Monthly State Let Construction Report For Abilene District As Of Nov 12, 2019 Page 1 Of 2

Last Update: Tuesday, November 12, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD ETC
HighwayIH 20
From.408 MI WEST OF CAUBLE RD
ToN SCURRY STREET
CSJ0005-05-114
Proj IDSTP 1902(336)HES
Work TypeSFT
 
23.8765297532.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-114
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193013
Totals5297532.080.000.000.0

CountyMITCHELL
HighwayIH 20
FromEAST OF THE UPRR OVERPASS
ToJUST EAST OF CR 424 UNDERPASS
CSJ0006-01-100
Proj IDNH 2019(391)
Work TypeOBLITERATE EXIST PAVEMENT
 
1.250328277.70290349.8588.4
Work Order02-20-19
Work Began04-22-19
Work Completed
Time Computed04-22-19
Contract Working Days93
Addl Days Granted0
Working Days Charged85
Percent Time Used91
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0006-01-100
DOUBLE A CONTRACTING, L.P. (5.38)
HJC FARMS, INC. (28.46)
TEXAS ALTERNATIVE GRASSER INCORPORATED (2.13)
CONTRACTORS SERVICE COMPANY (5.33)
Contract #01193233
Totals328277.700.00290349.8588.4

CountyNOLAN
HighwayIH 20
FromMITCHELL CO LINE
ToBI 20-L IN ROSCOE
CSJ0006-02-115
Proj IDNH 2019(522)
Work Type2" MILL & FILL, 1 CST AND 2" SMA D
 
6.4068705662.151255855.8514.4
CountyNOLAN
HighwayIH 20
From.14 MILE WEST OF SH 70
ToEAST BI 20 M
CSJ0006-03-135
Proj IDNH 2019(522)
Work TypeMILL, SPOT REPAIR, UNDERSEAL, OVER
 
3.6997005858.11195417.502.7
CountyNOLAN
HighwayIH 20
FromBS70/SH70
ToSH70
CSJ0006-03-136
Proj IDSTP 2019(639)HES
Work TypeINSTALL MEDIAN BARRIER FLATTEN SLOP
 
2.771800300.000.000.0
Work Order04-25-19
Work Began09-11-19
Work Completed
Time Computed05-28-19
Contract Working Days165
Addl Days Granted0
Working Days Charged37
Percent Time Used22
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-115
A BROTHERS MILLING, LLC (1.24)
CHEROKEE SERVICES (0.24)
CONTRACTORS SERVICE COMPANY (0.50)
DOUBLE A CONTRACTING, L.P. (2.85)
HJC FARMS, INC. (8.26)
RPV CONSTRUCTION, LLC (3.57)
Contract #03193206
Totals16511820.26265085.901451273.358.7

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-080
Proj IDNH 2019(920)
Work TypeOVERLAY
 
6.22010684704.91665907.086.2
Work Order06-17-19
Work Began10-21-19
Work Completed
Time Computed09-16-19
Contract Working Days310
Addl Days Granted0
Working Days Charged29
Percent Time Used9
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-080
CONTRACTORS SERVICE COMPANY (0.39)
AREA WIDE PROTECTIVE, INC. (0.98)
PRIMATE CONSTRUCTION, LP (0.30)
TOTAL HIGHWAY MAINTENANCE, LLC (1.18)
BLACKTOP INDUSTRIES LLC (5.71)
Contract #05193035
Totals10684704.91665907.08665907.086.2

CountyNOLAN
HighwayBI 20-M
FromAT THE UPRR
ToIN SWEETWATER (PSN 044)
CSJ0006-15-034
Proj IDBR 1702(521)
Work TypeREPLACE BRIDGE
 
0.3604949400.005070280.8899.9
Work Order03-23-18
Work Began05-21-18
Work Completed
Time Computed05-21-18
Contract Working Days139
Addl Days Granted8
Working Days Charged146
Percent Time Used99
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-034
A BROTHERS MILLING, LLC (0.17)
AVANZA CONSTRUCTION & EARTHWORKS, LLC (0.29)
BOWMAN ENGINEERING & CONSULTING, INC. (0.68)
DK CONTRACTING, LLC (0.16)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
RPV CONSTRUCTION (1.68)
SOUTH TEXAS PAINTING COMPANY (0.19)
TERRACON CONSULTANTS, INC. (2.02)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.94)
URBAN INFRACONSTRUCTION, LLC. (7.73)
BARRICADES UNLIMITED (0.63)
WILLIS ELECTRIC CO., LP (1.48)
TOTAL HIGHWAY MAINTENANCE, LLC (0.33)
NOBLES ROAD CONSTRUCTION, INC. (15.76)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.07)
TEXAS SHAFTS, INC. (3.66)
ASSOCIATED CUTTING, INC. (0.42)
CHOCTAW ERECTORS, INC. (4.63)
MCL CONTRACTING, LLC (0.24)
WEBBER BARRIER SERVICES, LLC. (1.09)
ERNESTO CASTRO (0.35)
TEXAS STUD WELDING (0.06)
Contract #01183026
Totals4949400.00106473.555070280.8899.9

CountyTAYLOR
HighwayBI 20-R
FromUS 83 (WINTERS FWY)
ToNEAR NEWMAN ROAD
CSJ0006-18-058
Proj IDC 6-18-58
Work TypeMILL & FILL W/ 1-CST AND SMA
 
6.5335844817.844724337.9181.6
Work Order07-31-18
Work Began09-06-18
Work Completed
Time Computed08-30-18
Contract Working Days162
Addl Days Granted2
Working Days Charged209
Percent Time Used127
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-058
FLAT LINE, INC. (2.42)
WILLIS ELECTRIC CO., LP (9.18)
HJC FARMS, INC. (2.99)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.82)
SCR CIVIL CONSTRUCTION, LLC (4.05)
CONTRACTORS SERVICE COMPANY (0.71)
WOLFE CONSTRUCTION GROUP, INC. (0.21)
FUSION COMMUNICATIONS, LLC (1.20)
DUSTROL, INC. (1.01)
Contract #05183018
Totals5844817.84218751.564724337.9181.6

CountyJONES
HighwayUS 83
FromSH 92 IN HAMLIN
ToUS 277 NORTH OF ANSON
CSJ0033-04-063
Proj IDSTP 1302(059)
Work TypeCONSTRUCT SUPER TWO
 
15.34210819113.522186752.6320.2
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed01-21-19
Contract Working Days269
Addl Days Granted0
Working Days Charged171
Percent Time Used63
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-063
DOUBLE A CONTRACTING, L.P. (0.35)
CONTRACTORS SERVICE COMPANY (0.74)
A BROTHERS MILLING, LLC (0.76)
HJC FARMS, INC. (4.04)
FLAT LINE, INC. (2.33)
MURRAY CONSTRUCTION (0.62)
W. S. CONSTRUCTION COMPANY (6.32)
Contract #09183206
Totals10819113.52699237.732186752.6320.2

CountyTAYLOR
HighwayUS 83
FromS OF FM 204(CLARK/REMINGTON RD)
ToFM 707
CSJ0034-01-126
Proj IDNH 1802(506)
Work TypeEMB, FL BS, STRS, AND ACP
 
2.69419355727.865195507.2126.8
CountyTAYLOR
HighwayUS 83
FromJUST SOUTH OF FM 204
ToUS 83 -US 84 SPLIT
CSJ0034-01-128
Proj IDNH 1802(506)
Work TypeEXC,FLX BS,ACP,OBL PVMT
 
5.9568637814.624126051.3547.7
Work Order11-01-18
Work Began01-21-19
Work Completed
Time Computed01-10-19
Contract Working Days553
Addl Days Granted0
Working Days Charged204
Percent Time Used36
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-126
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
DIIBS SPECIALISTS (0.53)
DK CONTRACTING, LLC (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.55)
SOUTH TEXAS PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
BO SIMON INC (5.28)
DUSTROL, INC. (0.63)
HJC FARMS, INC. (2.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.88)
WILLIS ELECTRIC CO., LP (4.24)
STATEWIDE TRANSPORT, LLC (2.48)
ROBERT FLOYD SUE TRUCKING, INC (0.00)
NSTARRWAY VENTURES, LP (0.18)
WAYNE BRYANT LOGISTICS, LLC (0.24)
NOBLES ROAD CONSTRUCTION, INC. (0.24)
MICA CORPORATION (0.80)
Contract #08183203
Totals27993542.48837443.349321558.5633.2

CountyTAYLOR
HighwayUS 83
FromUS 277 (S14TH) (FTG RDS& RAMPS ONLY
ToLP 322/US 83 INTERCHANGE
CSJ0034-01-137
Proj IDSTP 2019(984)
Work TypeOVERLAY
 
4451081.560.000.0
Work Order07-23-19
Work Began00-00-00
Work Completed
Time Computed08-23-19
Contract Working Days64
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193025
Totals4451081.560.000.000.0

CountyNOLAN
HighwayFM 608
FromCR 152
ToFM 2319
CSJ0053-15-024
Proj IDSTP 2018(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.1164261779.48327966.487.6
Work Order07-16-19
Work Began10-14-19
Work Completed
Time Computed10-14-19
Contract Working Days253
Addl Days Granted0
Working Days Charged11
Percent Time Used4
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-024
CONTRACTORS SERVICE COMPANY (0.84)
HJC FARMS, INC. (2.35)
TOTAL HIGHWAY MAINTENANCE, LLC (3.00)
Contract #05193023
Totals4261779.48327966.48327966.487.6

CountyHOWARD
HighwayUS 87
FromUPRR @ BEALS CREEK
To..
CSJ0068-08-065
Proj IDBR 1802(503)
Work TypeBRIDGE REHAB
 
0.1606661050.951304001.1819.5
Work Order11-15-18
Work Began10-14-19
Work Completed
Time Computed01-15-19
Contract Working Days181
Addl Days Granted0
Working Days Charged11
Percent Time Used6
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-065
BARRICADES UNLIMITED (0.74)
SCOTT DERR PAINTING CO, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
WILLIS ELECTRIC CO., LP (1.41)
OLYMPUS PAINTING CONTRACTORS, INC. (18.05)
CHOCTAW ERECTORS, INC. (0.49)
Contract #08183050
Totals6661050.95729541.851304001.1819.5

CountyHOWARD
HighwayUS 87
FromWASSON ROAD
To1 MILE NORTH OF RM 33
CSJ0069-01-057
Proj IDNH 2019(640)
Work TypeDRAINAGE WORK
 
1.8931647746.001169152.5070.9
CountyHOWARD
HighwayRM 33
FromWASSON ROAD
ToLONGSHORE DRIVE
CSJ0558-05-013
Proj IDSTP 2019(641)
Work TypeDRAINAGE IMPROVEMENTS
 
0.511218316.30136837.5062.6
Work Order04-08-19
Work Began04-29-19
Work Completed
Time Computed05-01-19
Contract Working Days134
Addl Days Granted0
Working Days Charged113
Percent Time Used84
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0069-01-057
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (14.03)
BLACK JACK ENERGY SERVICES, LLC (35.91)
TEXAS ALTERNATIVE GRASSER INCORPORATED (2.30)
Contract #03193030
Totals1866062.3042537.501305990.0069.9

CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
To2.717 MI S OF FM 2482
CSJ0125-04-029
Proj IDSTP 2019(430)HES
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
15.13031300.740.000.0
CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
ToUS 180 IN ALBANY
CSJ0125-04-033
Proj IDSTP 2019(392)
Work TypeREHABILITATE AND WIDEN ROADWAY
 
17.30812550076.271803485.5814.3
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days429
Addl Days Granted0
Working Days Charged97
Percent Time Used22
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-04-029
MURRAY CONSTRUCTION (0.52)
CONTRACTORS SERVICE COMPANY (0.41)
PRIMATE CONSTRUCTION, LP (0.75)
NIXON ENGINEERING (0.21)
HJC FARMS, INC. (1.71)
TOTAL HIGHWAY MAINTENANCE, LLC (1.85)
J & M CONTRACTING, COMPANY (9.58)
TRANSGLOBAL, LLC (0.13)
Contract #01193004
Totals12581377.01938569.781803485.5814.3

CountySHACKELFORD
HighwaySH 6
FromPECAN STREET ALBANY
ToCALLAHAN CO LINE
CSJ0126-01-039
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
17.5739227644.070.000.0
CountyCALLAHAN
HighwaySH 6
FromCALLAHAN CO LINE
ToEASTLAND CO LINE
CSJ0126-02-020
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
2.2833436044.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days322
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0126-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193203
Totals12663688.290.000.000.0

CountyFISHER
HighwayUS 180
FromALKALI CREEK
To.
CSJ0296-02-033
Proj IDBR 2018(951)
Work TypeBRIDGE REPLACEMENT
 
0.1461763518.631764921.0899.9
Work Order07-19-18
Work Began09-17-18
Work Completed
Time Computed09-17-18
Contract Working Days200
Addl Days Granted0
Working Days Charged159
Percent Time Used79
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0296-02-033
HJC FARMS, INC. (12.09)
BARRICADES UNLIMITED (1.79)
WOLFE CONSTRUCTION GROUP, INC. (0.33)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.93)
TEX OP CONSTRUCTION, LP (0.97)
CONTRACTORS SERVICE COMPANY (0.65)
GARY A. CRAIN, INC. (0.19)
RUNNING HORSE CONSTRUCTION, INC. (1.41)
Contract #06183223
Totals1763518.630.001764921.0899.9

CountyFISHER
HighwayUS 180
FromFM 57
ToUS 180
CSJ0296-03-038
Proj IDBR 2019(982)
Work TypeBR
 
0.5434583865.380.000.0
CountyFISHER
HighwayFM 57
FromSH 70
ToUS 180
CSJ0317-01-037
Proj IDSTP 2019(985)
Work TypeWIDEN NON-FREEWAY
 
12.39612063124.230.000.0
CountyFISHER
HighwayFM 57
FromPLUM CREEK
To.
CSJ0317-01-038
Proj IDBR 2019(983)
Work TypeBR
 
1930380.930.000.0
Work Order07-16-19
Work Began10-16-19
Work Completed
Time Computed10-15-19
Contract Working Days673
Addl Days Granted0
Working Days Charged9
Percent Time Used1
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0296-03-038
A BROTHERS MILLING, LLC (0.84)
BARRICADES UNLIMITED (1.15)
LINDAMOOD DEMOLITION, INC. (0.92)
SCOTT DERR PAINTING CO, LLC (0.23)
WEST TEXAS ROCK RESOURCES, LLC (0.05)
WILLIS ELECTRIC CO., LP (0.76)
BLACKTOP INDUSTRIES LLC (2.19)
BOWMAN ENGINEERING & CONSULTING, INC. (0.27)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.04)
Contract #06193009
Totals18577370.540.000.000.0

CountyJONES
HighwayUS 180
FromFM 1226
ToSHACKELFORD COUNTY LINE
CSJ0296-05-034
Proj IDSTP 2019(393)
Work TypeBASE REPAIR LEVEL UP AND OVERLAY
 
11.0357597359.931036774.2413.6
Work Order02-25-19
Work Began06-03-19
Work Completed
Time Computed03-27-19
Contract Working Days332
Addl Days Granted0
Working Days Charged106
Percent Time Used31
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-05-034
CONTRACTORS SERVICE COMPANY (0.77)
STRIPE-A-ZONE, INC. (0.45)
HJC FARMS, INC. (8.96)
FLAT LINE, INC. (2.09)
J & M CONTRACTING, COMPANY (5.08)
Contract #01193040
Totals7597359.93332621.031036774.2413.6

CountyCALLAHAN
HighwayUS 283
FromIH 20
ToAPPROX .25 MILES NORTH OF IH 20
CSJ0437-02-014
Proj IDSTP 2018(312)
Work TypeREHABILITATION
 
1.8703117046.362990209.5197.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began02-06-18
Work Completed
Time Computed02-06-18
Contract Working Days179
Addl Days Granted0
Working Days Charged224
Percent Time Used125
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0437-02-014
CONTRACTORS SERVICE COMPANY (1.52)
WOLFE CONSTRUCTION GROUP, INC. (0.20)
WEST TEXAS RUMBLE STRIP (0.14)
TEXAS ALTERNATIVE GRASSER, INC. (0.02)
O. TREVINO CONSTRUCTION, LLC (24.68)
HJC FARMS, INC. (1.21)
WILLIS ELECTRIC CO., LP (1.15)
STRIPING TECHNOLOGY, L.P. (2.06)
Contract #12173005
Totals3117046.360.002990209.5197.3

CountyJONES ETC
HighwayFM 707 ETC
FromUS 83
ToFM 605
CSJ0484-01-023
Proj IDSTP 1802(504)HES
Work TypeWIDEN ROADWAY
 
32.44313833694.006901813.2449.8
Work Order09-24-18
Work Began10-23-18
Work Completed
Time Computed10-23-18
Contract Working Days648
Addl Days Granted0
Working Days Charged234
Percent Time Used36
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0484-01-023
A BROTHERS MILLING, LLC (0.09)
CONTRACTORS SERVICE COMPANY (0.69)
HJC FARMS, INC. (1.57)
DOUBLE A CONTRACTING, L.P. (3.18)
MURRAY CONSTRUCTION (1.06)
THORNTON"S TREE SERVICE, INC. (2.34)
Contract #08183009
Totals13833694.00813013.936901813.2449.8

CountyHOWARD
HighwayFM 700
FromAT US 87
To.
CSJ0668-04-004
Proj IDSTP 2019(922)
Work TypeINC
 
0.6007761125.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days286
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0668-04-004
ALAMO BROTHERS CONCRETE INC (5.16)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.28)
BARRICADES UNLIMITED (0.65)
BLACK JACK ENERGY SERVICES, LLC (12.40)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.27)
SLATON BROTHERS, INC. (7.64)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC. (0.07)
Contract #07193220
Totals7761125.500.000.000.0

page 1 | page 2