Monthly State Let Construction Report For Abilene District As Of Aug 23, 2019 Page 1 Of 2

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromIH 20 AND MOORE FIELD ROAD
ToIH 20 AND MORE FIELD ROAD
CSJ0005-05-112
Proj IDBR 1702(476)
Work TypeINSTALL CRASHWALLS
 
1.0047767027.747730883.0899.5
Work Order08-08-17
Work Began10-16-17
Work Completed
Time Computed09-07-17
Contract Working Days309
Addl Days Granted131
Working Days Charged421
Percent Time Used95
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-112
CONTRACTORS SERVICE COMPANY (1.06)
DIIBS SPECIALISTS (0.66)
DOUBLE A CONTRACTING, L.P. (3.12)
GIBSON & ASSOCIATES, INC. (0.47)
MCL CONTRACTING, LLC (1.60)
NELSON INDUSTRIAL SERVICES, INC. (0.08)
PRICE CONSTRUCTION, LTD. (1.34)
S & S BRIDGE PAINTING, INC. (7.03)
TEXAS CURB CUT, LP (0.04)
LLOYD D. NABORS DEMOLITION LLC (0.69)
TEXOP CONSTRUCTION (0.11)
D & D STUD WELDING (0.04)
PENHALL COMPANY (0.05)
A BROTHERS MILLING, LLC (0.17)
Contract #07173231
Totals7767027.74368031.577730883.0899.5

CountyHOWARD ETC
HighwayIH 20
From.408 MI WEST OF CAUBLE RD
ToN SCURRY STREET
CSJ0005-05-114
Proj IDSTP 1902(336)HES
Work TypeSFT
 
23.8765297532.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193013
Totals5297532.080.000.000.0

CountyHOWARD ETC
HighwayBI 20-G ETC
FromIH 20
ToNEAR JONES STREET IN BIG SPRING
CSJ0005-10-023
Proj IDC 5-10-23
Work TypeSEAL COAT
 
309.86013457009.4612755907.6094.7
Work Order01-17-19
Work Began04-25-19
Work Completed
Time Computed04-25-19
Contract Working Days104
Addl Days Granted0
Working Days Charged72
Percent Time Used69
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0005-10-023
VIZCAINO, L.P. (6.20)
BARRICADES PLUS, LLC (1.23)
Contract #12183002
Totals13457009.4611309286.3812755907.6094.7

CountyMITCHELL
HighwayIH 20
FromEAST OF THE UPRR OVERPASS
ToJUST EAST OF CR 424 UNDERPASS
CSJ0006-01-100
Proj IDNH 2019(391)
Work TypeOBLITERATE EXIST PAVEMENT
 
1.250328277.70209293.5563.7
Work Order02-20-19
Work Began04-22-19
Work Completed
Time Computed04-22-19
Contract Working Days93
Addl Days Granted0
Working Days Charged63
Percent Time Used67
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0006-01-100
DOUBLE A CONTRACTING, L.P. (5.38)
HJC FARMS, INC. (28.46)
TEXAS ALTERNATIVE GRASSER INCORPORATED (2.13)
CONTRACTORS SERVICE COMPANY (5.33)
Contract #01193233
Totals328277.7066713.29209293.5563.7

CountyNOLAN
HighwayIH 20
FromMITCHELL CO LINE
ToBI 20-L IN ROSCOE
CSJ0006-02-115
Proj IDNH 2019(522)
Work Type2" MILL & FILL, 1 CST AND 2" SMA D
 
6.4068705662.150.000.0
CountyNOLAN
HighwayIH 20
From.14 MILE WEST OF SH 70
ToEAST BI 20 M
CSJ0006-03-135
Proj IDNH 2019(522)
Work TypeMILL, SPOT REPAIR, UNDERSEAL, OVER
 
3.6997005858.110.000.0
CountyNOLAN
HighwayIH 20
FromBS70/SH70
ToSH70
CSJ0006-03-136
Proj IDSTP 2019(639)HES
Work TypeINSTALL MEDIAN BARRIER FLATTEN SLOP
 
2.771800300.000.000.0
Work Order04-25-19
Work Began00-00-00
Work Completed
Time Computed05-28-19
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-115
A BROTHERS MILLING, LLC (1.24)
CHEROKEE SERVICES (0.24)
CONTRACTORS SERVICE COMPANY (0.50)
DOUBLE A CONTRACTING, L.P. (2.85)
HJC FARMS, INC. (8.26)
RPV CONSTRUCTION, LLC (3.57)
Contract #03193206
Totals16511820.260.000.000.0

CountyNOLAN
HighwayIH 20
FromEAST BI 20-M IN SWEETWATER
ToTAYLOR COUNTY LINE
CSJ0006-03-132
Proj IDNH 2017(456)
Work TypeMILL,SPOT REPAIR,UNDERSEAL &OVERLAY
 
12.47714579827.2815763157.7899.9
Work Order05-09-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days331
Addl Days Granted0
Working Days Charged256
Percent Time Used77
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-132
CONTRACTORS SERVICE COMPANY (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
AARON"S CONCRETE SAWING AND SEALING INC. (0.54)
DOUBLE A CONTRACTING, L.P. (1.65)
DUSTROL, INC. (1.53)
RPV CONSTRUCTION (2.93)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.35)
CHEROKEE SERVICES (0.86)
HJC FARMS, INC. (3.21)
SCR CONSTRUCTION CO., INC. (1.35)
TITAN MILLING INC. (0.99)
Contract #03173237
Totals14579827.285981.6215763157.7899.9

CountyTAYLOR
HighwayIH 20
FromAT NOODLE CREEK (IH 20 NFR & SFR)
To0.10 MI E OF FM 1085
CSJ0006-04-072
Proj IDBR 2018(827)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
4.403894985.25984217.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-18
Work Began09-08-18
Work Completed
Time Computed07-23-18
Contract Working Days71
Addl Days Granted50
Working Days Charged133
Percent Time Used109
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-04-072
DIIBS SPECIALISTS (5.98)
FLAT LINE, INC. (0.85)
Contract #05183044
Totals894985.250.00984217.0999.9

CountyCALLAHAN
HighwayIH 20
FromTAYLOR COUNTY LINE
ToEAST OF FM 1707
CSJ0006-07-079
Proj IDC 6-7-79
Work TypeMILL AND OVERLAY
 
6.6937087728.077410037.1099.9
Work Order07-19-18
Work Began08-24-18
Work Completed
Time Computed08-20-18
Contract Working Days109
Addl Days Granted0
Working Days Charged117
Percent Time Used107
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-079
TEX OP CONSTRUCTION, LP (2.17)
HJC FARMS, INC. (7.35)
DOUBLE A CONTRACTING, L.P. (0.29)
MPB, INC. (0.55)
CONTRACTORS SERVICE COMPANY (0.45)
FLAT LINE, INC. (1.06)
Contract #06183252
Totals7087728.070.007410037.1099.9

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-080
Proj IDNH 2019(920)
Work TypeOVERLAY
 
6.22010684704.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days310
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193035
Totals10684704.910.000.000.0

CountyNOLAN
HighwayBI 20-M
FromAT THE UPRR
ToIN SWEETWATER (PSN 044)
CSJ0006-15-034
Proj IDBR 1702(521)
Work TypeREPLACE BRIDGE
 
0.3604949400.004963807.3399.9
Work Order03-23-18
Work Began05-21-18
Work Completed
Time Computed05-21-18
Contract Working Days139
Addl Days Granted8
Working Days Charged146
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-034
A BROTHERS MILLING, LLC (0.17)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.29)
BOWMAN ENGINEERING & CONSULTING, INC. (0.68)
DK CONTRACTING, LLC (0.16)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
RPV CONSTRUCTION (1.68)
SOUTH TEXAS PAINTING COMPANY (0.19)
TERRACON CONSULTANTS, INC. (2.02)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94)
URBAN INFRACONSTRUCTION, LLC. (7.73)
BARRICADES UNLIMITED (0.63)
WILLIS ELECTRIC CO., LP (1.48)
TOTAL HIGHWAY MAINTENANCE, LLC (0.33)
NOBLES ROAD CONSTRUCTION, INC. (15.76)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.07)
TEXAS SHAFTS, INC. (3.66)
ASSOCIATED CUTTING, INC. (0.42)
CHOCTAW ERECTORS, INC. (4.63)
MCL CONTRACTING, LLC (0.24)
WEBBER BARRIER SERVICES, LLC. (1.09)
ERNESTO CASTRO (0.35)
TEXAS STUD WELDING (0.06)
Contract #01183026
Totals4949400.000.004963807.3399.9

CountyTAYLOR
HighwayBI 20-R
FromUS 83 (WINTERS FWY)
ToNEAR NEWMAN ROAD
CSJ0006-18-058
Proj IDC 6-18-58
Work TypeMILL & FILL W/ 1-CST AND SMA
 
6.5335844817.843692334.4863.1
Work Order07-31-18
Work Began09-06-18
Work Completed
Time Computed08-30-18
Contract Working Days162
Addl Days Granted0
Working Days Charged155
Percent Time Used95
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-058
FLAT LINE, INC. (2.42)
WILLIS ELECTRIC CO., LP (9.18)
HJC FARMS, INC. (2.99)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.82)
SCR CIVIL CONSTRUCTION, LLC (4.05)
CONTRACTORS SERVICE COMPANY (0.71)
WOLFE CONSTRUCTION GROUP, INC. (0.21)
FUSION COMMUNICATIONS, LLC (1.20)
DUSTROL, INC. (1.01)
Contract #05183018
Totals5844817.8477587.533692334.4863.1

CountyJONES
HighwayUS 83
FromSH 92
ToHAMLIN NORTH CITY LIMITS
CSJ0033-03-029
Proj IDSTP 1702(131)
Work TypeCEMENT TRT BASE,1-CST,6" MILL
 
2.7524161245.375119567.2299.9
Work Order06-07-17
Work Began10-12-17
Work Completed
Time Computed07-06-17
Contract Working Days242
Addl Days Granted68
Working Days Charged317
Percent Time Used102
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-03-029
BRENDA CONSTRUCTION (6.51)
CONTRACTORS SERVICE COMPANY (1.54)
DOUBLE A CONTRACTING, L.P. (1.99)
DUSTROL, INC. (1.92)
HJC FARMS, INC. (2.66)
TOTAL HIGHWAY MAINTENANCE, LLC (0.58)
TEX OP CONSTRUCTION, LP (0.34)
Contract #05173221
Totals4161245.370.005119567.2299.9

CountyJONES
HighwayUS 83
FromSH 92 IN HAMLIN
ToUS 277 NORTH OF ANSON
CSJ0033-04-063
Proj IDSTP 1302(059)
Work TypeCONSTRUCT SUPER TWO
 
15.34210819113.521208022.6211.1
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed01-21-19
Contract Working Days269
Addl Days Granted0
Working Days Charged110
Percent Time Used40
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-063
DOUBLE A CONTRACTING, L.P. (0.35)
CONTRACTORS SERVICE COMPANY (0.74)
A BROTHERS MILLING, LLC (0.76)
HJC FARMS, INC. (4.04)
FLAT LINE, INC. (2.33)
MURRAY CONSTRUCTION (0.62)
W. S. CONSTRUCTION COMPANY (6.32)
Contract #09183206
Totals10819113.52167566.951208022.6211.1

CountyTAYLOR
HighwayUS 83
FromS OF FM 204(CLARK/REMINGTON RD)
ToFM 707
CSJ0034-01-126
Proj IDNH 1802(506)
Work TypeEMB, FL BS, STRS, AND ACP
 
2.69419355727.863526335.2218.2
CountyTAYLOR
HighwayUS 83
FromJUST SOUTH OF FM 204
ToUS 83 -US 84 SPLIT
CSJ0034-01-128
Proj IDNH 1802(506)
Work TypeEXC,FLX BS,ACP,OBL PVMT
 
5.9568637814.622656781.3830.7
Work Order11-01-18
Work Began01-21-19
Work Completed
Time Computed01-10-19
Contract Working Days553
Addl Days Granted0
Working Days Charged138
Percent Time Used24
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-126
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
DIIBS SPECIALISTS (0.53)
DK CONTRACTING, LLC (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.55)
SOUTH TEXAS PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
BO SIMON INC (5.28)
DUSTROL, INC. (0.63)
HJC FARMS, INC. (2.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.88)
WILLIS ELECTRIC CO., LP (4.24)
STATEWIDE TRANSPORT, LLC (2.48)
ROBERT FLOYD SUE TRUCKING, INC (0.00)
NSTARRWAY VENTURES, LP (0.18)
WAYNE BRYANT LOGISTICS, LLC (0.24)
NOBLES ROAD CONSTRUCTION, INC. (0.24)
Contract #08183203
Totals27993542.481216998.406183116.6022.0

CountyTAYLOR
HighwayUS 83
FromUS 277 (S14TH) (FTG RDS& RAMPS ONLY
ToLP 322/US 83 INTERCHANGE
CSJ0034-01-137
Proj IDSTP 2019(984)
Work TypeOVERLAY
 
4451081.560.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193025
Totals4451081.560.000.000.0

CountyNOLAN
HighwayFM 608
FromCR 152
ToFM 2319
CSJ0053-15-024
Proj IDSTP 2018(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.1164261779.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days253
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193023
Totals4261779.480.000.000.0

CountyHOWARD
HighwayUS 87
FromUPRR @ BEALS CREEK
To..
CSJ0068-08-065
Proj IDBR 1802(503)
Work TypeBRIDGE REHAB
 
0.1606661050.95574459.338.6
Work Order11-15-18
Work Began00-00-00
Work Completed
Time Computed01-15-19
Contract Working Days181
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-065
BARRICADES UNLIMITED (0.74)
SCOTT DERR PAINTING CO, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
WILLIS ELECTRIC CO., LP (1.41)
OLYMPUS PAINTING CONTRACTORS, INC. (18.05)
Contract #08183050
Totals6661050.9543027.58574459.338.6

CountyHOWARD
HighwayUS 87
FromWASSON ROAD
To1 MILE NORTH OF RM 33
CSJ0069-01-057
Proj IDNH 2019(640)
Work TypeDRAINAGE WORK
 
1.8931647746.00865047.5052.4
CountyHOWARD
HighwayRM 33
FromWASSON ROAD
ToLONGSHORE DRIVE
CSJ0558-05-013
Proj IDSTP 2019(641)
Work TypeDRAINAGE IMPROVEMENTS
 
0.511218316.30111265.5050.9
Work Order04-08-19
Work Began04-29-19
Work Completed
Time Computed05-01-19
Contract Working Days134
Addl Days Granted0
Working Days Charged53
Percent Time Used39
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0069-01-057
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (14.03)
BLACK JACK ENERGY SERVICES, LLC (35.91)
TEXAS ALTERNATIVE GRASSER INCORPORATED (2.30)
Contract #03193030
Totals1866062.30189023.00976313.0052.3

CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
To2.717 MI S OF FM 2482
CSJ0125-04-029
Proj IDSTP 2019(430)HES
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
15.13031300.740.000.0
CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
ToUS 180 IN ALBANY
CSJ0125-04-033
Proj IDSTP 2019(392)
Work TypeREHABILITATE AND WIDEN ROADWAY
 
17.30812550076.27695217.805.5
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days429
Addl Days Granted0
Working Days Charged37
Percent Time Used8
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-04-029
MURRAY CONSTRUCTION (0.52)
CONTRACTORS SERVICE COMPANY (0.41)
PRIMATE CONSTRUCTION, LP (0.75)
NIXON ENGINEERING (0.21)
HJC FARMS, INC. (1.71)
TOTAL HIGHWAY MAINTENANCE, LLC (1.85)
J & M CONTRACTING, COMPANY (9.58)
TRANSGLOBAL, LLC (0.13)
Contract #01193004
Totals12581377.01660635.00695217.805.5

CountyJONES
HighwayUS 277
FromHASKELL COUNTY LINE
ToFM 1636 (EAST)
CSJ0157-05-060
Proj IDNH 2018(407)
Work TypeSPT RPR,MILL& FILL,1-CST,OVERLAY
 
7.2806432024.479295219.6099.9
Work Order02-14-18
Work Began04-09-18
Work Completed
Time Computed03-15-18
Contract Working Days105
Addl Days Granted115
Working Days Charged230
Percent Time Used104
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-05-060
CONTRACTORS SERVICE COMPANY (0.26)
HJC FARMS, INC. (7.77)
MPB, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (2.22)
ZACK BURKETT CO. (61.45)
FOUTSCO PAVING COMPANY, LLC (7.85)
TEXOP CONSTRUCTION (0.50)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (8.55)
Contract #01183210
Totals6432024.471012075.569295219.6099.9

page 1 | page 2