Monthly State Let Construction Report For Abilene District As Of Sep 18, 2019 Page 2 Of 2

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySHACKELFORD
HighwaySH 6
FromPECAN STREET ALBANY
ToCALLAHAN CO LINE
CSJ0126-01-039
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
17.5739227644.070.000.0
CountyCALLAHAN
HighwaySH 6
FromCALLAHAN CO LINE
ToEASTLAND CO LINE
CSJ0126-02-020
Proj IDSTP 2020(029)
Work TypeRESTORATION
 
2.2833436044.220.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days322
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0126-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193203
Totals12663688.290.000.000.0

CountyJONES
HighwayUS 277
FromHASKELL COUNTY LINE
ToFM 1636 (EAST)
CSJ0157-05-060
Proj IDNH 2018(407)
Work TypeSPT RPR,MILL& FILL,1-CST,OVERLAY
 
7.2806432024.479359395.3899.9
Work Order02-14-18
Work Began04-09-18
Work Completed
Time Computed03-15-18
Contract Working Days105
Addl Days Granted115
Working Days Charged236
Percent Time Used107
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-05-060
CONTRACTORS SERVICE COMPANY (0.26)
HJC FARMS, INC. (7.77)
MPB, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (2.22)
ZACK BURKETT CO. (61.45)
FOUTSCO PAVING COMPANY, LLC (7.85)
TEXOP CONSTRUCTION (0.50)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (8.55)
Contract #01183210
Totals6432024.4764175.789359395.3899.9

CountyFISHER
HighwayUS 180
FromALKALI CREEK
To.
CSJ0296-02-033
Proj IDBR 2018(951)
Work TypeBRIDGE REPLACEMENT
 
0.1461763518.631764921.0899.9
Work Order07-19-18
Work Began09-17-18
Work Completed
Time Computed09-17-18
Contract Working Days200
Addl Days Granted0
Working Days Charged159
Percent Time Used79
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0296-02-033
HJC FARMS, INC. (12.09)
BARRICADES UNLIMITED (1.79)
WOLFE CONSTRUCTION GROUP, INC. (0.33)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.93)
TEX OP CONSTRUCTION, LP (0.97)
CONTRACTORS SERVICE COMPANY (0.65)
GARY A. CRAIN, INC. (0.19)
RUNNING HORSE CONSTRUCTION, INC. (1.41)
Contract #06183223
Totals1763518.6347288.951764921.0899.9

CountyFISHER
HighwayUS 180
FromFM 57
ToUS 180
CSJ0296-03-038
Proj IDBR 2019(982)
Work TypeBR
 
0.5434583865.380.000.0
CountyFISHER
HighwayFM 57
FromSH 70
ToUS 180
CSJ0317-01-037
Proj IDSTP 2019(985)
Work TypeWIDEN NON-FREEWAY
 
12.39612063124.230.000.0
CountyFISHER
HighwayFM 57
FromPLUM CREEK
To.
CSJ0317-01-038
Proj IDBR 2019(983)
Work TypeBR
 
1930380.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days673
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNF CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0296-03-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193009
Totals18577370.540.000.000.0

CountyJONES
HighwayUS 180
FromFM 1226
ToSHACKELFORD COUNTY LINE
CSJ0296-05-034
Proj IDSTP 2019(393)
Work TypeBASE REPAIR LEVEL UP AND OVERLAY
 
11.0357597359.93568613.717.4
Work Order02-25-19
Work Began06-03-19
Work Completed
Time Computed03-27-19
Contract Working Days332
Addl Days Granted0
Working Days Charged66
Percent Time Used19
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-05-034
CONTRACTORS SERVICE COMPANY (0.77)
STRIPE-A-ZONE, INC. (0.45)
HJC FARMS, INC. (8.96)
FLAT LINE, INC. (2.09)
J & M CONTRACTING, COMPANY (5.08)
Contract #01193040
Totals7597359.9320502.00568613.717.4

CountyCALLAHAN
HighwayUS 283
FromIH 20
ToAPPROX .25 MILES NORTH OF IH 20
CSJ0437-02-014
Proj IDSTP 2018(312)
Work TypeREHABILITATION
 
1.8703117046.362990209.5197.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began02-06-18
Work Completed
Time Computed02-06-18
Contract Working Days179
Addl Days Granted0
Working Days Charged224
Percent Time Used125
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0437-02-014
CONTRACTORS SERVICE COMPANY (1.52)
WOLFE CONSTRUCTION GROUP, INC. (0.20)
WEST TEXAS RUMBLE STRIP (0.14)
TEXAS ALTERNATIVE GRASSER, INC. (0.02)
O. TREVINO CONSTRUCTION, LLC (24.68)
HJC FARMS, INC. (1.21)
WILLIS ELECTRIC CO., LP (1.15)
STRIPING TECHNOLOGY, L.P. (2.06)
Contract #12173005
Totals3117046.360.002990209.5197.3

CountyCALLAHAN
HighwayUS 283
FromSHACKELFORD COUNTY LINE
ToAPPROX REF MARKER 308
CSJ0437-02-017
Proj IDSTP 2019(394)
Work Type3"OVERLAY
 
4.5313259092.613178490.9697.5
Work Order02-20-19
Work Began03-25-19
Work Completed
Time Computed03-25-19
Contract Working Days129
Addl Days Granted10
Working Days Charged91
Percent Time Used65
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0437-02-017
A BROTHERS MILLING, LLC (0.40)
CONTRACTORS SERVICE COMPANY (0.58)
DIIBS SPECIALISTS (3.30)
DOUBLE A CONTRACTING, L.P. (0.50)
FLAT LINE, INC. (1.07)
HJC FARMS, INC. (0.44)
Contract #01193210
Totals3259092.611685935.863178490.9697.5

CountyJONES ETC
HighwayFM 707 ETC
FromUS 83
ToFM 605
CSJ0484-01-023
Proj IDSTP 1802(504)HES
Work TypeWIDEN ROADWAY
 
32.44313833694.005848649.0642.2
Work Order09-24-18
Work Began10-23-18
Work Completed
Time Computed10-23-18
Contract Working Days648
Addl Days Granted0
Working Days Charged195
Percent Time Used30
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0484-01-023
A BROTHERS MILLING, LLC (0.09)
CONTRACTORS SERVICE COMPANY (0.69)
HJC FARMS, INC. (1.57)
DOUBLE A CONTRACTING, L.P. (3.18)
MURRAY CONSTRUCTION (1.06)
THORNTON"S TREE SERVICE, INC. (2.34)
Contract #08183009
Totals13833694.00921095.285848649.0642.2

CountyHOWARD
HighwayFM 700
FromAT US 87
To.
CSJ0668-04-004
Proj IDSTP 2019(922)
Work TypeINC
 
0.6007761125.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days286
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0668-04-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193220
Totals7761125.500.000.000.0

CountyTAYLOR
HighwayFM 89
FromFM 707
ToJUST SOUTH OF MABRAY LANE
CSJ0699-01-055
Proj IDC 699-1-55
Work TypeMILL AND OVERLAY
 
2.6201793003.06545245.8330.4
Work Order04-16-19
Work Began06-18-19
Work Completed
Time Computed06-13-19
Contract Working Days100
Addl Days Granted0
Working Days Charged51
Percent Time Used51
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0699-01-055
TOTAL HIGHWAY MAINTENANCE, LLC (0.81)
TEX OP CONSTRUCTION, LP (2.39)
DK CONTRACTING, LLC (0.20)
BONTKE BROTHERS CONSTRUCTION COMPANY (8.38)
D. I. J. CONSTRUCTION, INC. (4.23)
Contract #03193222
Totals1793003.06291508.38545245.8330.4

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT
CSJ0908-00-088
Proj IDNH 2019(516)
Work TypeFY 2019 TRAFFIC CONTROL DEVICES
 
0.1001682111.261522457.4790.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-18-19
Work Began03-21-19
Work Completed
Time Computed03-21-19
Contract Working Days143
Addl Days Granted0
Working Days Charged84
Percent Time Used58
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-088
BRYDL CONTRACTING, INC. (30.35)
RED SIXTEEN CONSTRUCTION, INC (30.35)
Contract #02193036
Totals1682111.260.001522457.4790.5

CountyTAYLOR
HighwayVA
FromIH-20 TAYLOR
ToUS 277 HASKELL
CSJ0908-00-092
Proj IDSTP 1902(338)
Work TypeRES
 
4.4301171614.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days41
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-092
TEX OP CONSTRUCTION, LP (16.42)
TOTAL HIGHWAY MAINTENANCE, LLC (7.41)
Contract #07193058
Totals1171614.000.000.000.0

CountyTAYLOR
HighwayVA
FromIH-20 NOLAN
ToIH-20 HOWARD
CSJ0908-00-093
Proj IDSTP 1902(340)
Work TypeRES
 
1285512.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days44
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193060
Totals1285512.000.000.000.0

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.0062031556.540.0
Work Order01-13-17
Work Began02-21-17
Work Completed
Time Computed02-13-17
Contract Working Days680
Addl Days Granted4
Working Days Charged637
Percent Time Used93
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
STRIPE-A-ZONE, INC. (0.50)
W. S. CONSTRUCTION COMPANY (4.96)
DELHUR INDUSTRIES, INC. (33.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.10)
DIIBS SPECIALISTS (0.46)
TEXAS SHAFTS, INC. (1.91)
AARON CONCRETE CONTRACTORS, L.P. (1.54)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.90)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ROBERT KENT CONSTRUCTION (0.23)
EMERGY (2.44)
DTM TRUCKING, INC. (0.15)
HERITAGE ASPHALT COMPANY (9.45)
PLATINUM PIPELINE SERVICES, LLC (0.03)
CHOCTAW ERECTORS, INC. (2.45)
COLLIER DIRECTIONAL DRILLING (0.03)
BARRICADES UNLIMITED (0.13)
Contract #09163001
Totals0.00612934.1362031556.540.0

CountySCURRY ETC
HighwayCR
FromON CR 134 (SIGNED CR 398)
ToAT CANYON CREEK TRIBUTARY (PSN 1)
CSJ0908-19-025
Proj IDBR 2018(378)
Work TypeBR
 
0.3612153442.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days239
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193228
Totals2153442.500.000.000.0

CountySCURRY
HighwayVA
FromUS 84
ToVARIOUS
CSJ0908-19-027
Proj IDSTP 1902(339)
Work TypeRES
 
1138632.890.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193059
Totals1138632.890.000.000.0

CountyHOWARD
HighwayFM 1584
FromFM 846
ToUS 87
CSJ1503-02-011
Proj IDSTP 1802(505)HES
Work TypePAVEMENT WIDENING
 
4.5333443262.372732013.9579.3
Work Order10-01-18
Work Began11-06-18
Work Completed
Time Computed10-31-18
Contract Working Days210
Addl Days Granted0
Working Days Charged152
Percent Time Used72
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1503-02-011
BARRICADES UNLIMITED (1.73)
DTM TRUCKING, INC. (6.99)
HJC FARMS, INC. (0.84)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.82)
PAVEMENT MARKINGS INC. (1.85)
REECE CONSTRUCTION CO., INC. (1.37)
FELIX CHAVEZ & SON CONSTRUCTION (0.74)
ARANDA"S TRUCKING (0.74)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.40)
Contract #08183219
Totals3443262.37340575.492732013.9579.3

CountySCURRY
HighwayFM 1607
From485' WEST OF MIDLAND AVE
To630' EAST OF HOUSTON STREET
CSJ1529-02-010
Proj IDSTP 2019(642)
Work TypePED
 
0.535197824.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1529-02-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193244
Totals197824.000.000.000.0

CountyJONES ETC
HighwayFM 1661 ETC
FromHASKELL/JONES CO LINE
ToUS 83
CSJ1654-01-019
Proj IDSTP 2019(327)
Work TypeSEAL COAT
 
265.87710412142.529962336.5595.6
Work Order01-22-19
Work Began04-16-19
Work Completed
Time Computed04-16-19
Contract Working Days104
Addl Days Granted0
Working Days Charged86
Percent Time Used82
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1654-01-019
FLAT LINE, INC. (7.39)
RED SIXTEEN CONSTRUCTION, INC (0.83)
Contract #12183227
Totals10412142.525000.009962336.5595.6

page 1 | page 2