 |
Major Investment Study
SH 183 Preliminary Engineering and Environmental Assessment |
Project Description | Project
Summary |
Study Area Map |
Recommended Plan of Action | Project
Coordination Work Group Meetings | Public
Meetings and Slide Presentation | Contact List
| Project Schedules |
Approved 2004 schematic |
Project Bulletin
| SH 183 Reevaluation Schematic
SH 183/WEST FORK CORRIDOR MAJOR
INVESTMENT STUDY
RECOMMENDED PLAN OF ACTION
Subject to appropriate environmental and engineering
processing and clearances, the SH 183/ West Fork Corridor MIS recommended
seven (7) elements for improvement in the corridor:
- Enhanced work trip reduction measures.
- Bicycle and pedestrian facilities.
- Enhanced transportation facility management.
- Addition of a second track for the Trinity
Railway Express.
- Improvements to major east-west arterials,
including Irving Blvd., Rock Island Road, Trinity Blvd., and Hunter
Ferrell Road, as well as over 100 signalization and intersection
improvements.
- Reconstruction of SH 183 with widening from 6 to
8 general purpose main lanes, and a managed high occupancy vehicle (HOV)
system on SH 183 from SH 360 to a connection with the proposed I-35E HOV
system.
- A new reliever roadway constructed as a strategic
regional arterial west of Loop 12, and a toll way east of Loop 12, with
provisions for an extension west to Fort Worth.
MIS Recommended Improvements to SH 183
Existing SH 183 is a 6-lane divided freeway with a
narrow right-of-way, especially between Beltline Road and Carl Road. For
this work item, SH 183 is proposed to be widened to 8 general use main lanes
(4 in each direction) with three reversible managed High Occupancy Vehicle
(HOV) lanes.
Highly directional traffic using SH 183 has a demand
for seven lanes in the peak direction (eastbound in the morning and
westbound in the evening), and four lanes in the off-peak direction.
Reversible lanes can provide capacity most efficiently, using less
right-of-way and costing less to construct than a permanent lane in each
direction. Travel modeling by the NCTCOG shows a projected need for the
equivalent of 1.5 lanes to serve HOV traffic. A three lane managed HOV
allows for extra HOV capacity if demand exceeds expectations. Any remaining
capacity would be filled with Express Single Occupant Vehicles (SOV) given
this privilege by paying a toll. Managed
HOV
lanes use congestion pricing (tolls rates that vary by time of day and level
of congestion) to regulate the number of SOV’s sharing the HOV lanes. Toll
revenue is assumed to off-set operating costs only.
This plan uses 3 lanes of managed HOV from Beltline
Rd. to I-35E, and 2 lanes of HOV from SH 360 to Beltline Road. Only 2 lanes
of HOV can fit through the major interchanges with SH 161, SH 360 and
International Parkway. The total estimated cost of the SH 183 improvements
is $650 million.
This price is based on an at-grade section generally
following the existing profile, but it does not include any extra provisions
for depressing the main lanes. Regardless of any widening, the total
reconstruction of the freeway, including frontage roads, is necessary
because of its old age and the need to improve its functionality.
Efforts will be made during the environmental
assessment (part of the National Environmental Policy Act (NEPA) process) to
refine and reduce the displacements and right-of-way needs. The narrow
right-of-way requires that any widening which does not use multiple-level,
decked structures acquire adjacent property. A number of displacements will
be necessary, although the specific Right-of-Way (ROW) needs will not be
determined until the Environmental Assessment is performed as part of the
NEPA process.
Major Unresolved Issues for SH 183
The following are issues that were recommended to be
investigated and resolved prior to the approval of the environmental
assessment and schematic design of SH 183:
- SH 183 Depressed Main Lanes -
At the request of the City of Irving, the study team investigated
depressing the main lanes of SH 183 in the area from west of Story Road to
east of O’Connor Blvd. A shortened version that only depressed the main
lanes under O’Connor and MacArthur Blvd. was also investigated due to the
drainage impacts from Delaware Creek crossing east of Story Road. Ramp
locations and other factors limit any right-of-way savings from
potentially cantilevering the frontage roads. The costs have been
estimated at over $80 million for the shorter length, and over $150
million for the length from Story to O’Connor. This option is being
considered to reduce visual intrusion and improve community cohesion.
- Managed HOV Operation -
Managed HOV lanes have yet to be used in Dallas, and
are still a very new, developing technology. Only a few managed HOV lane
systems have been implemented in the United States. HOV only lanes have
been very successful in Dallas, and managed HOV lanes are anticipated to
have the same success. The regional transportation agencies have yet to
determine who will operate managed HOV lanes. It is expected that both the
technology and the operation will be resolved by the time this proposed
system is ready for implementation.
- SH 183 Ramp Locations
- Three separate ramping schemes were developed for SH 183: an x-ramp
system, a diamond ramp system, and a combination of the two. These ramp
alternatives have been reviewed by local city staff, this study’s
community groups and the general public. With the exception of a few
requests for single, isolated ramp location preferences, no overall system
of ramping has emerged as the locally preferred option. Specific ramp
locations will be developed during the environmental assessment and
schematic design effort that follows the MIS.
- SH 183 Alignment at Jaycee Park
- The SH 183 right-of-way is most narrow in the area between Story Road
and MacArthur Blvd., especially on the south side between William Brewster
Road and Story Road. Improvements that maintain the existing SH 183 main
lane centerline could potentially impact many residences, businesses and
Jaycee Park itself. The neighborhood residents have asked that an
alternative alignment be evaluated that does not require additional
right-of-way from the south side. Specific alternative alignments, and
refinement of the right-of-way needs and necessary displacements will be
developed during the environmental assessment and schematic design effort
that follows the MIS.
Go to the Top
|