 |
Northeast Parkway Route Location Study
El Paso, Texas |
Project Description | Study Area Maps
| Public Involvement |
Newsletters | Schematic Design/Environmental Assessment
PROJECT DESCRIPTION
Introduction/Project Overview
The Texas Department of Transportation (TxDOT), in cooperation with the
New Mexico Department of Transportation, conducted a route location study
for a limited access highway connecting Loop 375 in northeast El Paso near
Railroad Drive to Interstate Highway 10 (IH 10) in Anthony, NM. The project
examined the feasibility of establishing an alternative route to the
congested IH 10 corridor through El Paso for through truck and other
traffic. IH 10 congestion is a function of the unique political and
mountainous physical geography of the El Paso area that effectively channels
all interstate traffic through the center of El Paso on IH 10. An
alternative cross-mountain route entails steep grades that preclude its use
on a regular basis by truck and through traffic. As a result, there is
frequent severe congestion on IH 10 with no possibility for alternative
routing of through truck and auto traffic and hazardous cargoes.
The El Paso District of TxDOT contracted with Jacobs Civil Inc. of Dallas,
TX to prepare studies and consult with affected federal, state and local
agencies to determine an optimal alignment for a limited access, divided
bypass facility. This facility would link IH 10 at the NM 404/IH10
interchange just north of the Texas/New Mexico border to Loop 375 near the
Railroad Drive overpass. In this effort Jacobs was assisted by Moreno
Cardenas, Inc. of El Paso and PBS&J of Austin.
Study Purpose
The purpose of the study was to determine a feasible location for a
limited access, divided roadway for commercial and other IH 10 through
traffic, allowing this traffic to bypass the congested center of El Paso.
The map shows the approximate limits of the study corridor.
NORTHEAST PARKWAY STUDY CORRIDOR MAP
Project Schedule
The route location study began in February 2002 and concluded in August,
2003. Traffic studies justifying project need, information gathering for a
project geographic information system, agency discussions, three work group
coordination meetings and two public meetings were major work elements.
Significant agency and public concerns were noted and reflected in the route
location alternatives developed.
Analysis of Alternatives
The Plan
Initially, the route location study identified seven alternatives,
including No-Build and Transportation System Management (TSM) options. TSM
approaches to congestion mitigation improve traffic flow through better
management of existing facilities without adding to roadway capacity.
Typical TSM strategies include intersection and signalization improvements
on arterial streets and bottleneck removal programs to alleviate traffic
congestion on a freeway system. Following public and agency input and an
analysis of environmental, cost and technical constraints and opportunities,
the number of alternatives was narrowed to three. Finally, additional
studies and public input yielded a preferred alternative . This preferred
alternative constitutes the basis for more detailed design and environmental
impact documentation in the next phase of project development.
Technical Studies
The first step in the analysis was an assessment of the ability of the
regional roadway system to accommodate projected 2025 traffic volumes
without the Northeast Parkway in place. The traffic analysis prepared for
this No-Build condition used the El Paso Metropolitan Planning
Organization’s 2025 traffic model and concluded that IH 10 and US 54, among
other regional freeways, would experience severe traffic congestion (Level
of Service F) in the 2025 design year. Additional analysis of relatively
simple, cost-effective TSM improvements to reduce congestion yielded only
minimal congestion relief. IH 10 and US 54 still operated at a failing (F)
Level of Service. Therefore, study of additional roadway capacity on new
rights-of-way was warranted.
The Preliminary Concept Report identified five route location
alternatives, plus the No-Build and TSM options, for review and comment by
agencies and the public. The five potential routes addressed the project’s
purpose and need and reflected the results of agency discussions conducted
to date. As shown on the following map, they were:
- Alternative A – Loop 375/Martin Luther King, Jr.
- Alternative B – Greenbelt
- Alternative C – Railroad Pipeline
- Alternative D – 2025 MTP
- Alternative E – Stan Roberts, Sr.
Alternatives A and E used, to the extent possible, existing public (i.e.,
roads) rights-of-way, whereas Alternatives B, C and D were on new
alignments. Total right-of-way requirements varied from about 610 acres for
Alternative A to slightly more than 1,000 acres for Alternative E.
MAP OF PRELIMINARY CONCEPT
ALTERNATIVES
All alignment alternatives were located to minimize residential and
commercial displacements, respect major utility facilities and distribution
systems (e.g., El Paso Water Utilities, El Paso Natural Gas and El Paso
Electric) and avoid sensitive natural environmental systems, such as the
Bureau of Land Management’s Organ/Franklin Mountains Area of Critical
Environmental Concern. Alternatives A and B, the Loop 375/Martin Luther
King, Jr. and Greenbelt Alternatives, respectively, entailed potentially
significant residential and commercial displacements, as their alignments
were in close proximity to established neighborhoods. As a result, noise,
neighborhood disruption and other quality of life impacts would occur with
these alternatives. Alternative D, 2025 MTP, respected most corridor
location constraints, but impacted Fort Bliss’s Long Range Fan, and Fort
Bliss has indicated its opposition to these impacts. Alternatives C and E,
Railroad/Pipeline and Stan Roberts, Sr., respectively, avoided this impact
and did not appear to present any other associated significant issues.
The five route location alternatives, plus the No-Build and TSM options,
were discussed with the public at a meeting on October 29, 2002.
Approximately 75 people, including representatives of local, state and
federal agencies and area elected officials, attended. The consensus of
those present was that Alternatives A and B entailed potentially significant
and unacceptable impacts. Continuing agency consultation, traffic analyses
and technical studies have confirmed this conclusion with respect to the
identified evaluation measures – cost, environmental/socioeconomic, traffic,
and public acceptance. Three alternatives:
Alternative C – Railroad/Pipeline
Alternative D – 2025 MTP
Alternative E – Stan Roberts, Sr.
appeared to offer the most traffic benefit for the least environmental
and dollar cost. Accordingly, TxDOT dropped Alternatives A and B from
further analysis and directed the consultant to perform additional traffic,
environmental and design studies only on Alternatives C, D and E.
The No-Build and TSM Alternatives were carried forward for comparison with
the three route location alternatives.
In terms of traffic operations, Northeast Parkway will operate at an
acceptable level of service under all alternatives. All alternatives,
however, highlight the existing capacity constraints on Loop 375 between IH
10 and Northeast Parkway (south and east of the study area). Alternative E
will have the least negative impact on the section of Loop 375 east of
Northeast Parkway, because it attracts less traffic than Alternatives C and
D. Alternatives C and D will have more negative impact on Loop 375, but
offer more benefit to the total system by reducing vehicle miles of travel (VMT)
on other regional arterials (including IH 10).
All revised preliminary concept alternatives minimized residential and
commercial displacements, respected major utility facilities and
distribution systems (e.g., El Paso Water Utilities, El Paso Natural Gas and
El Paso Electric) and avoided sensitive natural environmental systems, such
as the Bureau of Land Management’s Organ/Franklin Mountains Area of Critical
Environmental Concern. All three route alternatives entailed similar
environmental impacts. Alternative D, 2025 MTP, respected most corridor
location constraints, but impacted Fort Bliss’s Long Range Fan to the extent
that it would need to be relocated. Alternatives C and E, Railroad/Pipeline
and Stan Roberts, Sr., respectively, avoided this impact, but Alternative E,
because it entailed frontage road construction along Stan Roberts, Sr. Ave.
and Martin Luther King Jr., Blvd., may disrupt adjoining land uses. There
did not appear to be any other significant natural or human environmental
issues. The studies supporting these conclusions were presented in the
Revised Preliminary Concept Report (December 2002).
Subsequent cost, technical and environmental studies indicated that
Alternative C – Railroad/Pipeline offered the most traffic benefit at the
least dollar and environmental cost. This conclusion was detailed in the
draft Final Concept Report (March, 2003), discussed with federal,
state and local agency representatives at the 3rd Working Group Meeting in
April, 2003 and presented to the public at a second meeting in June, 2003.
As no major opposition was expressed at any working group or public meeting,
the Final Concept Report (August, 2003) confirmed the conclusion that
Alternative C was the preferred alignment option. It was recognized,
however, that detailed environmental and technical studies to be performed
during the schematic/environmental phase of project development might alter
alignments slightly or suggest the mixing and matching of segments of one
alignment with those of another.
MAP OF REVISED ALTERNATIVES C, D AND E
(FINAL CONCEPT ALTERNATIVES)
Order-of-magnitude costs for each of the preliminary concept
alternatives, plus the TSM improvement option, are presented in Table
S-1. Preliminary summary ratings for each of the alternatives on
each of the evaluation criteria are presented in Table S-2.
|
Table S-1 |
|
Preliminary Cost Summary |
|
TSM Improvements and Concept Alignments |
|
Alignment |
New Mexico |
Texas |
Total |
| TSM |
$1,614,000 |
$5,876,000 |
$7,490,000 |
| C - Railroad/Pipeline |
$86,053,000 |
$129,339,000 |
$215,393,000 |
| D – 2025 MTP |
$86,053,000 |
$131,911,000 |
$217,965,000 |
| E - Stan Roberts, Sr. |
$93,679,000 |
$138,697,000 |
$232,376,000 |
|
| |
|
Table S-2
Northeast Parkway Route Location Study
El Paso, TX – Dona Ana County, NM
Route Alternative Ratings |
| |
|
|
Alternatives |
|
Criterion |
C
RR/P’line
|
D
2025
MTP
|
E
S.Roberts
|
No Build |
TSM |
|
Social/Economic/Environmental |
|
|
|
|
|
|
1- Res/Com
Displacements |
0 |
0 |
0 |
+ |
+ |
|
2-
Utilities/Distribution Systems |
0 |
0 |
+ |
++ |
+ |
|
3-
Environmentally Sensitive Areas |
0 |
0 |
+ |
++ |
++ |
|
4-
Consistency with El Paso Plan |
++ |
+ |
+ |
0 |
0 |
|
5- Cultural
Resources |
- |
- |
0 |
++ |
++ |
|
6- Changes in
Accessibility |
++ |
++ |
+ |
-- |
- |
|
|
0 |
0 |
- |
- |
- |
|
Design |
|
|
|
|
|
|
8-
Constructability |
0 |
0 |
- |
++ |
+ |
|
9- Cost |
0 |
0 |
- |
-- |
-- |
|
Traffic Operations |
|
|
|
|
|
|
10- Reduction
in VMT1 |
+ |
+ |
- |
-- |
-- |
|
11- VMC2 |
+ |
+ |
++ |
0 |
0 |
|
12- Travel
Time Savings |
+ |
+ |
- |
-- |
-- |
|
13-
Congestion (volume/capacity) |
++ |
++ |
- |
-- |
-- |
|
Public Involvement |
|
|
|
|
|
|
14- Public
Acceptance |
++ |
+ |
+ |
-- |
-- |
|
Key: |
1VMT
= Vehicle Miles of Travel |
|
++
Significantly Positive |
2 VMC = Vehicle Miles of
Capacity |
|
+
Positive |
|
0
Neutral |
|
-
Negative |
|
- -
Significantly Negative |
|
SUBSEQUENT PROJECT DEVELOPMENT TASKS
The next step in TxDOT’s project development process is the preparation of
the design schematic and environmental documentation. Some minor alignment
changes may be made to reflect site specific circumstances or because the
detailed design and environmental studies performed as part of the
environmental impact documentation process suggest that a slightly different
alignment may cause fewer environmental impacts. Alternatively, as noted
above, detailed studies may suggest that alignment segments in Texas and New
Mexico (e.g., Alt. E in NM and Alt. C in Tx) be switched to reflect better
knowledge of the corridor.
TxDOT is pursuing alternative funding mechanisms for this project. A
preliminary traffic and revenue study has been prepared concurrent with this
report’s preparation to explore the feasibility of constructing the
Northeast Parkway as a toll facility. Various tolling strategies have been
evaluated and are contained in an April, 2003 Preliminary Traffic and
Revenue Study prepared by URS Corporation.
|