1993 English Special Provisions to Item 006 - CONTROL OF MATERIALS (Statewide & Districtwide, Current)
SP006-036 |
PDF |
RTF |
- Provides price list for items sold to the Contractor by the Department. Replaces 006-035 beginning with the October 2005 letting.
Replaces SP006-035 . Statewide Use.
|
SP006-025 |
PDF |
RTF |
- Revises Article 6.2 to provide for charging the Contractor for testing done at their convenience. Clarifies that the Engineer may perform additional tests at his/her discretion. (District's option)
Statewide Use.
|
SP006-022 |
PDF |
RTF |
- Implements the requirements mandated by Senate Bill 178. All Non-Federal-Aid Routine Maintenance Contracts (beginning with 04/00 letting).
Replaces SP006-008 . Statewide Use.
|
SP006-021 |
PDF |
RTF |
- Implements the requirements mandated by Senate Bill 178. All Non-Federal-Aid Construction projects (beginning with 04/00 letting).
Statewide Use.
|
SP006-018 |
PDF |
RTF |
- Provides for the use of Non-Hazardous Recyclable Materials (NRMS's). All Construction projects (beginning with 09/99 letting).
Statewide Use.
|
SP006-003 |
PDF |
RTF |
- Adds requirements that Contractor furnish copy of purchase order showing delivery date and that equipment and materials damaged before final acceptance be replaced at Contractor's expense. May be used at the district's option on projects with traffic signals and/or illumination.
Statewide Use.
|
|