitted to the Engineer for review and
approval.
For alternate designs, use the same live load as
the original design and adhere to the current versions of the AASHTO
LRFD Bridge Design Specifications and the TxDOT LRFD Bridge Design
Manual.
Alternate bridge designs can differ from the
original design only by type of girder used. Do not raise the roadway
grade or lower the structure bottom chord elevation to accommodate the
alternate girders. No other change to the original design is allowed
except as necessary to accommodate the alternate girders. Substructure
re-design may be necessary to accommodate the alternate girders. No
additional compensation will be made for these alternate designs or for
any increase in quantities required to accommodate the alternate
designs, including quantities paid for under other Items.
PAYMENT DESCRIPTION |
UNITS |
1) |
"Prestress Concrete (Structural Component and Type or Size Specified)" |
LF, EA, SF, SY, CY |
REFERENCE ITEMS
Required
(420), (421), (424), (426), (427), (434), (440)
Optional
(442) When structural steel is required.
Go to Top
426 - PRESTRESSING
SPECIFICATION REQUIREMENTS
1) Class of concrete will be shown on
the plans.
2) Total tension will be shown on the
plans for pretensioning.
3) Post-tensioned tendons will be
grouted or ungrouted, as required by plans.
4) Concrete strengths for stressing
and staged loading of post-tensioned structural elements will be specified on
the plans.
5) Elastomeric bridge bearings will be
in accordance with Item 434, including measurement and payment.
6) This is a plans quantity
measurement Item.
OPTIONAL REQUIREMENTS
1) When precast units are allowed or
required, they will be in accordance with Item 424.
2) When joint sealants and fillers are
allowed or required, they will be in accordance with DMS-6310.
3) When structural steel is allowed or
required, it will be in accordance with Item 442.
4) Special requirements for vertical
grouting, when used, need to be included.
5) If testing is desired to more
accurately estimate friction losses for prestressing steel in ducts, specify an
in-place friction test.
6) For segmental construction, specify
duct connection pressure field test for internal tendons after erection
and before grouting.
7) If calculation adjustments for
elongation are required from an apparent modulus derived by testing, specify a
bench test.
8) When post-tensioning of precast
units is not measured and paid for as specified in Item 425, note it on the
plans.
|
PAYMENT DESCRIPTION |
UNITS |
1) |
"Post-tensioning (Grouted)" |
MKF |
2) |
"Post-tensioning (Ungrouted)" |
MKF |
REFERENCE ITEMS
Required
(420), (421), (434), (440), (442)
Optional
(445) When galvanized steel pipe is required