2004 English Special Provisions by Item (All)
|
Specification Information
|
Search For a Special Provision or Specification
|
|
SP247-047 |
PDF |
RTF |
- For project 0052-02-033, 0920-02-087 in Bailey, Liberty Counties. Allows flexible Base (Roadway Delivery) to be measured by the ton, any cubic yard method, or by the square yard. Includes required SP 247-033.
One-Time Use.
|
SP247-046 |
PDF |
RTF |
- For project 1088-04-023, 2343-01-030, 3364-01-010 in Nueces County. Under Article 247.4. Construction, F. Ride Quality - The first sentence is replaced with: This section apples to the final travel lanes that receive only one lift of Hot Mix ACP, unless otherwise shown on the plans.
One-Time Use.
|
SP247-045 |
PDF |
RTF |
- For project 0706-03-022, 0706-04-018, 0895-01-014, 0926-06-015, 0937-02-029, 1677-01-015, 1879-01-022 in Houston, Nacogdoches, Shelby Counties. Revises Article 247.4 F. Ride Quality, second paragraph.
One-Time Use.
|
SP247-044 |
PDF |
RTF |
- This SP incorporates the requirements of SP 247-037 and adds a requirement for the contractor to perform Tex-1000-S and furnish the data collected to TxDOT.
Replaces SP247-037 . Districtwide Use. Atlanta District.
|
SP247-043 |
PDF |
RTF |
- For project 0610-06-076 in Bowie County. Adds provision requiring the contractor to perform Tex- 1000-S and furnish the data collected to TxDOT.
One-Time Use.
|
SP247-042 |
PDF |
RTF |
- For project 6197-67-001 in Walker County. Provides for the Department to supply the aggregates. Defines Measurement as by the SY of surface area in its final position.
One-Time Use.
|
SP247-041 |
PDF |
RTF |
- Adds ride quality with only one lift of Hot Mix ACP or a 1 or 2 course surface treatment for the final surface for quality control and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---041 contains the requirements of 247---033 and 247---026 and may be used in lieu of 247---033.
Districtwide Use. Pharr District.
|
SP247-040 |
PDF |
RTF |
- - Adds ride quality and lime treatment to flexible base and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---040 contains the requirements of 247---033 and 247---030 and may be used in lieu of 247---033.
Replaces SP247-030 . Statewide Use.
|
SP247-039 |
PDF |
RTF |
- - Adds ride quality and allows measurement for Flexible Base (Roadway Delivery) to include any cubic yard method and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---039 contains the requirements of 247---033 and 247---029 and may be used in lieu of 247---033.
Replaces SP247-029 . Statewide Use.
|
SP247-038 |
PDF |
RTF |
- Adds ride quality and cement treatment to flexible base and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---038 contains the requirements of 247---033 and 247---028 and may be used in lieu of 247---033.
Replaces SP247-028 . Statewide Use.
|
SP247-037 |
PDF |
RTF |
- Provides clarification on establishing target grading limits and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E.. SP 247---037 contains the requirements of 247---033 and 247---025 and may be used in lieu of 247---033
Replaces SP247-025 .Replaced by SP247-044 . Districtwide Use. Atlanta District.
|
SP247-036 |
PDF |
RTF |
- Measures ride quality of the base course after placement of the prime coat and before placement of the surface treatment and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---036 contains the requirements of 247---033 and 247---021 and may be used in lieu of 247---033.
Replaces SP247-021 . Statewide Use.
|
SP247-035 |
PDF |
RTF |
- For project 0569-01-048 in Cass County. Adds Grade 5 Flex base.
One-Time Use.
|
SP247-034 |
PDF |
RTF |
- For project 0369-03-027, 0369-03-028 in Uvalde County. Amend Articles 247.2 and 247.4.
One-Time Use.
|
SP247-033 |
PDF |
RTF |
- Adds Grade 5 allowing for a coarser gradation & requires a 3 psi lateral pressure strength requirement instead of a 0 psi lateral pressure strength requirement. Required on all projects using Item 247 beginning with the July 2009 letting.
Replaces SP247-020 . (Change Memo: de-15-09). Statewide Use.
|
SP247-032 |
PDF |
RTF |
- For project 0264-07-028 in Tom Green County. Provides for the use of grade 5 flexible base, it also includes the specification contents of 247-030, which adds ride quality, lime treatment to flexible base and provides for certain recycled materials.
One-Time Use.
|
SP247-031 |
PDF |
RTF |
- For project 0222-03-056 in Morris County. Adds grade 5 flexible base to Table 1, Material Requirements and incorporates previously approved
Atlanta District SP 247---025 which clarifies target grading requirements.
One-Time Use.
|
SP247-030 |
PDF |
RTF |
- VOID - DO NOT USE. Adds ride quality and lime treatment to flexible base and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---030 contains the requirements of 247---020 and 247---014 and may be used in lieu of 247---020.
Replaces SP247-014 .Replaced by SP247-040 . (Change Memo: de-10-07). Statewide Use.
|
SP247-029 |
PDF |
RTF |
- VOID - DO NOT USE. Adds ride quality and allows measurement for Flexible Base (Roadway Delivery) to include any cubic yard method and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---029 contains the requirements of 247---020 and 247---013 and may be used in lieu of 247---020.
Replaces SP247-013 .Replaced by SP247-039 . (Change Memo: de-10-07). Statewide Use.
|
SP247-028 |
PDF |
RTF |
- VOID - DO NOT USE. Adds ride quality and cement treatment to flexible base and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---028 contains the requirements of 247---020 and 247---012 and may be used in lieu of 247---020.
Replaces SP247-012 .Replaced by SP247-038 . (Change Memo: de-10-07). Statewide Use.
|
SP247-027 |
PDF |
RTF |
- For project 0211-09-028, 0334-08-031 in Andrews, Fayette Counties. Combines SW 247-020 and DW 247-013
One-Time Use.
|
SP247-026 |
PDF |
RTF |
- Adds ride quality with only one lift of Hot Mix ACP or a 1 or 2 course surface treatment for the final surface for quality control and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---026 contains the requirements of 247---020 and 247---016 and may be used in lieu of 247---020.
Replaces SP247-016 . Districtwide Use. Pharr District.
|
SP247-025 |
PDF |
RTF |
- VOID - DO NOT USE. Provides clarification on establishing target grading limits and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---025 contains the requirements of 247---020 and 247---001 and may be used in lieu of 247---020.
Replaces SP247-001 .Replaced by SP247-037 . Districtwide Use. Atlanta District.
|
SP247-024 |
PDF |
RTF |
- For project 0863-01-044 in Hidalgo County. Provide recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E.
One-Time Use.
|
SP247-023 |
PDF |
RTF |
- For project 0299-04-059 in Maverick County. Measure ride quality of the base course after placement of the prime coat and before placement of the surface treatment. Use a high speed or lightweight inertial profiler certified at the Texas Transportation Institute.
One-Time Use.
|
SP247-022 |
PDF |
RTF |
- For project 1388-02-008 in Panola County. Target grading will be required. Establish the stockpile gradation within the master grading limits. The stockpile gradation will become the target gradation used for molding specimens for triaxial classification.
One-Time Use.
|
SP247-021 |
PDF |
RTF |
- VOID - DO NOT USE. Measures ride quality of the base course after placement of the prime coat and before placement of the surface treatment and provides recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. SP 247---021 contains the requirements of 247---020 and 247---011 and may be used in lieu of 247---020.
Replaces SP247-011 .Replaced by SP247-036 . (Change Memo: de-49-06). Statewide Use.
|
SP247-020 |
PDF |
RTF |
- Provide recycled materials that have a maximum sulfate content of 3000 ppm when tested in accordance with Tex-145-E. Required on all projects with Item 247 beginning with the March 2007 letting. Replaced by 247-033.
Replaced by SP247-033 . (Change Memo: de-49-06). Statewide Use.
|
SP247-019 |
PDF |
RTF |
- For project 1169-01-023 in Uvalde County. This section applies to the final travel lanes that receive only one lift of Hot Mix ACP or a 1 or 2 course surface treatment for the final surface, unless otherwise shown on the plans.
One-Time Use.
|
SP247-018 |
PDF |
RTF |
- For project 0008-09-030, 0385-01-018, 0649-02-027, 1179-02-030 in Parker County. For cubic yard measurement, In Vehicle, In Stockpile, or In Final Position will be specified.
One-Time Use.
|
SP247-017 |
PDF |
RTF |
- For project 0171-04-065 in Tarrant County. This section applies to the final travel lanes that receive a 1 or 2 course surface treatment for the final surface, unless otherwise shown on the plans.
One-Time Use.
|
SP247-016 |
PDF |
RTF |
- Adds Ride Quality to flexible base with only one lift of Hot Mix ACP or a 1 or 2 course surface treatment for the final surface for quality control.
Replaced by SP247-026 . Districtwide Use. Pharr District.
|
SP247-015 |
PDF |
RTF |
- For project 1993-01-013 in Palo Pinto County. Flexible Base (Roadway Delivery). The ton or any cubic yard method. For cubic yard measurement, In Vehicle, In Stockpile, or In Final Position will be specified.
One-Time Use.
|
SP247-014 |
PDF |
RTF |
- Adds Ride Quality (SP 247---011, statewide) to SP 247---005 (districtwide, which adds lime treatment to flexible base).
Replaces SP247-005 .Replaced by SP247-030 . Districtwide Use. Yoakum District, Corpus Christi District.
|
SP247-013 |
PDF |
RTF |
- Adds Ride Quality (SP 247---011, statewide) to SP 247---007 (districtwide, which allows measurement for Flexible Base (Roadway Delivery) to include any cubic yard method).
Replaces SP247-007 .Replaced by SP247-029 . Districtwide Use. Fort Worth District, Tyler District, Yoakum District, Corpus Christi District, Pharr District.
|
SP247-012 |
PDF |
RTF |
- Adds Ride Quality (SP 247---011 statewide) to SP 247---004 (districtwide which adds cement treatment to flexible base).
Replaces SP247-004 .Replaced by SP247-028 . Districtwide Use. Yoakum District, Corpus Christi District.
|
SP247-011 |
PDF |
RTF |
- Provides for having the ride quality of the base course measured. Ride quality will only be applied to the final travel lanes that receive a 1 or 2 course surface treatment for the final surface.
Replaced by SP247-021 . Statewide Use.
|
SP247-010 |
PDF |
RTF |
- For project 0721-01-013 in Terry County. Flexible Base (Roadway Delivery). The ton, any cubic yard method, or by square yard.
One-Time Use.
|
SP247-009 |
PDF |
RTF |
- For project 1633-01-008 in Yoakum County. Flex Base (Roadway Delivery)
One-Time Use.
|
SP247-008 |
PDF |
RTF |
- For project 0969-02-004 in Hockley County. Added ''In Final Position'' for cubic yard Flexible Base (Roadway Delivery).
One-Time Use.
|
SP247-007 |
PDF |
RTF |
- Changes Flexible Base (Roadway Delivery) measurement to by the ton or any cubic yard method. Changes Flexible Base (Roadway Delivery) payment for cubic yard measurement to be In Vehicle, In Stockpile, or In Final Position.
Replaces SP247-003 .Replaced by SP247-013 . (Change Memo: de-01-97). Districtwide Use. Tyler District, Yoakum District, Corpus Christi District, Pharr District.
|
SP247-006 |
PDF |
RTF |
- For project 1065-02-028 in Cameron County. Changes measurement and payment methods.
One-Time Use.
|
SP247-005 |
PDF |
RTF |
- Provides for payment of flexible base including lime and lime treatment
Replaced by SP247-014 . Districtwide Use. Yoakum District, Corpus Christi District.
|
SP247-004 |
PDF |
RTF |
- Provides for payment of flexible base.
Replaced by SP247-012 . Districtwide Use. Yoakum District, Corpus Christi District.
|
SP247-003 |
PDF |
RTF |
- Changes measurement and payment methods.
Replaced by SP247-007 . Districtwide Use. Yoakum District, Corpus Christi District, Pharr District.
|
SP247-002 |
PDF |
RTF |
- For project 0921-26-010 in Hidalgo County. Update measurement options.
One-Time Use.
|
SP247-001 |
PDF |
RTF |
- Provide clarification on establishing target grading limits.
Replaced by SP247-025 . Districtwide Use. Atlanta District.
|