The Atlanta District services the following counties: Bowie, Camp, Cass, Harrison, Marion, Morris, Panola, Titus and Upshur. The district designs, builds, operates and maintains the state transportation system across county lines.
In this district, US Highway 59 from Texarkana to north of Tenaha will be developed to meet interstate standards as part of the I-69 system development.
Learn more about future I-69 projects by clicking on the highlighted areas on the map below. Projects are also listed under the map for quick reference and additional information.
All construction dates above are tentative and dependent on available funding.
Project Listings
County | Project | Phase | Description |
---|---|---|---|
Bowie County and Cass County | US 59-Texarkana to Queen City | Route Study Completed | Route Study to upgrade US 59 to interstate standards |
Bowie | US 59 from I-369/SL 151 to south of FM 2148 | Long-Term Planning | Construct 4-lane divided highway to interstate standards |
Bowie County and Cass County | US 59 from south of FM 2148 to FM 2327(S) | Study | Construct 4-lane divided highway to interstate standards |
Harrison County | Future I-369 | Route Study Completed | Determining options for development of I-369 in the Marshall area |
Harrison County | SL 390 (Future US 59/I-369) from North of Marshall to US 80* | Under Development | Construct 4-lane divided highway to interstate standards |
Harrison County | SL 390 (Future US 59/I-369) from US 80 to I-20* | Under Development | Construct 4-lane divided highway to interstate standards on new location |
Harrison County | SL 390 (Future US 59/I-369) from I-20 to US 59 south of Marshall | Long-Term Planning | Construct 4-lane divided highway to interstate standards on new location |
Panola | US 59 at FM 1794* | Under Development | Construct grade separation to meet interstate standards (future I-369) |
* For more project information, click the link on the project area map above.