Monthly State Let Construction Report For Abilene District As Of Jan 11, 2021 Page 1 Of 3

Last Update: Monday, January 11, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD ETC
HighwayIH 20
From.408 MI WEST OF CAUBLE RD
ToN SCURRY STREET
CSJ0005-05-114
Proj IDSTP 1902(336)HES
Work TypeSFT
 
23.8765297532.084885047.1292.2
Work Order09-18-19
Work Began05-08-20
Work Completed
Time Computed12-18-19
Contract Working Days187
Addl Days Granted0
Working Days Charged177
Percent Time Used94
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-114
FOX CONTRACTING KY, INC. (18.72)
BARRICADES UNLIMITED (0.78)
Contract #08193013
Totals5297532.0829820.004885047.1292.2

CountyMITCHELL
HighwayIH 20
FromHOWARD COUNTY LINE
ToFM 670
CSJ0005-07-058
Proj IDNH 2021(178)
Work TypeOVERLAY
 
9.32813256487.760.000.0
CountyMITCHELL
HighwayIH 20
FromFM 670
To.636 MILES TO EAST
CSJ0005-08-108
Proj IDNH 2021(178)
Work TypeOVERLAY
 
0.6361421492.220.000.0
CountyMITCHELL
HighwayBI 20-H
FromFM 670
ToBI 20H
CSJ0005-11-027
Proj IDSTP 2021(179)
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.00677490.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days325
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-07-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12203004
Totals14755469.980.000.000.0

CountyNOLAN
HighwayIH 20
FromMITCHELL CO LINE
ToBI 20-L IN ROSCOE
CSJ0006-02-115
Proj IDNH 2019(522)
Work Type2" MILL & FILL, 1 CST AND 2" SMA D
 
6.4068705662.158601551.2798.8
CountyNOLAN
HighwayIH 20
From.14 MILE WEST OF SH 70
ToEAST BI 20 M
CSJ0006-03-135
Proj IDNH 2019(522)
Work TypeMILL, SPOT REPAIR, UNDERSEAL, OVER
 
3.6997005858.114536137.2864.7
CountyNOLAN
HighwayIH 20
FromBS70/SH70
ToSH70
CSJ0006-03-136
Proj IDSTP 2019(639)HES
Work TypeINSTALL MEDIAN BARRIER FLATTEN SLOP
 
2.771800300.000.000.0
Work Order04-25-19
Work Began09-11-19
Work Completed
Time Computed05-28-19
Contract Working Days165
Addl Days Granted165
Working Days Charged268
Percent Time Used81
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-115
A BROTHERS MILLING, LLC (1.24)
CHEROKEE SERVICES (0.24)
CONTRACTORS SERVICE COMPANY (0.50)
DOUBLE A CONTRACTING, L.P. (2.85)
HJC FARMS, INC. (8.26)
RPV CONSTRUCTION, LLC (3.57)
FLAT LINE, INC. (0.04)
Contract #03193206
Totals16511820.261157016.3513137688.5579.5

CountyNOLAN
HighwayIH 20
FromWEST BU20L
To.14 MILE WEST OF SH 70
CSJ0006-02-121
Proj IDNH 2020(618)
Work TypeOVERLAY
 
9.97720032973.641438081.307.1
Work Order06-18-20
Work Began09-25-20
Work Completed
Time Computed09-16-20
Contract Working Days604
Addl Days Granted0
Working Days Charged45
Percent Time Used7
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-121
RPV CONSTRUCTION, LLC (4.14)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
FC TRAFFIC CONTROL, INC. (0.79)
HJC FARMS, INC. (1.69)
HERITAGE MATERIALS, LLC (1.19)
MOBILE ENTERPRISES, INC. (0.36)
ACT SAW CUTTING & REMOVAL (0.39)
LINEAR TRAFFIC MARKINGS LLC (1.97)
DIAMOND C LOGISTICS TX LLC (4.21)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.19)
Contract #03203003
Totals20032973.6460566.001438081.307.1

CountyNOLAN
HighwayIH 20
FromLOOP 170
To.14 MILES WEST OF SH 70
CSJ0006-02-125
Proj IDC 62-1-25
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.2082903813.00266015.209.1
CountyNOLAN
HighwayIH 20
From.14 MILES WEST SH 70
ToBI 20M EAST
CSJ0006-03-140
Proj IDC 63-1-40
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.2011820640.210.000.0
Work Order09-18-20
Work Began00-00-00
Work Completed
Time Computed09-17-20
Contract Working Days162
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-125
BARRICADES UNLIMITED (2.82)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.30)
ENJ STEEL, LLC (2.23)
Contract #08203222
Totals4724453.21266015.20266015.205.6

CountyNOLAN ETC
HighwayIH 20 ETC
From0.159 MI WEST OF SH 70
ToCO RD 131
CSJ0006-03-137
Proj IDNH 2021(180)
Work TypeSEAL COAT
 
422.57912805207.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days104
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-137
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12203007
Totals12805207.180.000.000.0

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-080
Proj IDNH 2019(920)
Work TypeOVERLAY
 
6.22010684704.919275171.3486.8
Work Order06-17-19
Work Began10-21-19
Work Completed
Time Computed09-16-19
Contract Working Days310
Addl Days Granted0
Working Days Charged281
Percent Time Used90
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-080
CONTRACTORS SERVICE COMPANY (0.39)
AREA WIDE PROTECTIVE, INC. (0.98)
PRIMATE CONSTRUCTION, LP (0.30)
TOTAL HIGHWAY MAINTENANCE, LLC (1.18)
BLACKTOP INDUSTRIES LLC (5.71)
AARON CONCRETE CONTRACTORS, L.P. (1.18)
W. S. CONSTRUCTION COMPANY (2.88)
Contract #05193035
Totals10684704.91103888.009275171.3486.8

CountyCALLAHAN
HighwayIH 20
FromEAST OF 1707
ToBAIRD CITY LIMITS
CSJ0006-07-085
Proj IDC 6-7-85
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.6814097726.750.000.0
Work Order09-18-20
Work Began00-00-00
Work Completed
Time Computed12-16-20
Contract Working Days175
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203227
Totals4097726.750.000.000.0

CountyTAYLOR
HighwaySH 351
FromBU 83-D (TREADAWAY ST)
ToIH 20
CSJ0011-01-038
Proj IDNH 2020(354)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.6364596548.001029264.6822.3
Work Order02-04-20
Work Began06-01-20
Work Completed
Time Computed05-04-20
Contract Working Days193
Addl Days Granted0
Working Days Charged112
Percent Time Used58
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-038
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.54)
STREET FOUNDATION DRILLING, INC. (2.34)
WILLIS ELECTRIC CO., LP (9.51)
MOBILE ENTERPRISES, INC. (2.62)
CONTRACTORS SERVICE COMPANY (0.79)
FUSION COMMUNICATIONS, LLC (0.61)
Contract #12193019
Totals4596548.008787.061029264.6822.3

CountySHACKELFORD
HighwayUS 180
From4TH STREET IN ALBANY
ToSH 351
CSJ0011-05-051
Proj IDSTP 2020(692)
Work TypeREHABILITATION OF EXISTING ROAD
 
10086760.111548166.0015.3
Work Order07-13-20
Work Began09-14-20
Work Completed
Time Computed09-14-20
Contract Working Days257
Addl Days Granted0
Working Days Charged61
Percent Time Used23
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-05-051
CONTRACTORS SERVICE COMPANY (0.32)
D. I. J. CONSTRUCTION, INC. (0.66)
RPV CONSTRUCTION, LLC (6.41)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.68)
G3 DRILLING & BLASTING, INC. (1.18)
Contract #05203005
Totals10086760.11211930.001548166.0015.3

CountySHACKELFORD
HighwayUS 180
FromALBANY EAST CITY LIMITS
ToSTEPHENS COUNTY LINE
CSJ0011-06-049
Proj IDSTP 2020(172)
Work TypeRESTORATION
 
11.4068259120.38870202.0510.5
Work Order02-20-20
Work Began05-18-20
Work Completed
Time Computed05-18-20
Contract Working Days479
Addl Days Granted0
Working Days Charged136
Percent Time Used28
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-049
BARRICADES UNLIMITED (2.89)
CONTRACTORS SERVICE COMPANY (1.12)
HJC FARMS, INC. (3.14)
HUDSON, INC. SOUTH (1.65)
STRIPE-A-ZONE, INC. (0.33)
W. S. CONSTRUCTION COMPANY (18.34)
Contract #01203007
Totals8259120.38104558.75870202.0510.5

CountySTONEWALL
HighwayUS 83
FromAT DOUBLE MTN FORK OF BRAZOS RIVER
To.
CSJ0033-01-040
Proj IDBR 1802(318)
Work TypeBRIDGE REPLACEMENT
 
0.1374007232.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-15-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days358
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0033-01-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11203216
Totals4007232.000.000.000.0

CountyJONES
HighwayUS 83
FromSH 92 IN HAMLIN
ToUS 277 NORTH OF ANSON
CSJ0033-04-063
Proj IDSTP 1302(059)
Work TypeCONSTRUCT SUPER TWO
 
15.34210819113.525922939.1554.7
Work Order10-22-18
Work Began01-21-19
Work Completed
Time Computed01-21-19
Contract Working Days269
Addl Days Granted175
Working Days Charged362
Percent Time Used81
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-063
DOUBLE A CONTRACTING, L.P. (0.35)
CONTRACTORS SERVICE COMPANY (0.74)
A BROTHERS MILLING, LLC (0.76)
HJC FARMS, INC. (4.04)
FLAT LINE, INC. (2.33)
MURRAY CONSTRUCTION (0.62)
W. S. CONSTRUCTION COMPANY (6.32)
Contract #09183206
Totals10819113.5217425.005922939.1554.7

CountyTAYLOR
HighwayUS 83
FromS OF FM 204(CLARK/REMINGTON RD)
ToFM 707
CSJ0034-01-126
Proj IDNH 1802(506)
Work TypeEMB, FL BS, STRS, AND ACP
 
2.69419355727.8613862220.5671.6
CountyTAYLOR
HighwayUS 83
FromJUST SOUTH OF FM 204
ToUS 83 -US 84 SPLIT
CSJ0034-01-128
Proj IDNH 1802(506)
Work TypeEXC,FLX BS,ACP,OBL PVMT
 
5.9568637814.628413078.8397.3
Work Order11-01-18
Work Began01-21-19
Work Completed
Time Computed01-10-19
Contract Working Days553
Addl Days Granted3
Working Days Charged511
Percent Time Used91
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-126
BOWMAN ENGINEERING & CONSULTING, INC. (0.28)
DIIBS SPECIALISTS (0.53)
DK CONTRACTING, LLC (0.43)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.55)
SOUTH TEXAS PAINTING COMPANY (0.10)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.93)
BO SIMON INC (5.28)
DUSTROL, INC. (0.63)
HJC FARMS, INC. (2.99)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.88)
WILLIS ELECTRIC CO., LP (4.24)
STATEWIDE TRANSPORT, LLC (2.48)
ROBERT FLOYD SUE TRUCKING, INC (0.00)
NSTARRWAY VENTURES, LP (0.18)
WAYNE BRYANT LOGISTICS, LLC (0.24)
NOBLES ROAD CONSTRUCTION, INC. (0.24)
MICA CORPORATION (0.80)
FLAT LINE, INC. (0.00)
HALLIGAN SERVICES LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.03)
FLATWORKS, LLC (0.13)
Contract #08183203
Totals27993542.48538814.6622275299.3979.5

CountyTAYLOR
HighwayUS 83
FromNORTH OF FM 707
ToNEAR ANTILLEY ROAD
CSJ0034-01-127
Proj IDNH 2B20(043)
Work TypeWIDEN FREEWAY
 
1.0303381358.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began12-07-20
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-127
A BROTHERS MILLING, LLC (0.41)
4-WAY HAULERS, LLC (3.29)
CONTRACTORS SERVICE COMPANY (1.23)
DK CONTRACTING, LLC (0.62)
STRIPING TECHNOLOGY, L.P. (1.41)
WILLIS ELECTRIC CO., LP (7.90)
KLP COMMERCIAL, L.L.C. (4.22)
STREET FOUNDATION DRILLING, INC. (0.23)
Contract #08203225
Totals3381358.220.000.000.0

CountyTAYLOR
HighwayUS 83
FromUS 277 (S14TH) (FTG RDS& RAMPS ONLY
ToLP 322/US 83 INTERCHANGE
CSJ0034-01-137
Proj IDSTP 2019(984)
Work TypeOVERLAY
 
4451081.564331263.7197.6
Work Order07-23-19
Work Began06-14-20
Work Completed
Time Computed08-23-19
Contract Working Days64
Addl Days Granted22
Working Days Charged100
Percent Time Used116
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-137
A BROTHERS MILLING, LLC (2.13)
CONTRACTORS SERVICE COMPANY (2.38)
MPB, INC. (0.97)
TOTAL HIGHWAY MAINTENANCE, LLC (3.07)
WILLIS ELECTRIC CO., LP (0.17)
Contract #06193025
Totals4451081.5640480.004331263.7197.6

CountyNOLAN
HighwayFM 608
FromCR 152
ToFM 2319
CSJ0053-15-024
Proj IDSTP 2018(628)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.1164261779.481796510.5842.1
Work Order07-16-19
Work Began10-14-19
Work Completed
Time Computed10-14-19
Contract Working Days253
Addl Days Granted5
Working Days Charged212
Percent Time Used82
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0053-15-024
CONTRACTORS SERVICE COMPANY (0.84)
HJC FARMS, INC. (2.35)
TOTAL HIGHWAY MAINTENANCE, LLC (3.00)
Contract #05193023
Totals4261779.48346155.301796510.5842.1

CountyHOWARD
HighwayUS 87
FromUPRR @ BEALS CREEK
To..
CSJ0068-08-065
Proj IDBR 1802(503)
Work TypeBRIDGE REHAB
 
0.1606661050.957441020.3399.9
Work Order11-15-18
Work Began10-14-19
Work Completed
Time Computed01-15-19
Contract Working Days181
Addl Days Granted20
Working Days Charged201
Percent Time Used100
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0068-08-065
BARRICADES UNLIMITED (0.74)
SCOTT DERR PAINTING CO, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.82)
WILLIS ELECTRIC CO., LP (1.41)
OLYMPUS PAINTING CONTRACTORS, INC. (18.05)
CHOCTAW ERECTORS, INC. (0.49)
ACCESS RIGGING LLC (2.18)
NATIONAL BRIDGE, LLC (7.01)
Contract #08183050
Totals6661050.954055.567441020.3399.9

CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
To2.717 MI S OF FM 2482
CSJ0125-04-029
Proj IDSTP 2019(430)HES
Work TypeMILLED EDGELINE RUMBLE STRIPS
 
15.13031300.740.000.0
CountySHACKELFORD
HighwayUS 283
FromTHROCKMORTON COUNTY LINE
ToUS 180 IN ALBANY
CSJ0125-04-033
Proj IDSTP 2019(392)
Work TypeREHABILITATE AND WIDEN ROADWAY
 
17.30812550076.276807144.7054.2
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days429
Addl Days Granted0
Working Days Charged316
Percent Time Used73
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0125-04-029
MURRAY CONSTRUCTION (0.52)
CONTRACTORS SERVICE COMPANY (0.41)
PRIMATE CONSTRUCTION, LP (0.75)
NIXON ENGINEERING (0.21)
HJC FARMS, INC. (1.71)
TOTAL HIGHWAY MAINTENANCE, LLC (1.85)
J & M CONTRACTING, COMPANY (9.58)
TRANSGLOBAL, LLC (0.13)
LANCO TURF & SEEDING, INC. (0.02)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (1.53)
Contract #01193004
Totals12581377.0118000.006807144.7054.1

CountySHACKELFORD
HighwaySH 6
FromPECAN STREET ALBANY
ToCALLAHAN CO LINE
CSJ0126-01-039
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
17.5739227644.072758429.2929.8
CountyCALLAHAN
HighwaySH 6
FromCALLAHAN CO LINE
ToEASTLAND CO LINE
CSJ0126-02-020
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
2.2833436044.222064835.4660.0
Work Order10-21-19
Work Began12-02-19
Work Completed
Time Computed12-02-19
Contract Working Days322
Addl Days Granted0
Working Days Charged208
Percent Time Used64
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0126-01-039
BLACKTOP INDUSTRIES LLC (3.67)
CHEROKEE SERVICES (0.08)
CONTRACTORS SERVICE COMPANY (0.29)
COPPELL CONSTRUCTION CO., INC. (11.16)
D. I. J. CONSTRUCTION, INC. (1.47)
WEST TEXAS ROCK RESOURCES, LLC (0.19)
MURRAY CONSTRUCTION (0.93)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.14)
AARON CONCRETE CONTRACTORS, L.P. (0.46)
BOWMAN ENGINEERING & CONSULTING, INC. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
SOUTH TEXAS PAINTING COMPANY (0.05)
Contract #09193203
Totals12663688.29811621.904823264.7538.0

page 1 | page 2 | page 3