Over the course of the 18-month study period, February 2002 through
August 2003, numerous agency working group meetings and two public meetings
were held to inform the public of the progress of the route alternatives
development and evaluation. In addition, newsletters with current project
information and upcoming milestones were regularly sent to concerned
citizens and agencies. This web page will be periodically updated to inform
the public of the progress of the project.
Public Meetings
Two public meetings kept the public up-to-date on study progress and major
project decisions, and gathered concerns and comments from the public. This
web page was updated as meetings were held, information exchanged and
conclusions reached throughout the study process. A summary of each meeting
was provided.
The first public meeting was held on October 29, 2002 at the El Paso Police
Department’s Northeast Regional Command Center, 9600 Dyer Street. TxDOT
planners and engineers along with representatives of the consulting firm
were on hand from 5 – 8 PM to discuss the alternatives developed to date,
answer questions and obtain input on the significant project issues to be
considered in the corridor and design development process. Approximately 75
persons attended, and in general, the project was favorably received. There
was consensus among those present that the project was needed to reduce
congestion along IH 10. There was also strong and consistent opposition
expressed to Alternatives A and B, Loop 375/Martin Luther King, Jr. and
Greenbelt, respectively. These Alternatives were subsequently dropped from
further study.
A second public meeting was held on June 11, 2003, also at the Police
Department’s Northeast Regional Command Center, to present the results of
additional cost, environmental and technical studies that supported
selecting Alternative C – Railroad/Pipeline as the preferred alignment
alternative. Again, the consensus of the approximately 75 persons in
attendance was that Alternative C was acceptable, as was Alternative E. Some
concern was expressed about Alternative C’s impacts to sensitive natural
environments found in the foothills of the Franklin Mountains.
Working Group Meetings
Key to the development of route alternatives and their evaluation is the
early identification of corridor issues that will affect the location and
design of the proposed limited access highway. Federal, state and local
agencies and major private entities and groups are integral to this process,
and to that end, an agency working group was set up to provide oversight and
feedback to the study team at major milestones during the course of the
work. The working group consisted of representatives from the following
agencies and groups:
New Mexico Department of Transportation
City of El Paso
El Paso County
El Paso Metropolitan Planning Organization
Federal Highway Administration
Fort Bliss
US Dept. of the Interior- Bureau of Land Management
Doña Ana County
El Paso Water Utilities
El Paso Natural Gas
El Paso Electric
US Army Corps of Engineers
Texas Commission on Environmental Quality
1st Working Group Meeting- April 11, 2002
The first Working Group Meeting convened on April 11, 2002 in the offices of
the El Paso District of the Texas Department of Transportation to provide
federal, state and local agencies an overview of the project’s scope and to
obtain their input on the major alignment location issues. Representatives
from ten public entities, as well as some private individuals, attended.
Among the agencies consulted and present at the meeting included the city
and county of El Paso, Fort Bliss, the Bureau of Land Management (BLM), the
New Mexico Department of Transportation, El Paso Natural Gas (EPNG) and El
Paso Water Utilities (EPWU). Doña Ana County, NM was not represented, but a
subsequent meeting with its planning director obtained that county’s input.
Other meetings, both before and after the scoping meeting, with the BLM,
Fort Bliss, EPWU, EPNG and the City of El Paso provided additional focus on
the issues important to each.
In general, consultations with these agencies produced agreement on the
purpose and need for the project. A number of agency-specific issues were
raised that had to be addressed in the alignment development phase, but none
of the issues was of a magnitude that would preclude continued project
development of concept alignments. These issues were summarized in the
Issues Summary Report, dated May 2002.
2nd Working Group Meeting- August 28, 2002
A second working group meeting presented the results of the traffic analyses
justifying the need for action and the inadequacies of TSM improvements in
addressing the project need, the evaluation criteria used to rate each of
the alignment alternatives and the five route alternatives that addressed
the location opportunities and constraints identified at the first working
group meeting and in subsequent agency meetings and discussions.
3rd Working Group Meeting- April 24, 2003
A third working group meeting presented the results of additional cost,
traffic and environmental studies that supported a recommendation for
selecting Alternative C – Railroad/Pipeline as the preferred alternative.
There was also a presentation of alternative financing mechanisms given the
State’s current limited financial resources.
Project Newsletters
As part of its public involvement and information program, TxDOT prepared
newsletters at key points in the study process. Information on schedule,
upcoming meetings, alternatives under consideration and other important
project information was presented. The first newsletter provided information
on the preliminary alignment alternatives under consideration and was mailed
to interested citizens, public officials and agencies in mid-October, 2002.
A second newsletter, mailed to area residents in mid April, 2003, identified
the reasons for recommending Alternative C as the preferred route location
alternative. If you would like to receive project newsletters, contact the
TxDOT individual listed below.
Feedback
Public input is essential to project success. Therefore, comments or
questions on the study process or the route alternatives under study are
welcome and should be directed to Ms. Marty Boyd, E.I.T., Project Manager,
(915) 790-4326, mboyd@dot.state.tx.us,
or Mr. Jack Lord, AICP, Deputy Project Manager, (915) 790-4329,
jlord@dot.state.tx.us, at the El
Paso District Office of TxDOT, 13301 Gateway Blvd. West, El Paso, TX 79928.