TxDOT Expressway
Search:
   Home   |    Contact Us   |    Tools & Plug-Ins  
spacer
DOT Links©

spacer
spacer
Current Weather
69°F

Sunny
Humidity:17%
Dew Point:23°F
Wind:  From the Northwest at 12 mph gusting to 17 mph
Reported at Tyler, TX.  Last Updated on Friday Nov. 7, 2008 at 3:30 PM CST.
More Weather...
spacer spacer spacer
State Loop 49 sign logo State Loop 49 Project - Tyler, Texas

Photo Gallery

 
Phase I

click on photo to enlarge

 
click to enlarge Contractors are currently working to clear the area for Phase I Construction from SH 155, east to US 69. TxDOT worked meticulously with the United States Army Corps of Engineers (USACE) and the Texas Commission on Environmental Quality (TCEQ) on the appropriate environmental impact studies, wetland permits, and water quality certification, to ensure minimal effect to the surrounding area. - July 2003
   
click to enlarge View of work currently taking place on the east side of SH 155 just south of Tyler. The contractor has installed silt fences and the public can now see Loop 49 taking on a more defined outline. - August 2003
   
click to enlarge Workers are drilling the hole in which to place a drilled shaft, which are reinforced concrete foundations for the bridge pier. Each shaft is 48" in diameter and approximately 20’ in depth. This section will be connected to a reinforced concrete base (the footing) and both will be underground. - September 2003
   
click to enlarge Workers are pouring concrete into the form for a footing. - October 2003
   
click to enlarge This is the completed footing, a reinforced concrete base that sits atop the drilled shafts. This section will connect to and support the completed bridge pier. It will also be underground. - October 2003
   
click to enlarge Workers are constructing a box culvert on a lower level over which the service roads will be built. The service roads will run adjacent to Loop 49 connecting traffic from Henry Moore Road and FM 2493, as well as providing points of access to and from Loop 49. - October 2003
   
click to enlarge Setting up reinforced steel cages for columns at Henry Moore Road. This bridge of Loop 49 will extend over Henry Moore Road and FM 2493. These will be points of access. - November 2003
   

click to enlarge

Reinforced steel cage for the bridge column. - November 2003
   
click to enlarge A bridge abutment which bears the rose insignia. This rose is seen in various other locations throughout Smith County and will be seen from either direction by motorists traveling on Loop 49 (the rose inlay will later be painted) - November 2003
   
click to enlarge Putting the reusable column form in place for the bridge column. Concrete will then be poured inside to cure. - December 2003
   

click to enlarge

Removing the reusable column form. You can see the elastomeric form-liner on the inside, which gives the column the appearance of a brick inlay. (The brick will later be painted) - December 2003
   

click to enlarge

Making progress. At this point three columns have been formed (the one closest will soon have its form removed). The road below is Henry Miller Road and this shot is looking toward FM 2493. - December 2003
   
click to enlarge This picture was taken near Saline Creek where crews are working to build embankments. A bridge will be built over this area. - January 2004
   
click to enlarge This picture is taken from atop an embankment at Saline Creek. (The path to the side is temporary for workers to get through.) In time, there will be a bridge built straight out from where the photographer stands. - January 2004
   
click to enlarge This picture was taken at West Mud Creek. The structures are referred to as "bents" and will support a bridge across this winding creek. - January 2004
   
click to enlarge The west-end abutment for the bridge over FM 2493 and Henry Miller Road gets some finishing work to smooth out the appearance of the concrete. - January 2004
   
click to enlarge Bringing it up – This picture over Henry Miller Road shows great progress in construction. The second column has been fitted with the reusable cap form (rectangular rust-colored top). Concrete will be poured into the form to cure. This will be the first completed bridge pier, but soon each pier will have a cap and, together, they will support a bridge containing two travel lanes of Loop 49. - January 2004
   
click to enlarge Fabricating rebar for the caps. One of the contractors commented to the photographer that, in his 17 years of construction, this was the largest steel fabrication he’d ever worked with. - January 2004
   
 
spacer spacer
Disclaimer | Accessibility Policy | Privacy and Security Policy | Open Records | TxDOT Contacts