Monthly State Let Construction Report For Abilene District As Of Jun 08, 2018 Page 1 Of 2

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromMARTIN COUNTY LINE
ToNEAR US 87 (WB LANES ONLY)
CSJ0005-05-109
Proj IDNH 2018(341)
Work TypeOVERLAY
 
8.8156798902.474276890.8962.9
Work Order02-14-18
Work Began03-07-18
Work Completed
Time Computed03-07-18
Contract Working Days92
Addl Days Granted0
Working Days Charged58
Percent Time Used63
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-109
CONTRACTORS SERVICE COMPANY (0.27)
DOUBLE A CONTRACTING, L.P. (0.83)
GIBSON & ASSOCIATES, INC. (10.90)
HJC FARMS, INC. (3.72)
RPV CONSTRUCTION (2.22)
SCR CIVIL CONSTRUCTION, LLC (12.91)
TEXOP CONSTRUCTION (1.83)
WOLFE CONSTRUCTION GROUP, INC. (0.09)
Contract #12173012
Totals6798902.472614573.974276890.8962.9

CountyHOWARD
HighwayIH 20
FromIH 20 AND MOORE FIELD ROAD
ToIH 20 AND MORE FIELD ROAD
CSJ0005-05-112
Proj IDBR 1702(476)
Work TypeINSTALL CRASHWALLS
 
1.0047767027.742268702.7329.2
Work Order08-08-17
Work Began10-16-17
Work Completed
Time Computed09-07-17
Contract Working Days309
Addl Days Granted0
Working Days Charged150
Percent Time Used48
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-112
CONTRACTORS SERVICE COMPANY (1.06)
DIIBS SPECIALISTS (0.66)
DOUBLE A CONTRACTING, L.P. (3.12)
GIBSON & ASSOCIATES, INC. (0.47)
MCL CONTRACTING, LLC (1.60)
NELSON INDUSTRIAL SERVICES, INC. (0.08)
PRICE CONSTRUCTION, LTD. (1.34)
S & S BRIDGE PAINTING, INC. (7.03)
TEXAS CURB CUT, LP (0.04)
Contract #07173231
Totals7767027.74420087.772268702.7329.2

CountyHOWARD ETC
HighwayIH 20 ETC
FromAT FM 700
ToFRONTAGE ROADS ONLY
CSJ0005-06-116
Proj IDSTP 2018(314)HES
Work TypeFLASH BEACON,SIGNALS,SIGNS
 
5.1901092202.76366531.9933.5
Work Order12-19-17
Work Began03-19-18
Work Completed
Time Computed02-16-18
Contract Working Days77
Addl Days Granted10
Working Days Charged51
Percent Time Used58
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-116
ALTUS TRAFFIC MANAGEMENT LLC (0.72)
D. I. J. CONSTRUCTION, INC. (3.41)
MEX DRILLING (2.33)
TCB FOUNDATION DRILLERS, INC. (2.39)
WG ENGINEERING & CONSTRUCTION, LLC (6.77)
Contract #11173205
Totals1092202.7695951.16366531.9933.5

CountyHOWARD
HighwayIH 20
FromIH 20 WEST BOUND AT UNION PAC RR
ToIH 20 WEST BOUND AT UNION PAC RR
CSJ0005-06-117
Proj IDBR 1702(598)
Work TypeBRIDGE REHAB
 
0.2401316919.24205695.0915.6
Work Order01-10-18
Work Began04-16-18
Work Completed
Time Computed02-08-18
Contract Working Days99
Addl Days Granted0
Working Days Charged30
Percent Time Used30
Contractor(s)
STRUCTURAL TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-117
S & S BRIDGE PAINTING, INC. (24.55)
TOTAL HIGHWAY MAINTENANCE, LLC (5.40)
SCOTT DERR PAINTING CO, LLC (0.87)
RUBIO"S PAVING (0.34)
HJC FARMS, INC. (4.49)
DUSTROL, INC. (2.67)
STATE CONCRETE, INC. (2.56)
RAMPART HYDRO SERVICES (6.15)
Contract #08173037
Totals1316919.24113340.50205695.0915.6

CountyHOWARD
HighwayIH 20
FromN SCURRY ST
ToMOSS LAKE RD
CSJ0005-06-119
Proj IDSTP 1702(599)HES
Work TypeINSTALL MEDIAN BARRIER
 
11.6611664669.161227830.7073.7
Work Order09-28-17
Work Began02-05-18
Work Completed
Time Computed10-30-17
Contract Working Days93
Addl Days Granted0
Working Days Charged80
Percent Time Used86
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-119
WOLFE CONSTRUCTION GROUP, INC. (0.71)
Contract #08173040
Totals1664669.16451846.001227830.7073.7

CountyHOWARD ETC
HighwayIH 20 ETC
From.4 MILES EAST OF US 87
ToMITCHELL COUNTY LINE
CSJ0005-06-120
Proj IDNH 2018(548)
Work TypeINSTALL PAVEMENT MARKINGS
 
390.6721637144.671595335.6397.4
Work Order03-07-18
Work Began03-12-18
Work Completed
Time Computed03-12-18
Contract Working Days80
Addl Days Granted0
Working Days Charged38
Percent Time Used47
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-06-120
RED SIXTEEN CONSTRUCTION, INC (9.14)
Contract #02183216
Totals1637144.67132908.641595335.6397.4

CountyNOLAN
HighwayIH 20
FromEAST BI 20-M IN SWEETWATER
ToTAYLOR COUNTY LINE
CSJ0006-03-132
Proj IDNH 2017(456)
Work TypeMILL,SPOT REPAIR,UNDERSEAL &OVERLAY
 
12.47714579827.2810179705.5869.8
Work Order05-09-17
Work Began07-10-17
Work Completed
Time Computed07-10-17
Contract Working Days331
Addl Days Granted0
Working Days Charged188
Percent Time Used56
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-132
CONTRACTORS SERVICE COMPANY (0.68)
WEST TEXAS RUMBLE STRIP (0.20)
AARON"S CONCRETE SAWING AND SEALING INC. (0.54)
DOUBLE A CONTRACTING, L.P. (1.65)
DUSTROL, INC. (1.53)
RPV CONSTRUCTION (2.93)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.35)
CHEROKEE SERVICES (0.86)
HJC FARMS, INC. (3.21)
SCR CONSTRUCTION CO., INC. (1.35)
TITAN MILLING INC. (0.99)
Contract #03173237
Totals14579827.281987255.5610179705.5869.8

CountyNOLAN
HighwayIH 20
FromBS 70-G_(I-20 NFR ONLY)
ToEAST ARIZONA AVENUE (IN SWEETWATER)
CSJ0006-03-134
Proj IDNH 2018(584)
Work TypeREHABILITATE EXISTING ROADWAY
 
0.6231487306.6112284.000.8
Work Order04-26-18
Work Began00-00-00
Work Completed
Time Computed05-30-18
Contract Working Days113
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-134
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183236
Totals1487306.6112284.0012284.000.8

CountyTAYLOR
HighwayIH 20
FromAT NOODLE CREEK (IH 20 NFR & SFR)
To0.10 MI E OF FM 1085
CSJ0006-04-072
Proj IDBR 2018(827)
Work TypeUPGRADE BRIDGE AND APPROACH RAILING
 
4.403894985.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-04-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183044
Totals894985.250.000.000.0

CountyTAYLOR
HighwayIH 20
FromIH 20 EAST BOUND LANE
ToAT SH 351(AMBLER AVE IN ABILENE)
CSJ0006-06-099
Proj IDBR 1602(557)
Work TypeREPLACE BRIDGE AND APPROACHES
 
3.93212169359.9512025816.9398.8
CountyTAYLOR
HighwaySH 351
FromEAST STAMFORD STREET
ToEAST OVERLAND STREET
CSJ0011-01-035
Proj IDNH 1602(559)
Work TypeEXC,EMB, CONC PAV
 
0.1802469640.052443728.5498.9
Work Order11-29-16
Work Began03-20-17
Work Completed
Time Computed12-29-16
Contract Working Days445
Addl Days Granted0
Working Days Charged314
Percent Time Used70
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-099
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
DUSTIN ALLEN, INC. (1.19)
A BROTHERS MILLING, LLC (0.69)
STRIPE-A-ZONE, INC. (2.11)
NOBLES ROAD CONSTRUCTION, INC. (23.37)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.85)
WILLIS ELECTRIC CO., LP (2.41)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.88)
MCL CONTRACTING, LLC (0.09)
MCL CONTRACTING, LLC (0.83)
BRENDA CONSTRUCTION (4.15)
UNDER CONSTRUCTION INC. (0.31)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.08)
HJC FARMS, INC. (0.26)
NORTH TEXAS BOMANITE, INC. (0.19)
JE CASEY, LLC (0.08)
Contract #10163008
Totals14639000.0026487.7014469545.4798.8

CountyCALLAHAN
HighwayIH 20
FromTAYLOR COUNTY LINE
ToEAST OF FM 1707
CSJ0006-07-079
Proj IDC 6-7-79
Work TypeMILL AND OVERLAY
 
6.6937087728.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183252
Totals7087728.070.000.000.0

CountyCALLAHAN ETC
HighwayFM 18 ETC
FromTAYLOR C/L
ToBI 20T
CSJ0006-11-022
Proj IDSTP 2018(554)HESG
Work TypePROFILE EDGELINE MARKINGS
 
350.0891810774.91935049.1451.6
Work Order03-08-18
Work Began04-16-18
Work Completed
Time Computed04-06-18
Contract Working Days63
Addl Days Granted0
Working Days Charged35
Percent Time Used55
Contractor(s)
SURFACE PREPARATION TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-11-022
PMI PAVEMENT MARKING, INC. (65.04)
Contract #02183007
Totals1810774.91633721.06935049.1451.6

CountyNOLAN ETC
HighwayBI 20-L ETC
From0.8 MILE NORTH OF IH 20
To1.2 MILES NORTH OF IH 20
CSJ0006-14-004
Proj IDSTP 2017(834)HES
Work TypeSURFACE TREAT AND INSTALL CHEVRONS
 
23.2231848432.221850493.4699.9
Work Order05-18-17
Work Began09-20-17
Work Completed
Time Computed08-16-17
Contract Working Days90
Addl Days Granted30
Working Days Charged117
Percent Time Used97
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-14-004
WILLIS ELECTRIC CO., LP (33.43)
HJC FARMS, INC. (16.58)
THORNTON"S TREE SERVICE, INC. (0.97)
Contract #03173026
Totals1848432.227061.241850493.4699.9

CountyNOLAN
HighwayBI 20-M
FromAT THE UPRR
ToIN SWEETWATER (PSN 044)
CSJ0006-15-034
Proj IDBR 1702(521)
Work TypeREPLACE BRIDGE
 
0.3604949400.00440885.008.9
Work Order03-23-18
Work Began05-21-18
Work Completed
Time Computed05-21-18
Contract Working Days139
Addl Days Granted0
Working Days Charged4
Percent Time Used2
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-034
A BROTHERS MILLING, LLC (0.17)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.29)
BOWMAN ENGINEERING & CONSULTING, INC (0.68)
DK CONTRACTING, LLC (0.16)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
RPV CONSTRUCTION (1.68)
SOUTH TEXAS PAINTING COMPANY (0.19)
TERRACON CONSULTANTS, INC. (2.02)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94)
URBAN INFRACONSTRUCTION, LLC. (7.73)
BARRICADES UNLIMITED (0.63)
WILLIS ELECTRIC CO., LP (1.48)
TOTAL HIGHWAY MAINTENANCE, LLC (0.33)
NOBLES ROAD CONSTRUCTION, INC. (15.76)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.07)
Contract #01183026
Totals4949400.00440885.00440885.008.9

CountyTAYLOR
HighwayBI 20-R
FromUS 83 (WINTERS FWY)
ToNEAR NEWMAN ROAD
CSJ0006-18-058
Proj IDC 6-18-58
Work TypeMILL & FILL W/ 1-CST AND SMA
 
6.5335844817.840.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183018
Totals5844817.840.000.000.0

CountyCALLAHAN
HighwayIH 20
FromNEAR BAIRD WEST CITY LIMIT_(WBL)
ToAPPROX 0.3 MI E OF MEXIA CREEK
CSJ0007-01-054
Proj IDNH 2017(855)
Work TypeOVERLAY
 
17.5828248492.448659952.9499.9
Work Order05-18-17
Work Began07-17-17
Work Completed
Time Computed07-17-17
Contract Working Days303
Addl Days Granted0
Working Days Charged176
Percent Time Used58
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-054
DOUBLE A CONTRACTING, L.P. (0.28)
CONTRACTORS SERVICE COMPANY (0.28)
TOTAL HIGHWAY MAINTENANCE, LLC (1.05)
A BROTHERS MILLING, LLC (2.59)
HJC FARMS, INC. (12.03)
VELASQUEZ CONCRETE (1.01)
SCR CIVIL CONSTRUCTION, LLC (0.84)
Contract #04173009
Totals8248492.44168575.008659952.9499.9

CountyTAYLOR
HighwaySH 351
FromBU 83-D (TREADAWAY ST)
ToRAINY CREEK
CSJ0011-01-036
Proj IDC 11-1-36
Work TypeMILL,SPOT REPAIR & OVERLAY
 
1.5441708497.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-036
O. TREVINO CONSTRUCTION, LLC (3.31)
W.O.E. CONSTRUCTION (0.31)
DIIBS SPECIALISTS (1.09)
WILLIS ELECTRIC CO., LP (6.22)
Contract #03183027
Totals1708497.380.000.000.0

CountyJONES
HighwayUS 83
FromSH 92
ToHAMLIN NORTH CITY LIMITS
CSJ0033-03-029
Proj IDSTP 1702(131)
Work TypeCEMENT TRT BASE,1-CST,6" MILL
 
2.7524161245.373416523.5282.1
Work Order06-07-17
Work Began10-12-17
Work Completed
Time Computed07-06-17
Contract Working Days242
Addl Days Granted18
Working Days Charged181
Percent Time Used69
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-03-029
BRENDA CONSTRUCTION (6.51)
CONTRACTORS SERVICE COMPANY (1.54)
DOUBLE A CONTRACTING, L.P. (1.99)
DUSTROL, INC. (1.92)
HJC FARMS, INC. (2.66)
TOTAL HIGHWAY MAINTENANCE, LLC (0.58)
Contract #05173221
Totals4161245.371207753.373416523.5282.1

CountyJONES
HighwayUS 83
FromFM 707
To0.57 MI SOUTH OF FM 1082
CSJ0033-05-091
Proj IDNH 2018(499)
Work TypeRESTORATION OF EXISTING ROAD
 
10.4265078876.003761848.8974.0
Work Order02-14-18
Work Began03-21-18
Work Completed
Time Computed03-15-18
Contract Working Days110
Addl Days Granted0
Working Days Charged47
Percent Time Used42
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-091
DOUBLE A CONTRACTING, L.P. (0.36)
HJC FARMS, INC. (1.95)
CONTRACTORS SERVICE COMPANY (0.31)
A BROTHERS MILLING, LLC (1.41)
FLAT LINE, INC. (0.82)
Contract #01183020
Totals5078876.001928544.433761848.8974.0

CountyJONES ETC
HighwayUS 83 ETC
FromFM 707
ToTAYLOR COUNTY LINE
CSJ0033-05-092
Proj IDNH 2018(342)
Work TypeSEAL COAT
 
228.7759187304.691501414.2416.3
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed02-08-18
Contract Working Days88
Addl Days Granted0
Working Days Charged11
Percent Time Used12
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-05-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173007
Totals9187304.69289566.861501414.2416.3

page 1 | page 2