Monthly State Let Construction Report For Abilene District As Of Apr 11, 2020 Page 2 Of 2

Last Update: Saturday, April 11, 2020
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayFM 700
FromUS 87
To1550 FT. EAST OF BIRDWELL LANE
CSJ0668-02-020
Proj IDNH 2020(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.8594167074.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0668-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203020
Totals4167074.000.000.000.0

CountyHOWARD
HighwayFM 700
FromAT US 87
To.
CSJ0668-04-004
Proj IDSTP 2019(922)
Work TypeINC
 
0.6007761125.50638309.368.2
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed11-12-19
Contract Working Days286
Addl Days Granted0
Working Days Charged16
Percent Time Used5
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0668-04-004
ALAMO BROTHERS CONCRETE INC (5.16)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.28)
BARRICADES UNLIMITED (0.65)
BLACK JACK ENERGY SERVICES, LLC (12.40)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.27)
SLATON BROTHERS, INC. (7.64)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC. (0.07)
HJC FARMS, INC. (1.44)
Contract #07193220
Totals7761125.50182209.36638309.368.2

CountyTAYLOR ETC
HighwayFM 707 ETC
FromBI 20Q
ToUS 277
CSJ0677-01-023
Proj IDSTP 2020(357)
Work TypeSEAL COAT
 
202.6906775556.091109636.1716.3
Work Order01-15-20
Work Began00-00-00
Work Completed
Time Computed05-01-20
Contract Working Days103
Addl Days Granted0
Working Days Charged5
Percent Time Used4
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0677-01-023
FLAT LINE, INC. (7.37)
RED SIXTEEN CONSTRUCTION, INC (0.95)
Contract #12193013
Totals6775556.09968764.161109636.1716.3

CountyHOWARD
HighwaySH 350
FromCR 26
To1200 FT WEST OF FM 820
CSJ0693-01-036
Proj IDSTP 2020(030)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.80213149840.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-07-20
Work Began00-00-00
Work Completed
Time Computed04-04-20
Contract Working Days354
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0693-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12193205
Totals13149840.020.000.000.0

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT (EAST)
CSJ0908-00-081
Proj IDSTP 2020(521)
Work TypeTRAFFIC CONTROL DEVICES
 
0.1001479662.470.000.0
CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT
CSJ0908-00-099
Proj IDC 908-00-99
Work TypeTRAFFIC CONTROL DEVICES
 
303130.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203032
Totals1782793.220.000.000.0

CountyTAYLOR
HighwayVA
FromIH-20 TAYLOR
ToUS 277 HASKELL
CSJ0908-00-092
Proj IDSTP 1902(338)
Work TypeRES
 
4.4301171614.001147947.6797.9
Work Order08-22-19
Work Began10-01-19
Work Completed
Time Computed09-22-19
Contract Working Days41
Addl Days Granted0
Working Days Charged37
Percent Time Used90
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-092
TEX OP CONSTRUCTION, LP (16.42)
TOTAL HIGHWAY MAINTENANCE, LLC (7.41)
Contract #07193058
Totals1171614.000.001147947.6797.9

CountyTAYLOR
HighwayVA
FromIH-20 NOLAN
ToIH-20 HOWARD
CSJ0908-00-093
Proj IDSTP 1902(340)
Work TypeRES
 
1285512.00840437.4565.3
Work Order08-22-19
Work Began01-06-20
Work Completed
Time Computed09-23-19
Contract Working Days44
Addl Days Granted0
Working Days Charged24
Percent Time Used54
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-093
TEXOP CONSTRUCTION (13.87)
TOTAL HIGHWAY MAINTENANCE, LLC (11.95)
Contract #07193060
Totals1285512.00270528.50840437.4565.3

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT (WEST)
CSJ0908-00-096
Proj IDSTP 2020(585)
Work TypeTRAFFIC CONTROL DEVICES
 
1798464.250.000.0
CountyCALLAHAN
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT
CSJ0908-00-100
Proj IDC 908-00-100
Work TypeTRAFFIC CONTROL DEVICES
 
0.010199633.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203231
Totals1998097.410.000.000.0

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.0065813038.090.0
Work Order01-13-17
Work Began02-21-17
Work Completed
Time Computed02-13-17
Contract Working Days680
Addl Days Granted4
Working Days Charged765
Percent Time Used111
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
STRIPE-A-ZONE, INC. (0.50)
W. S. CONSTRUCTION COMPANY (4.96)
DELHUR INDUSTRIES, INC. (33.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.10)
DIIBS SPECIALISTS (0.46)
TEXAS SHAFTS, INC. (1.91)
AARON CONCRETE CONTRACTORS, L.P. (1.54)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.90)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ROBERT KENT CONSTRUCTION (0.23)
EMERGY (2.44)
DTM TRUCKING, INC. (0.15)
HERITAGE ASPHALT COMPANY (9.45)
PLATINUM PIPELINE SERVICES, LLC (0.03)
CHOCTAW ERECTORS, INC. (2.45)
COLLIER DIRECTIONAL DRILLING (0.03)
BARRICADES UNLIMITED (0.13)
TRP CONSTRUCTION GROUP, LLC (0.02)
Contract #09163001
Totals0.00445398.2765813038.090.0

CountySCURRY ETC
HighwayCR
FromON CR 134 (SIGNED CR 398)
ToAT CANYON CREEK TRIBUTARY (PSN 1)
CSJ0908-19-025
Proj IDBR 2018(378)
Work TypeBR
 
0.3612153442.50294584.8213.6
Work Order07-16-19
Work Began11-18-19
Work Completed
Time Computed10-15-19
Contract Working Days239
Addl Days Granted0
Working Days Charged53
Percent Time Used22
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-025
COMEN ENTERPRISE LLC (3.76)
CONTRACTORS SERVICE COMPANY (0.79)
MCL CONTRACTING, LLC (2.26)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.86)
Contract #06193228
Totals2153442.5035633.74294584.8213.6

CountyNOLAN
HighwayCR
FromON CR 238
ToAT DRAW
CSJ0908-20-026
Proj IDBR 1902(088)
Work TypeBRIDGE REPLACEMENT
 
488291.600.000.0
CountyNOLAN
HighwayCR
FromON CR 117
ToAT ROUGH CREEK
CSJ0908-20-027
Proj IDBR 1902(087)
Work TypeBRIDGE REPLACEMENT
 
342359.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-20-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203218
Totals830650.600.000.000.0

CountyHOWARD
HighwayFM 1584
FromFM 846
ToUS 87
CSJ1503-02-011
Proj IDSTP 1802(505)HES
Work TypePAVEMENT WIDENING
 
4.5333443262.373170198.9392.0
Work Order10-01-18
Work Began11-06-18
Work Completed
Time Computed10-31-18
Contract Working Days210
Addl Days Granted0
Working Days Charged190
Percent Time Used90
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1503-02-011
BARRICADES UNLIMITED (1.73)
DTM TRUCKING, INC. (6.99)
HJC FARMS, INC. (0.84)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.82)
PAVEMENT MARKINGS INC. (1.85)
REECE CONSTRUCTION CO., INC. (1.37)
FELIX CHAVEZ & SON CONSTRUCTION (0.74)
ARANDA"S TRUCKING (0.74)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.40)
PMI PAVEMENT MARKING, LLC (0.14)
Contract #08183219
Totals3443262.370.003170198.9392.0

CountySCURRY
HighwayFM 1607
From485' WEST OF MIDLAND AVE
To630' EAST OF HOUSTON STREET
CSJ1529-02-010
Proj IDSTP 2019(642)
Work TypePED
 
0.535197824.00169519.0085.6
Work Order09-25-19
Work Began11-11-19
Work Completed
Time Computed10-28-19
Contract Working Days43
Addl Days Granted0
Working Days Charged43
Percent Time Used100
Contractor(s)
TALBRAN ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 1529-02-010
E3 LAND DEVELOPMENT COMPANY (61.54)
Contract #08193244
Totals197824.000.00169519.0085.6

CountyHOWARD
HighwayFM 2230
FromFM 846
ToUS 87
CSJ2149-01-010
Proj IDC 2149-1-10
Work TypeREHABILITATION OF EXISTING ROAD
 
6.6815693174.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days216
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIERRA LEASE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02203006
Totals5693174.520.000.000.0

CountyBORDEN ETC
HighwayFM 1054 ETC
FromUS 180
ToFM 1584
CSJ3276-01-020
Proj IDSTP 2020(359)
Work TypeSEAL COAT
 
244.1509612826.111378837.0914.3
Work Order01-24-20
Work Began00-00-00
Work Completed
Time Computed05-01-20
Contract Working Days103
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 3276-01-020
RED SIXTEEN CONSTRUCTION, INC (0.95)
BARRICADES PLUS, LLC (1.39)
FLAT LINE, INC. (6.05)
Contract #12193010
Totals9612826.111179730.341378837.0914.3

page 1 | page 2