2014 English Special Provisions to Item 008 - PROSECUTION AND PROGRESS (Statewide & Districtwide, Current)

SP008-023  PDF  RTF   - Article 8.7.2., Wrongful Default,” of the Standard Specifications is voided and not replaced. Required on all contracts beginning with the January 2017 letting. Statewide Use.
SP008-010  PDF  RTF   - Replaces Article 8.1 to allow work to begin 180 days after authorization. Requires Specification Committee approval prior to use. Do not use with SP008-002, SP008-003, SP008-004, SP008-005, SP008-009, or SP008-011. Statewide Use.
SP008-009  PDF  RTF   - Replaces Article 8.1 to allow work to begin 150 days after authorization. Optional for all projects beginning with the February 2015 letting. May be used as OTU without further request until SW-SP is approved. Do not use with SP008-002, SP008-003, SP008-004, SP008-005, SP008-010, or Sp008-011. Statewide Use.
SP008-006  PDF  RTF   - Provides for incentives using Road-User Cost or Contract Administration Liquidated Damages and disincentives using Road-User Cost. May be used at the districts option. (2004 008-069) Statewide Use.
SP008-005  PDF  RTF   - Replaces Article 8.1 and 8.3 to identify an asphalt season. Optional for all projects beginning with the January 2015 letting. May be used as OTU without further request until SW-SP is approved. For surface treatment, asphaltic concrete overlay, and microsurfacing contracts only. Do not use with SP008-002, SP008-003, or SP008-004. Statewide Use.
SP008-004  PDF  RTF   - Replaces Article 8.1 to allow work to begin 120 days after authorization. Optional for all projects beginning with the January 2015 letting. May be used as OTU without further request until SW-SP is approved. Do not use with SP008-002, SP008-003, or SP008-005. Statewide Use.
SP008-003  PDF  RTF   - Replaces Standard Article 8.1 to allow work to begin 90 days after authorization. Optional for all projects beginning with the January 2015 letting. May be used as OTU without further request until SW-SP is approved. Do not use with SP008-002, SP008-004, or SP008-005. Statewide Use.
SP008-002  PDF  RTF   - Replaces Article 8.1 to allow work to begin 60 days after authorization. Optional for all projects beginning with the January 2015 letting. May be used as OTU without further request until SW-SP is approved. Do not use with SP008-003, SP008-004, or SP008-005. Statewide Use.

  AUSTIN - DISTRICT 14
SP008-017  PDF  RTF   - Lane closure assessment fees. Replaces 2014 SP 008-001 beginning with the March 2016 letting. Approved for CSJ 0006-02-112, 0033-08-038, 0168-10-073, 0675-07-096, 6299-15-001, 0675-07-101. Replaces SP008-001 . Districtwide Use.

  DALLAS - DISTRICT 18
SP008-017  PDF  RTF   - Lane closure assessment fees. Replaces 2014 SP 008-001 beginning with the March 2016 letting. Approved for CSJ 0006-02-112, 0033-08-038, 0168-10-073, 0675-07-096, 6299-15-001, 0675-07-101. Replaces SP008-001 . Districtwide Use.

  HOUSTON - DISTRICT 12
SP008-017  PDF  RTF   - Lane closure assessment fees. Replaces 2014 SP 008-001 beginning with the March 2016 letting. Approved for CSJ 0006-02-112, 0033-08-038, 0168-10-073, 0675-07-096, 6299-15-001, 0675-07-101. Replaces SP008-001 . Districtwide Use.

  SAN ANTONIO - DISTRICT 15
SP008-017  PDF  RTF   - Lane closure assessment fees. Replaces 2014 SP 008-001 beginning with the March 2016 letting. Approved for CSJ 0006-02-112, 0033-08-038, 0168-10-073, 0675-07-096, 6299-15-001, 0675-07-101. Replaces SP008-001 . Districtwide Use.