Monthly State Let Construction Report For Abilene District As Of Nov 12, 2021 Page 1 Of 3

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMITCHELL
HighwayIH 20
FromHOWARD COUNTY LINE
ToFM 670
CSJ0005-07-058
Proj IDNH 2021(178)
Work TypeOVERLAY
 
9.32813256487.762287807.8617.2
CountyMITCHELL
HighwayIH 20
FromFM 670
To.636 MILES TO EAST
CSJ0005-08-108
Proj IDNH 2021(178)
Work TypeOVERLAY
 
0.6361421492.221558.400.1
CountyMITCHELL
HighwayBI 20-H
FromFM 670
ToBI 20H
CSJ0005-11-027
Proj IDSTP 2021(179)
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.00677490.0054255.6070.0
Work Order01-14-21
Work Began05-10-21
Work Completed
Time Computed04-14-21
Contract Working Days325
Addl Days Granted0
Working Days Charged127
Percent Time Used39
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-07-058
BARRICADES UNLIMITED (2.17)
CONTRACTORS SERVICE COMPANY (0.31)
DUSTY ALLEN, INC. (3.07)
HJC FARMS, INC. (2.19)
SCR CIVIL CONSTRUCTION, LLC (0.48)
TEXOP CONSTRUCTION (1.91)
W. S. CONSTRUCTION COMPANY (13.85)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
DUSTIN ALLEN, INC. (3.07)
Contract #12203004
Totals14755469.98539358.022343621.8615.8

CountyNOLAN
HighwayIH 20
FromWEST BU20L
To.14 MILE WEST OF SH 70
CSJ0006-02-121
Proj IDNH 2020(618)
Work TypeOVERLAY
 
9.97720032973.645573463.9227.8
Work Order06-18-20
Work Began09-25-20
Work Completed
Time Computed09-16-20
Contract Working Days604
Addl Days Granted0
Working Days Charged193
Percent Time Used31
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-121
RPV CONSTRUCTION, LLC (4.14)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
FC TRAFFIC CONTROL, INC. (0.79)
HJC FARMS, INC. (1.69)
HERITAGE MATERIALS, LLC (1.19)
MOBILE ENTERPRISES, INC. (0.36)
ACT SAW CUTTING & REMOVAL (0.39)
LINEAR TRAFFIC MARKINGS LLC (1.97)
DIAMOND C LOGISTICS TX LLC (4.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
TEX OP CONSTRUCTION, LP (1.21)
LMN TRANSPORT (1.42)
Contract #03203003
Totals20032973.64259269.625573463.9227.8

CountyNOLAN
HighwayIH 20
FromLOOP 170
To.14 MILES WEST OF SH 70
CSJ0006-02-125
Proj IDC 62-1-25
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2082903813.002958905.6699.9
CountyNOLAN
HighwayIH 20
From.14 MILES WEST SH 70
ToBI 20M EAST
CSJ0006-03-140
Proj IDC 63-1-40
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.2011820640.211823490.7699.9
Work Order09-18-20
Work Began01-22-21
Work Completed
Time Computed09-17-20
Contract Working Days162
Addl Days Granted0
Working Days Charged151
Percent Time Used93
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-125
BARRICADES UNLIMITED (2.82)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30)
ENJ STEEL, LLC (2.23)
Contract #08203222
Totals4724453.2120900.944782396.4299.9

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-085
Proj IDC 6-7-85
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.6814097726.75348697.008.5
Work Order09-18-20
Work Began05-13-21
Work Completed
Time Computed12-16-20
Contract Working Days175
Addl Days Granted0
Working Days Charged80
Percent Time Used45
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-085
CONTRACTORS SERVICE COMPANY (0.54)
STRIPING TECHNOLOGY, L.P. (0.83)
Contract #08203227
Totals4097726.7519500.00348697.008.5

CountyTAYLOR
HighwaySH 351
FromBU 83-D (TREADAWAY ST)
ToIH 20
CSJ0011-01-038
Proj IDNH 2020(354)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.6364596548.001988978.7643.2
Work Order02-04-20
Work Began06-01-20
Work Completed
Time Computed05-04-20
Contract Working Days193
Addl Days Granted0
Working Days Charged157
Percent Time Used81
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-038
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.54)
STREET FOUNDATION DRILLING, INC. (2.34)
WILLIS ELECTRIC CO., LP (9.51)
MOBILE ENTERPRISES, INC. (2.62)
CONTRACTORS SERVICE COMPANY (0.79)
FUSION COMMUNICATIONS, LLC (0.61)
Contract #12193019
Totals4596548.00164755.151988978.7643.2

CountySHACKELFORD
HighwayUS 180
From4TH STREET IN ALBANY
ToSH 351
CSJ0011-05-051
Proj IDSTP 2020(692)
Work TypeREHABILITATION OF EXISTING ROAD
 
10086760.119283332.1192.0
Work Order07-13-20
Work Began09-14-20
Work Completed
Time Computed09-14-20
Contract Working Days257
Addl Days Granted0
Working Days Charged210
Percent Time Used81
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-05-051
CONTRACTORS SERVICE COMPANY (0.32)
D. I. J. CONSTRUCTION, INC. (0.66)
RPV CONSTRUCTION, LLC (6.41)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.68)
G3 DRILLING & BLASTING, INC. (1.18)
WEST TEXAS ROCK RESOURCES, LLC (0.09)
W. S. CONSTRUCTION COMPANY (0.92)
Contract #05203005
Totals10086760.11762667.569283332.1192.0

CountySHACKELFORD
HighwayUS 180
FromALBANY EAST CITY LIMITS
ToSTEPHENS COUNTY LINE
CSJ0011-06-049
Proj IDSTP 2020(172)
Work TypeRESTORATION
 
11.4068259120.382103845.3725.4
Work Order02-20-20
Work Began05-18-20
Work Completed
Time Computed05-18-20
Contract Working Days479
Addl Days Granted0
Working Days Charged307
Percent Time Used64
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-049
BARRICADES UNLIMITED (2.89)
CONTRACTORS SERVICE COMPANY (1.12)
HJC FARMS, INC. (3.14)
HUDSON, INC. SOUTH (1.65)
STRIPE-A-ZONE, INC. (0.33)
W. S. CONSTRUCTION COMPANY (18.34)
THORNTON"S TREE SERVICE, INC. (0.46)
Contract #01203007
Totals8259120.3845810.002103845.3725.4

CountySTONEWALL
HighwayUS 83
FromUS 380
ToUS 83
CSJ0032-07-036
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1006571.706000.000.5
CountySTONEWALL
HighwayUS 83
FromUS 380
ToUS 83
CSJ0106-05-039
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
341606.550.000.0
CountyNOLAN
HighwaySH 70
FromFM 153
ToFM 608
CSJ0264-02-030
Proj IDF 2021(521)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2233854.80204.000.0
Work Order06-10-21
Work Began08-09-21
Work Completed
Time Computed08-09-21
Contract Working Days172
Addl Days Granted0
Working Days Charged29
Percent Time Used16
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0032-07-036
CONTRACTORS SERVICE COMPANY (0.27)
L&H ELECTRICAL, LLC (15.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.23)
J & M CONTRACTING, COMPANY (3.25)
Contract #05213017
Totals3582033.052204.006204.000.1

CountyJONES
HighwayUS 83
FromSH 92 IN HAMLIN
ToUS 277 NORTH OF ANSON
CSJ0033-04-063
Proj IDSTP 1302(059)
Work TypeCONSTRUCT SUPER TWO
 
15.34210819113.5211117153.7199.9
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed01-21-19
Contract Working Days269
Addl Days Granted175
Working Days Charged460
Percent Time Used103
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-063
DOUBLE A CONTRACTING, L.P. (0.35)
CONTRACTORS SERVICE COMPANY (0.74)
A BROTHERS MILLING, LLC (0.76)
HJC FARMS, INC. (4.04)
FLAT LINE, INC. (2.33)
MURRAY CONSTRUCTION (0.62)
W. S. CONSTRUCTION COMPANY (6.32)
4-WAY HAULERS, LLC (0.26)
Contract #09183206
Totals10819113.52154206.7611117153.7199.9

CountyTAYLOR
HighwayBU 83-D
FromNORTH OF HILL ST
ToSOUTH OF HILL ST
CSJ0033-08-043
Proj IDF 2021(737)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
193985.2541864.0021.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-043
FUSION COMMUNICATIONS, LLC (3.76)
Contract #06213035
Totals193985.251916.0041864.0021.5

CountyTAYLOR
HighwayUS 83
FromS OF FM 204(CLARK/REMINGTON RD)
ToFM 707
CSJ0034-01-126
Proj IDNH 1802(506)
Work TypeEMB, FL BS, STRS, AND ACP
 
2.69419355727.8619275494.8499.9
CountyTAYLOR
HighwayUS 83
FromJUST SOUTH OF FM 204
ToUS 83 -US 84 SPLIT
CSJ0034-01-128
Proj IDNH 1802(506)
Work TypeEXC,FLX BS,ACP,OBL PVMT
 
5.9568637814.628407882.8097.3
Work Order11-01-18
Work Began01-21-19
Work Completed
Time Computed01-10-19
Contract Working Days553
Addl Days Granted92
Working Days Charged713
Percent Time Used110
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-126
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
DIIBS SPECIALISTS (0.53)
DK CONTRACTING, LLC (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.55)
SOUTH TEXAS PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
BO SIMON INC (5.28)
DUSTROL, INC. (0.63)
HJC FARMS, INC. (2.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.88)
WILLIS ELECTRIC CO., LP (4.24)
STATEWIDE TRANSPORT, LLC (2.48)
ROBERT FLOYD SUE TRUCKING, INC (0.00)
NSTARRWAY VENTURES, LP (0.18)
WAYNE BRYANT LOGISTICS, LLC (0.24)
NOBLES ROAD CONSTRUCTION, INC. (0.24)
MICA CORPORATION (0.80)
FLAT LINE, INC. (0.00)
HALLIGAN SERVICES LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.03)
FLATWORKS, LLC (0.13)
JB PINNACLE GROUP, LLC (0.83)
RIDGEBACK ASPHALT LIMITED LIABILITY COMPANY (0.28)
SOUTHEAST GRINDING & GROOVING, LLC (0.00)
Contract #08183203
Totals27993542.4881592.2527683377.6499.5

CountyTAYLOR
HighwayUS 83
FromNORTH OF FM 707
ToNEAR ANTILLEY ROAD
CSJ0034-01-127
Proj IDNH 2B20(043)
Work TypeWIDEN FREEWAY
 
1.0303381358.223464585.8399.9
Work Order09-18-20
Work Began12-07-20
Work Completed
Time Computed12-07-20
Contract Working Days255
Addl Days Granted0
Working Days Charged179
Percent Time Used70
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-127
A BROTHERS MILLING, LLC (0.41)
4-WAY HAULERS, LLC (3.29)
CONTRACTORS SERVICE COMPANY (1.23)
DK CONTRACTING, LLC (0.62)
STRIPING TECHNOLOGY, L.P. (1.41)
WILLIS ELECTRIC CO., LP (7.90)
KLP COMMERCIAL, L.L.C. (4.22)
STREET FOUNDATION DRILLING, INC. (0.23)
FLAT LINE, INC. (0.14)
FUSION COMMUNICATIONS, LLC (0.50)
Contract #08203225
Totals3381358.22111086.453464585.8399.9

CountySCURRY
HighwayUS 84
FromREF MRK 386
ToFM 1142
CSJ0053-07-040
Proj IDF 2021(743)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.2883245689.679080.000.2
Work Order08-18-21
Work Began10-12-21
Work Completed
Time Computed10-11-21
Contract Working Days141
Addl Days Granted0
Working Days Charged6
Percent Time Used4
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0053-07-040
WILLIS ELECTRIC CO., LP (4.17)
W. S. CONSTRUCTION COMPANY (2.89)
WEST TEXAS ROCK RESOURCES, LLC (0.13)
AREA WIDE PROTECTIVE, INC. (0.37)
MARCOM"S MOWING SERVICE, LLC (4.95)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.12)
BARRICADES UNLIMITED (2.67)
Contract #07213026
Totals3245689.679080.009080.000.2

CountySCURRY ETC
HighwayUS 84 ETC
From0.23 MILES EAST OF BU 84-G
ToCO RD 466
CSJ0053-09-073
Proj IDF 2021(401)
Work TypeSEAL COAT
 
17.7861432987.401312691.0991.6
Work Order04-29-21
Work Began08-16-21
Work Completed
Time Computed05-31-21
Contract Working Days104
Addl Days Granted0
Working Days Charged86
Percent Time Used82
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0053-09-073
BARRICADES UNLIMITED (4.02)
CONTRACTORS SERVICE COMPANY (2.61)
Contract #03213020
Totals1432987.4013910.001312691.0991.6

CountyNOLAN
HighwayFM 608
FromCR 152
ToFM 2319
CSJ0053-15-024
Proj IDSTP 2018(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.1164261779.483111054.7075.5
Work Order07-16-19
Work Began10-14-19
Work Completed
Time Computed10-14-19
Contract Working Days253
Addl Days Granted5
Working Days Charged368
Percent Time Used142
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-024
CONTRACTORS SERVICE COMPANY (0.84)
HJC FARMS, INC. (2.35)
TOTAL HIGHWAY MAINTENANCE, LLC (3.00)
LONE STAR EROSION CONTROL (0.41)
Contract #05193023
Totals4261779.48143976.503111054.7075.5

CountyHOWARD
HighwayUS 87
FromMARTIN COUNTY LINE
ToNORTH OF CR 50
CSJ0068-07-052
Proj IDF 2021(845)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.9141069252.870.000.0
CountyHOWARD
HighwayUS 87
FromNORTH OF CR 50
ToFM 2230
CSJ0068-08-068
Proj IDF 2021(845)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
9.6991481545.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-29-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213030
Totals2550798.000.000.000.0

CountyHOWARD
HighwayUS 87
From1750 FEET NORTH OF US 87 RELIEF ROUTE
ToCR 36
CSJ0068-08-067
Proj IDF 2021(846)
Work TypeREHABILITATION OF EXISTING ROAD
 
6899249.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days198
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-067
BARRICADES UNLIMITED (1.03)
HJC FARMS, INC. (0.58)
MARCOM"S MOWING SERVICE, LLC (1.03)
REECE CONSTRUCTION CO., INC. (2.55)
SCR CIVIL CONSTRUCTION, LLC (9.20)
TEXOP CONSTRUCTION (0.55)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.12)
Contract #08213219
Totals6899249.890.000.000.0

CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
To2.717 MI S OF FM 2482
CSJ0125-04-029
Proj IDSTP 2019(430)HES
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
15.13031300.7431300.7499.9
CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
ToUS 180 IN ALBANY
CSJ0125-04-033
Proj IDSTP 2019(392)
Work TypeREHABILITATE AND WIDEN ROADWAY
 
17.30812550076.2712674254.0599.9
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days429
Addl Days Granted0
Working Days Charged428
Percent Time Used99
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-04-029
MURRAY CONSTRUCTION (0.52)
CONTRACTORS SERVICE COMPANY (0.41)
PRIMATE CONSTRUCTION, LP (0.75)
NIXON ENGINEERING (0.21)
HJC FARMS, INC. (1.71)
TOTAL HIGHWAY MAINTENANCE, LLC (1.85)
J & M CONTRACTING, COMPANY (9.58)
TRANSGLOBAL, LLC (0.13)
LANCO TURF & SEEDING, INC. (0.02)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (1.53)
Contract #01193004
Totals12581377.010.0012705554.7999.9

CountySHACKELFORD
HighwaySH 6
FromPECAN STREET ALBANY
ToCALLAHAN CO LINE
CSJ0126-01-039
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
17.5739227644.079056371.6798.6
CountyCALLAHAN
HighwaySH 6
FromCALLAHAN CO LINE
ToEASTLAND CO LINE
CSJ0126-02-020
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
2.2833436044.223107904.4090.4
Work Order10-21-19
Work Began12-02-19
Work Completed
Time Computed12-02-19
Contract Working Days322
Addl Days Granted0
Working Days Charged356
Percent Time Used110
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0126-01-039
BLACKTOP INDUSTRIES LLC (3.67)
CHEROKEE SERVICES (0.08)
CONTRACTORS SERVICE COMPANY (0.29)
COPPELL CONSTRUCTION CO., INC. (11.16)
D. I. J. CONSTRUCTION, INC. (1.47)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
MURRAY CONSTRUCTION (0.93)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.14)
AARON CONCRETE CONTRACTORS, L.P. (0.46)
BOWMAN ENGINEERING & CONSULTING, INC. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
SOUTH TEXAS PAINTING COMPANY (0.05)
RPV CONSTRUCTION, LLC (1.54)
W. S. CONSTRUCTION COMPANY (0.16)
Contract #09193203
Totals12663688.2921710.0012164276.0796.4

CountyJONES
HighwayUS 277
FromFM 1636
ToANSON
CSJ0157-05-063
Proj IDC 157-5-63
Work TypeOVERLAY
 
7849211.949181185.5099.9
CountyJONES
HighwayUS 277
FromFM 1636
ToHASKELL CO LINE
CSJ0157-05-064
Proj IDC 157-5-64
Work TypeRESTORATION
 
7335735.035866621.3979.9
Work Order07-07-20
Work Began03-08-21
Work Completed
Time Computed01-07-20
Contract Working Days192
Addl Days Granted0
Working Days Charged122
Percent Time Used63
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-05-063
CHEROKEE SERVICES (0.63)
CONTRACTORS SERVICE COMPANY (0.29)
HJC FARMS, INC. (1.57)
STRIPE-A-ZONE, INC. (0.21)
STRIPING TECHNOLOGY, L.P. (1.97)
Contract #05203203
Totals15184946.97633527.0315047806.8999.0

page 1 | page 2 | page 3