Monthly State Let Construction Report For Abilene District As Of Jul 14, 2020 Page 1 Of 2

Last Update: Tuesday, July 14, 2020
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD ETC
HighwayIH 20
From.408 MI WEST OF CAUBLE RD
ToN SCURRY STREET
CSJ0005-05-114
Proj IDSTP 1902(336)HES
Work TypeSFT
 
23.8765297532.083311914.9262.5
Work Order09-18-19
Work Began05-08-20
Work Completed
Time Computed12-18-19
Contract Working Days187
Addl Days Granted0
Working Days Charged79
Percent Time Used42
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-114
FOX CONTRACTING KY, INC. (18.72)
BARRICADES UNLIMITED (0.78)
Contract #08193013
Totals5297532.083311914.923311914.9262.5

CountyNOLAN
HighwayIH 20
FromMITCHELL CO LINE
ToBI 20-L IN ROSCOE
CSJ0006-02-115
Proj IDNH 2019(522)
Work Type2" MILL & FILL, 1 CST AND 2" SMA D
 
6.4068705662.158333662.6495.7
CountyNOLAN
HighwayIH 20
From.14 MILE WEST OF SH 70
ToEAST BI 20 M
CSJ0006-03-135
Proj IDNH 2019(522)
Work TypeMILL, SPOT REPAIR, UNDERSEAL, OVER
 
3.6997005858.111824324.1626.0
CountyNOLAN
HighwayIH 20
FromBS70/SH70
ToSH70
CSJ0006-03-136
Proj IDSTP 2019(639)HES
Work TypeINSTALL MEDIAN BARRIER FLATTEN SLOP
 
2.771800300.000.000.0
Work Order04-25-19
Work Began09-11-19
Work Completed
Time Computed05-28-19
Contract Working Days165
Addl Days Granted165
Working Days Charged160
Percent Time Used48
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-115
A BROTHERS MILLING, LLC (1.24)
CHEROKEE SERVICES (0.24)
CONTRACTORS SERVICE COMPANY (0.50)
DOUBLE A CONTRACTING, L.P. (2.85)
HJC FARMS, INC. (8.26)
RPV CONSTRUCTION, LLC (3.57)
Contract #03193206
Totals16511820.264309424.0410157986.8061.5

CountyNOLAN
HighwayIH 20
FromWEST BU20L
To.14 MILE WEST OF SH 70
CSJ0006-02-121
Proj IDNH 2020(618)
Work TypeOVERLAY
 
9.97720032973.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-18-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days604
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-121
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203003
Totals20032973.640.000.000.0

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-080
Proj IDNH 2019(920)
Work TypeOVERLAY
 
6.22010684704.912413739.8422.5
Work Order06-17-19
Work Began10-21-19
Work Completed
Time Computed09-16-19
Contract Working Days310
Addl Days Granted0
Working Days Charged173
Percent Time Used55
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-080
CONTRACTORS SERVICE COMPANY (0.39)
AREA WIDE PROTECTIVE, INC. (0.98)
PRIMATE CONSTRUCTION, LP (0.30)
TOTAL HIGHWAY MAINTENANCE, LLC (1.18)
BLACKTOP INDUSTRIES LLC (5.71)
AARON CONCRETE CONTRACTORS, L.P. (1.18)
Contract #05193035
Totals10684704.91341148.082413739.8422.5

CountyTAYLOR
HighwaySH 351
FromBU 83-D (TREADAWAY ST)
ToIH 20
CSJ0011-01-038
Proj IDNH 2020(354)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.6364596548.00111129.202.4
Work Order02-04-20
Work Began06-01-20
Work Completed
Time Computed05-04-20
Contract Working Days193
Addl Days Granted0
Working Days Charged18
Percent Time Used9
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-038
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.54)
STREET FOUNDATION DRILLING, INC. (2.34)
WILLIS ELECTRIC CO., LP (9.51)
MOBILE ENTERPRISES, INC. (2.62)
CONTRACTORS SERVICE COMPANY (0.79)
FUSION COMMUNICATIONS, LLC (0.61)
Contract #12193019
Totals4596548.0043960.20111129.202.4

CountySHACKELFORD
HighwayUS 180
From4TH STREET IN ALBANY
ToSH 351
CSJ0011-05-051
Proj IDSTP 2020(692)
Work TypeREHABILITATION OF EXISTING ROAD
 
10086760.110.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-13-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days257
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-05-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05203005
Totals10086760.110.000.000.0

CountySHACKELFORD
HighwayUS 180
FromALBANY EAST CITY LIMITS
ToSTEPHENS COUNTY LINE
CSJ0011-06-049
Proj IDSTP 2020(172)
Work TypeRESTORATION
 
11.4068259120.38235188.922.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-20
Work Began05-18-20
Work Completed
Time Computed00-00-00
Contract Working Days479
Addl Days Granted0
Working Days Charged24
Percent Time Used5
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-049
BARRICADES UNLIMITED (2.89)
CONTRACTORS SERVICE COMPANY (1.12)
HJC FARMS, INC. (3.14)
HUDSON, INC. SOUTH (1.65)
STRIPE-A-ZONE, INC. (0.33)
W. S. CONSTRUCTION COMPANY (18.34)
Contract #01203007
Totals8259120.3839812.50235188.922.8

CountyJONES
HighwayUS 83
FromSH 92 IN HAMLIN
ToUS 277 NORTH OF ANSON
CSJ0033-04-063
Proj IDSTP 1302(059)
Work TypeCONSTRUCT SUPER TWO
 
15.34210819113.524009060.7137.0
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed01-21-19
Contract Working Days269
Addl Days Granted10
Working Days Charged254
Percent Time Used91
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-063
DOUBLE A CONTRACTING, L.P. (0.35)
CONTRACTORS SERVICE COMPANY (0.74)
A BROTHERS MILLING, LLC (0.76)
HJC FARMS, INC. (4.04)
FLAT LINE, INC. (2.33)
MURRAY CONSTRUCTION (0.62)
W. S. CONSTRUCTION COMPANY (6.32)
Contract #09183206
Totals10819113.52215327.654009060.7137.0

CountyTAYLOR
HighwayUS 83
FromS OF FM 204(CLARK/REMINGTON RD)
ToFM 707
CSJ0034-01-126
Proj IDNH 1802(506)
Work TypeEMB, FL BS, STRS, AND ACP
 
2.69419355727.8610526629.2354.3
CountyTAYLOR
HighwayUS 83
FromJUST SOUTH OF FM 204
ToUS 83 -US 84 SPLIT
CSJ0034-01-128
Proj IDNH 1802(506)
Work TypeEXC,FLX BS,ACP,OBL PVMT
 
5.9568637814.624627294.1853.5
Work Order11-01-18
Work Began01-21-19
Work Completed
Time Computed01-10-19
Contract Working Days553
Addl Days Granted0
Working Days Charged381
Percent Time Used68
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-126
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
DIIBS SPECIALISTS (0.53)
DK CONTRACTING, LLC (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.55)
SOUTH TEXAS PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
BO SIMON INC (5.28)
DUSTROL, INC. (0.63)
HJC FARMS, INC. (2.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.88)
WILLIS ELECTRIC CO., LP (4.24)
STATEWIDE TRANSPORT, LLC (2.48)
ROBERT FLOYD SUE TRUCKING, INC (0.00)
NSTARRWAY VENTURES, LP (0.18)
WAYNE BRYANT LOGISTICS, LLC (0.24)
NOBLES ROAD CONSTRUCTION, INC. (0.24)
MICA CORPORATION (0.80)
FLAT LINE, INC. (0.00)
HALLIGAN SERVICES LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.03)
Contract #08183203
Totals27993542.482256504.3315153923.4154.1

CountyTAYLOR
HighwayUS 83
FromUS 277 (S14TH) (FTG RDS& RAMPS ONLY
ToLP 322/US 83 INTERCHANGE
CSJ0034-01-137
Proj IDSTP 2019(984)
Work TypeOVERLAY
 
4451081.56460594.0110.3
Work Order07-23-19
Work Began00-00-00
Work Completed
Time Computed08-23-19
Contract Working Days64
Addl Days Granted0
Working Days Charged42
Percent Time Used65
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-137
A BROTHERS MILLING, LLC (2.13)
CONTRACTORS SERVICE COMPANY (2.38)
MPB, INC. (0.97)
TOTAL HIGHWAY MAINTENANCE, LLC (3.07)
Contract #06193025
Totals4451081.56460594.01460594.0110.3

CountyNOLAN
HighwayFM 608
FromCR 152
ToFM 2319
CSJ0053-15-024
Proj IDSTP 2018(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.1164261779.48952833.1522.3
Work Order07-16-19
Work Began10-14-19
Work Completed
Time Computed10-14-19
Contract Working Days253
Addl Days Granted0
Working Days Charged119
Percent Time Used47
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-024
CONTRACTORS SERVICE COMPANY (0.84)
HJC FARMS, INC. (2.35)
TOTAL HIGHWAY MAINTENANCE, LLC (3.00)
Contract #05193023
Totals4261779.48199474.39952833.1522.3

CountyHOWARD
HighwayUS 87
FromUPRR @ BEALS CREEK
To..
CSJ0068-08-065
Proj IDBR 1802(503)
Work TypeBRIDGE REHAB
 
0.1606661050.955200444.2578.0
Work Order11-15-18
Work Began10-14-19
Work Completed
Time Computed01-15-19
Contract Working Days181
Addl Days Granted20
Working Days Charged149
Percent Time Used74
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-065
BARRICADES UNLIMITED (0.74)
SCOTT DERR PAINTING CO, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
WILLIS ELECTRIC CO., LP (1.41)
OLYMPUS PAINTING CONTRACTORS, INC. (18.05)
CHOCTAW ERECTORS, INC. (0.49)
ACCESS RIGGING LLC (2.18)
NATIONAL BRIDGE, LLC (7.01)
Contract #08183050
Totals6661050.951580493.255200444.2578.0

CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
To2.717 MI S OF FM 2482
CSJ0125-04-029
Proj IDSTP 2019(430)HES
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
15.13031300.740.000.0
CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
ToUS 180 IN ALBANY
CSJ0125-04-033
Proj IDSTP 2019(392)
Work TypeREHABILITATE AND WIDEN ROADWAY
 
17.30812550076.275146321.0041.0
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days429
Addl Days Granted0
Working Days Charged216
Percent Time Used50
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-04-029
MURRAY CONSTRUCTION (0.52)
CONTRACTORS SERVICE COMPANY (0.41)
PRIMATE CONSTRUCTION, LP (0.75)
NIXON ENGINEERING (0.21)
HJC FARMS, INC. (1.71)
TOTAL HIGHWAY MAINTENANCE, LLC (1.85)
J & M CONTRACTING, COMPANY (9.58)
TRANSGLOBAL, LLC (0.13)
Contract #01193004
Totals12581377.0184670.005146321.0040.9

CountySHACKELFORD
HighwaySH 6
FromPECAN STREET ALBANY
ToCALLAHAN CO LINE
CSJ0126-01-039
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
17.5739227644.071482727.7016.0
CountyCALLAHAN
HighwaySH 6
FromCALLAHAN CO LINE
ToEASTLAND CO LINE
CSJ0126-02-020
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
2.2833436044.22973327.5128.3
Work Order10-21-19
Work Began12-02-19
Work Completed
Time Computed12-02-19
Contract Working Days322
Addl Days Granted0
Working Days Charged98
Percent Time Used30
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0126-01-039
BLACKTOP INDUSTRIES LLC (3.67)
CHEROKEE SERVICES (0.08)
CONTRACTORS SERVICE COMPANY (0.29)
COPPELL CONSTRUCTION CO., INC. (11.16)
D. I. J. CONSTRUCTION, INC. (1.47)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
MURRAY CONSTRUCTION (0.93)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.14)
AARON CONCRETE CONTRACTORS, L.P. (0.46)
BOWMAN ENGINEERING & CONSULTING, INC. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
SOUTH TEXAS PAINTING COMPANY (0.05)
Contract #09193203
Totals12663688.29583641.002456055.2119.3

CountyJONES
HighwayUS 277
FromFM 1636
ToANSON
CSJ0157-05-063
Proj IDC 157-5-63
Work TypeOVERLAY
 
7849211.940.000.0
CountyJONES
HighwayUS 277
FromFM 1636
ToHASKELL CO LINE
CSJ0157-05-064
Proj IDC 157-5-64
Work TypeRESTORATION
 
7335735.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-05-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05203203
Totals15184946.970.000.000.0

CountyFISHER
HighwayUS 180
FromFM 57
ToUS 180
CSJ0296-03-038
Proj IDBR 2019(982)
Work TypeBR
 
0.5434583865.381319173.7328.7
CountyFISHER
HighwayFM 57
FromSH 70
ToUS 180
CSJ0317-01-037
Proj IDSTP 2019(985)
Work TypeWIDEN NON-FREEWAY
 
12.39612063124.233919711.0532.4
CountyFISHER
HighwayFM 57
FromPLUM CREEK
To.
CSJ0317-01-038
Proj IDBR 2019(983)
Work TypeBR
 
1930380.931043396.6654.0
Work Order07-16-19
Work Began10-16-19
Work Completed
Time Computed10-15-19
Contract Working Days673
Addl Days Granted0
Working Days Charged153
Percent Time Used22
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0296-03-038
A BROTHERS MILLING, LLC (0.84)
BARRICADES UNLIMITED (1.15)
LINDAMOOD DEMOLITION, INC. (0.92)
SCOTT DERR PAINTING CO, LLC (0.23)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
WILLIS ELECTRIC CO., LP (0.76)
BLACKTOP INDUSTRIES LLC (2.19)
BOWMAN ENGINEERING & CONSULTING, INC. (0.27)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.04)
PENHALL COMPANY (0.08)
HODGES AND SON CONSTRUCTION COMPANY, INC. (2.07)
TORO BRAVO CONSTRUCTION, LLC (0.10)
Contract #06193009
Totals18577370.541468588.416282281.4433.8

CountyJONES
HighwayUS 180
FromFM 1226
ToSHACKELFORD COUNTY LINE
CSJ0296-05-034
Proj IDSTP 2019(393)
Work TypeBASE REPAIR LEVEL UP AND OVERLAY
 
11.0357597359.935517742.9672.6
Work Order02-25-19
Work Began06-03-19
Work Completed
Time Computed03-27-19
Contract Working Days332
Addl Days Granted0
Working Days Charged233
Percent Time Used70
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-05-034
CONTRACTORS SERVICE COMPANY (0.77)
STRIPE-A-ZONE, INC. (0.45)
HJC FARMS, INC. (8.96)
FLAT LINE, INC. (2.09)
J & M CONTRACTING, COMPANY (5.08)
Contract #01193040
Totals7597359.931804319.515517742.9672.6

CountyJONES ETC
HighwayFM 707 ETC
FromUS 83
ToFM 605
CSJ0484-01-023
Proj IDSTP 1802(504)HES
Work TypeWIDEN ROADWAY
 
32.44313833694.0010608109.6776.6
Work Order09-24-18
Work Began10-23-18
Work Completed
Time Computed10-23-18
Contract Working Days648
Addl Days Granted20
Working Days Charged369
Percent Time Used55
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0484-01-023
A BROTHERS MILLING, LLC (0.09)
CONTRACTORS SERVICE COMPANY (0.69)
HJC FARMS, INC. (1.57)
DOUBLE A CONTRACTING, L.P. (3.18)
MURRAY CONSTRUCTION (1.06)
THORNTON"S TREE SERVICE, INC. (2.34)
Contract #08183009
Totals13833694.00741613.7610608109.6776.6

CountyHOWARD
HighwaySH 176
FromMARTIN COUNTY LINE
ToIH 20 SOUTH FRONTAGE ROAD
CSJ0548-04-021
Proj IDSTP 2020(361)
Work TypeRESTORATION
 
11.1209975871.022287783.5122.9
Work Order01-03-20
Work Began04-07-20
Work Completed
Time Computed04-03-20
Contract Working Days180
Addl Days Granted0
Working Days Charged58
Percent Time Used32
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0548-04-021
A BROTHERS MILLING, LLC (1.36)
BLACK JACK ENERGY SERVICES, LLC (1.44)
CONTRACTORS SERVICE COMPANY (0.54)
DK CONTRACTING, LLC (0.72)
DOUBLE A CONTRACTING, L.P. (7.93)
HJC FARMS, INC. (0.38)
RPV CONSTRUCTION, LLC (0.93)
WILLIS ELECTRIC CO., LP (0.58)
FUSION COMMUNICATIONS, LLC (0.01)
W. S. CONSTRUCTION COMPANY (0.22)
Contract #12193206
Totals9975871.021681829.372287783.5122.9

CountyHOWARD
HighwayFM 700
FromUS 87
To1550 FT. EAST OF BIRDWELL LANE
CSJ0668-02-020
Proj IDNH 2020(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.8594167074.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-23-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0668-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203020
Totals4167074.000.000.000.0

page 1 | page 2