I-635 Managed Lane Information

 

LBJ Express Project Information

The goal of the LBJ Express Project is to finance, construct, operate and maintain a corridor of frontage road, general purpose and tolled managed lanes from east of Luna Road to east of US 75 (near Greenville Ave.) approximately 14 miles.

This includes tolled managed lanes within the right of way of I-635 and elevated tolled managed lane direct connectors along I-35E. The project also completes a continuous frontage road system along I-635 between the Dallas North Tollway and I-35E.

On February 26, 2009, the Texas Transportation Commission conditionally awarded the LBJ Express Project to LBJ Development Infrastructure Group (formerly LBJ Infrastructure Group), which will finance, design, construct, operate and maintain the 13-mile corridor for 52 years.

Update

On Sept. 4, 2009, TxDOT officials executed a comprehensive development agreement (CDA) with the LBJ Infrastructure Group to design, construct, finance, operate and maintain the 13-mile LBJ-635 corridor in Dallas County.

On May 7, 2009, TxDOT held a public hearing concerning the disclosure of financial information for the LBJ-635 Comprehensive Development Agreement. The public hearing summary and analysis is now available for review.

Type of PPP: Concession

April 28, 2005
Authorization by the Texas Transportation Commission to issue request for qualifications

May 23, 2005
TxDOT issues request for proposals and qualifications

September 22, 2005
Deadline to submit qualification proposals

November 22, 2005

TxDOT evaluation and short list of teams

October 26, 2006
Authorization by the Texas Transportation Commission to issue request for proposals

September 18, 2007
TxDOT issues request for proposals.

January 21, 2009
Deadline to submit proposals

Jan.-Feb. 2009
TxDOT evaluation

February, 2009
Selection of best-value proposal 

Mid-2010 to Mid-2011
Construction estimated to begin

Addendum No. 13 (January 19, 2009)

Addendum No. 12 (January 14, 2009)

Addendum No. 11 (December 23, 2008)

Addendum No. 10 (November 21, 2008)

Addendum No. 9 (October 10, 2008)

RFP Addendum No. 8 (July 21, 2008)

RFP Addendum No. 7 (June 27, 2008)

RFP Addendum No. 6 (June 4, 2008)

RFP Addendum No. 5 (May 1, 2008)

RFP Addendum No. 4 (April 3, 2008)

RFP Addendum No. 3 (March 19, 2008)

RFP Addendum No. 2 (March 3, 2008)

RFP Addendum No. 1 (Jan. 9, 2008)

Request for Proposals