2004 English Special Provisions to Item 004 - Scope of Work (All)


2004 English Special Provisions by Item (All)
Specification Information
Search For a Special Provision or Specification

SP004-021  PDF  RTF   - For project 6262-18-001, 6262-50-001, 6262-53-001, 6264-64-001, 6278-99-001 in Bexar, Dallas, Harris, Travis, Walker Counties. Provides for two contract extensions. One-Time Use.
SP004-020  PDF  RTF   - Allows for multiyear maintenance contracts to be extended. Optional for all non-federal aid maintenance projects beginning with the February 2012 letting. (Change Memo: de-11-12). Statewide Use.
SP004-019  PDF  RTF   - Allow for one year maintenance contracts to be extended. Optional for all non-federal aid maintenance projects beginning with the February 2012 letting. (Change Memo: de-11-12). Statewide Use.
SP004-018  PDF  RTF   - For project 0914-00-301, 0914-00-314 in Travis County. States the contract consists of furnishing, installing, testing, and integrating components of a corridor traffic management (CTM) system for the freeway corridor One-Time Use.
SP004-017  PDF  RTF   - This revises Article 4.2. to include the use of Table 1 for all contracts and revises Article 4.4 to add the definition of ''issue'', the Project Pledge, and Issue Resolution Process. This Special Provision is required for all project beginning with the May 2010 letting. Replaces SP004-013 . (Change Memo: de-07-10). Statewide Use.
SP004-015  PDF  RTF   - For project 0015-13-317 in Travis County. For this project, Item 004, “Scope of Work”, of the Standard Specifications, is hereby amended with respect to the clauses cited below, and no other clauses or requirements of this Item are waived or changed hereby. One-Time Use.
SP004-014  PDF  RTF   - For project 6193-72-001, 6193-73-001, 6193-74-001, 6193-75-001, 6193-76-001, 6253-63-001, 6253-64-001, 6253-65-001, 6253-66-001, 6253-67-001 in Cameron, Harris, Jefferson, Nueces, Victoria Counties. The Department at its Sole Discretion may elect to perform like work with in-house forces or additional contract forces on 5 Callout Debris Removal and Disposal Contracts. One-Time Use.
SP004-013  PDF  RTF   - Clarifies the definition and requirements for reimbursement of project overhead. Required on all projects beginning with the May 2009 letting. May be used prior to May 2009 at the district's option. Replaces SP004-012 .Replaced by SP004-017 . (Change Memo: de-07-09). Statewide Use.
SP004-012  PDF  RTF   - Combines 004---010 with 004---011 and replaces them. Required on all projects beginning with the April 2008 letting. Replaces SP004-010 SP004-011 .Replaced by SP004-013 . (Change Memo: de-04-08). Statewide Use.
SP004-011  PDF  RTF   - Combines 004---008 with 004---009. This special provision voids and replaces 004---008 and 004---009. Required on all projects beginning with the March 2008 letting. Replaces SP004-008 SP004-009 .Replaced by SP004-012 . (Change Memo: de-03-08). Statewide Use.
SP004-010  PDF  RTF   - Supplements Section 4.4.B. Dispute or Claims Procedure. Required on all projects beginning with the April 2008 letting. Replaced by SP004-012 . (Change Memo: de-01-08). Statewide Use.
SP004-009  PDF  RTF   - Article 4.4.A., Delay Claims, Damages occur when impacts that are the responsibility of the department result in additional costs to the contractor that could not have been reasonably anticipated at the time of letting. Required on all projects beginning with the March 2008 letting. Replaced by SP004-011 . (Change Memo: de-29-07). Statewide Use.
SP004-008  PDF  RTF   - The Contractor is responsible for notifying the sureties of any changes to the contract as required in the bond language. Required on all projects beginning with the July 2007 letting. Replaced by SP004-011 . (Change Memo: de-09-07). Statewide Use.
SP004-007  PDF  RTF   - For project 0151-09-036 in Travis County. Integrating components of a corridor traffic management (CTM) system for the freeway corridor. One-Time Use.
SP004-006  PDF  RTF   - Assume responsibility for the collection of additional data pertaining to as-built project documentation in support of a Computerized Transportation Management System. Districtwide Use. Houston District.
SP004-005  PDF  RTF   - For project 0110-04-166 in Montgomery County. Assume responsibility for the collection of additional data pertaining to as-built project documentation in support of a Computerized Transportation Management System. One-Time Use.
SP004-004  PDF  RTF   - For project 0271-04-067 in Waller County. The Contractor is responsible for the collection of additional data pertaining to as-built project documentation in support of a Computerized Transportation Management System. One-Time Use.
SP004-003  PDF  RTF   - For project 0508-07-027 in Harris County. Provision needed to require collection of as-built data. One-Time Use.
SP004-002  PDF  RTF   - For project 0912-00-291 in Harris County. Requires collection of as-built data. One-Time Use.
SP004-001  PDF  RTF   - For project 0177-06-064 in Harris County. Assume responsibility for the collection of additional data pertaining to as-built project documentation in support of a Computerized Transportation Management System. One-Time Use.