Monthly State Let Construction Report For Abilene District As Of Sep 17, 2020 Page 2 Of 2

Last Update: Monday, September 21, 2020
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJONES
HighwayUS 180
FromFM 1226
ToSHACKELFORD COUNTY LINE
CSJ0296-05-034
Proj IDSTP 2019(393)
Work TypeBASE REPAIR LEVEL UP AND OVERLAY
 
11.0357597359.937908616.4299.9
Work Order02-25-19
Work Began06-03-19
Work Completed
Time Computed03-27-19
Contract Working Days332
Addl Days Granted0
Working Days Charged273
Percent Time Used82
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-05-034
CONTRACTORS SERVICE COMPANY (0.77)
STRIPE-A-ZONE, INC. (0.45)
HJC FARMS, INC. (8.96)
FLAT LINE, INC. (2.09)
J & M CONTRACTING, COMPANY (5.08)
Contract #01193040
Totals7597359.93579476.447908616.4299.9

CountyJONES ETC
HighwayFM 707 ETC
FromUS 83
ToFM 605
CSJ0484-01-023
Proj IDSTP 1802(504)HES
Work TypeWIDEN ROADWAY
 
32.44313833694.0011816521.6185.4
Work Order09-24-18
Work Began10-23-18
Work Completed
Time Computed10-23-18
Contract Working Days648
Addl Days Granted20
Working Days Charged413
Percent Time Used61
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0484-01-023
A BROTHERS MILLING, LLC (0.09)
CONTRACTORS SERVICE COMPANY (0.69)
HJC FARMS, INC. (1.57)
DOUBLE A CONTRACTING, L.P. (3.18)
MURRAY CONSTRUCTION (1.06)
THORNTON"S TREE SERVICE, INC. (2.34)
Contract #08183009
Totals13833694.00742313.2911816521.6185.4

CountyHOWARD
HighwaySH 176
FromMARTIN COUNTY LINE
ToIH 20 SOUTH FRONTAGE ROAD
CSJ0548-04-021
Proj IDSTP 2020(361)
Work TypeRESTORATION
 
11.1209975871.026170416.7561.8
Work Order01-03-20
Work Began04-07-20
Work Completed
Time Computed04-03-20
Contract Working Days180
Addl Days Granted0
Working Days Charged105
Percent Time Used58
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0548-04-021
A BROTHERS MILLING, LLC (1.36)
BLACK JACK ENERGY SERVICES, LLC (1.44)
CONTRACTORS SERVICE COMPANY (0.54)
DK CONTRACTING, LLC (0.72)
DOUBLE A CONTRACTING, L.P. (7.93)
HJC FARMS, INC. (0.38)
RPV CONSTRUCTION, LLC (0.93)
WILLIS ELECTRIC CO., LP (0.58)
FUSION COMMUNICATIONS, LLC (0.01)
W. S. CONSTRUCTION COMPANY (0.22)
FC TRAFFIC CONTROL, INC. (0.07)
Contract #12193206
Totals9975871.022435403.436170416.7561.8

CountyHOWARD
HighwayFM 700
FromUS 87
To1550 FT. EAST OF BIRDWELL LANE
CSJ0668-02-020
Proj IDNH 2020(619)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.8594167074.0037490.060.8
Work Order04-23-20
Work Began00-00-00
Work Completed
Time Computed07-22-20
Contract Working Days110
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0668-02-020
A BROTHERS MILLING, LLC (2.34)
BARRICADES UNLIMITED (3.14)
CONTRACTORS SERVICE COMPANY (0.68)
HJC FARMS, INC. (2.33)
RPV CONSTRUCTION, LLC (4.68)
Contract #03203020
Totals4167074.000.0037490.060.8

CountyHOWARD
HighwayFM 700
FromAT US 87
To.
CSJ0668-04-004
Proj IDSTP 2019(922)
Work TypeINC
 
0.6007761125.503229961.9441.6
Work Order08-13-19
Work Began02-13-20
Work Completed
Time Computed11-12-19
Contract Working Days286
Addl Days Granted0
Working Days Charged93
Percent Time Used32
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0668-04-004
ALAMO BROTHERS CONCRETE INC (5.16)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (1.28)
BARRICADES UNLIMITED (0.65)
BLACK JACK ENERGY SERVICES, LLC (12.40)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.27)
SLATON BROTHERS, INC. (7.64)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC. (0.07)
HJC FARMS, INC. (1.44)
Contract #07193220
Totals7761125.50247663.763229961.9441.6

CountyTAYLOR ETC
HighwayFM 707 ETC
FromBI 20Q
ToUS 277
CSJ0677-01-023
Proj IDSTP 2020(357)
Work TypeSEAL COAT
 
202.6906775556.096104174.6490.0
Work Order01-15-20
Work Began05-04-20
Work Completed
Time Computed05-01-20
Contract Working Days103
Addl Days Granted0
Working Days Charged86
Percent Time Used83
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0677-01-023
FLAT LINE, INC. (7.37)
RED SIXTEEN CONSTRUCTION, INC (0.95)
Contract #12193013
Totals6775556.090.006104174.6490.0

CountyHOWARD
HighwaySH 350
FromCR 26
To1200 FT WEST OF FM 820
CSJ0693-01-036
Proj IDSTP 2020(030)
Work TypeREHABILITATION OF EXISTING ROAD
 
8.80213149840.023853980.1329.3
Work Order01-07-20
Work Began04-23-20
Work Completed
Time Computed04-04-20
Contract Working Days354
Addl Days Granted0
Working Days Charged88
Percent Time Used24
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0693-01-036
A BROTHERS MILLING, LLC (2.23)
BARRICADES UNLIMITED (0.85)
BLACK JACK ENERGY SERVICES, LLC (3.69)
CONTRACTORS SERVICE COMPANY (0.37)
MARCOM"S MOWING SERVICE, LLC (0.31)
RPV CONSTRUCTION, LLC (2.20)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.45)
W. S. CONSTRUCTION COMPANY (2.53)
Contract #12193205
Totals13149840.02259692.423853980.1329.3

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT (WEST)
CSJ0908-00-096
Proj IDSTP 2020(585)
Work TypeTRAFFIC CONTROL DEVICES
 
1798464.25581117.0232.3
CountyCALLAHAN
HighwayVA
FromVARIOUS LOCATIONS IN THE
ToABILENE DISTRICT
CSJ0908-00-100
Proj IDC 908-00-100
Work TypeTRAFFIC CONTROL DEVICES
 
0.010199633.160.000.0
Work Order05-12-20
Work Began06-11-20
Work Completed
Time Computed06-11-20
Contract Working Days72
Addl Days Granted0
Working Days Charged35
Percent Time Used48
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-096
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03203231
Totals1998097.41514504.12581117.0229.0

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS
ToIN ABILENE
CSJ0908-00-101
Proj IDSTP 2B20(011)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
326023.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days71
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-101
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07203048
Totals326023.970.000.000.0

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.0068715446.710.0
Work Order01-13-17
Work Began02-21-17
Work Completed
Time Computed02-13-17
Contract Working Days680
Addl Days Granted4
Working Days Charged860
Percent Time Used125
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
STRIPE-A-ZONE, INC. (0.50)
W. S. CONSTRUCTION COMPANY (4.96)
DELHUR INDUSTRIES, INC. (33.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.10)
DIIBS SPECIALISTS (0.46)
TEXAS SHAFTS, INC. (1.91)
AARON CONCRETE CONTRACTORS, L.P. (1.54)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.90)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ROBERT KENT CONSTRUCTION (0.23)
EMERGY (2.44)
DTM TRUCKING, INC. (0.15)
HERITAGE ASPHALT COMPANY (9.45)
PLATINUM PIPELINE SERVICES, LLC (0.03)
CHOCTAW ERECTORS, INC. (2.45)
COLLIER DIRECTIONAL DRILLING (0.03)
BARRICADES UNLIMITED (0.13)
TRP CONSTRUCTION GROUP, LLC (0.02)
Contract #09163001
Totals0.00121391.1268715446.710.0

CountySCURRY ETC
HighwayCR
FromON CR 134 (SIGNED CR 398)
ToAT CANYON CREEK TRIBUTARY (PSN 1)
CSJ0908-19-025
Proj IDBR 2018(378)
Work TypeBR
 
0.3612153442.501072890.5549.8
Work Order07-16-19
Work Began11-18-19
Work Completed
Time Computed10-15-19
Contract Working Days239
Addl Days Granted0
Working Days Charged158
Percent Time Used66
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-025
COMEN ENTERPRISE LLC (3.76)
CONTRACTORS SERVICE COMPANY (0.79)
MCL CONTRACTING, LLC (2.26)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.86)
TORO BRAVO CONSTRUCTION, LLC (0.84)
Contract #06193228
Totals2153442.50118335.261072890.5549.8

CountySCURRY
HighwayCS
FromON 26TH STREET
ToAT DEEP CREEK
CSJ0908-19-026
Proj IDBR 1802(837)
Work TypeBRIDGE REPLACEMENT
 
1160318.000.000.0
CountyFISHER
HighwayCR
FromON CR 110 (SIGNED CR 161)
ToAT SWEETWATER CREEK (PSN 1)
CSJ0908-23-048
Proj IDBR 1902(085)
Work TypeBRIDGE REPLACEMENT
 
432356.850.000.0
CountyFISHER
HighwayCR
FromON CR 160 (SIGNED CR 415)
ToAT COTTONWOOD CREEK (PSN 1)
CSJ0908-23-050
Proj IDBR 1902(086)
Work TypeBRIDGE REPLACEMENT
 
409899.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-20-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days151
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07203224
Totals2002573.850.000.000.0

CountyNOLAN
HighwayCR
FromON CR 238
ToAT DRAW
CSJ0908-20-026
Proj IDBR 1902(088)
Work TypeBRIDGE REPLACEMENT
 
488291.6087500.0017.9
CountyNOLAN
HighwayCR
FromON CR 117
ToAT ROUGH CREEK
CSJ0908-20-027
Proj IDBR 1902(087)
Work TypeBRIDGE REPLACEMENT
 
342359.0080250.0023.4
Work Order04-23-20
Work Began07-22-20
Work Completed
Time Computed07-22-20
Contract Working Days106
Addl Days Granted0
Working Days Charged27
Percent Time Used25
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-20-026
CONTRACTORS SERVICE COMPANY (1.08)
TEXAS ALTERNATIVE GRASSER INCORPORATED (1.56)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.75)
Contract #03203218
Totals830650.60150250.00167750.0020.1

CountyJONES
HighwayCR
FromON CR 303
ToAT DRAW CREEK
CSJ0908-24-050
Proj IDBR 1902(092)
Work TypeBRIDGE REPLACEMENT
 
0.018959462.000.000.0
CountyCALLAHAN
HighwayCR
FromCR 429
ToAT COTTONWOOD CREEK
CSJ0908-34-027
Proj IDBR 1902(091)
Work TypeBRIDGE REPLACEMENT
 
0.025403254.250.000.0
CountyCALLAHAN
HighwayCS
FromON WALNUT STREET IN BAIRD
ToAT SPRING CREEK (PSN 1)
CSJ0908-34-028
Proj IDBR 1902(090)
Work TypeBRIDGE REPLACEMENT
 
0.022428216.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days169
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-24-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05203025
Totals1790933.000.000.000.0

CountyTAYLOR
HighwayFM 1750
FromNORTH OF LOOP 322
ToSOUTH OF INDUSTRIAL
CSJ1655-01-032
Proj IDC 1655-1-32
Work TypeSAFETY IMPROVEMENT PROJECTS
 
383309.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 1655-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203053
Totals383309.880.000.000.0

CountyHOWARD
HighwayFM 2230
FromFM 846
ToUS 87
CSJ2149-01-010
Proj IDC 2149-1-10
Work TypeREHABILITATION OF EXISTING ROAD
 
6.6815693174.522977262.1452.2
Work Order04-14-20
Work Began04-27-20
Work Completed
Time Computed04-27-20
Contract Working Days216
Addl Days Granted0
Working Days Charged78
Percent Time Used36
Contractor(s)
TIERRA LEASE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-010
BARRICADES UNLIMITED (0.00)
Contract #02203006
Totals5693174.52725462.392977262.1452.2

CountyBORDEN ETC
HighwayFM 1054 ETC
FromUS 180
ToFM 1584
CSJ3276-01-020
Proj IDSTP 2020(359)
Work TypeSEAL COAT
 
244.1509612826.119216235.4195.8
Work Order01-24-20
Work Began06-24-20
Work Completed
Time Computed05-01-20
Contract Working Days103
Addl Days Granted0
Working Days Charged61
Percent Time Used59
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 3276-01-020
RED SIXTEEN CONSTRUCTION, INC (0.95)
BARRICADES PLUS, LLC (1.39)
FLAT LINE, INC. (6.05)
Contract #12193010
Totals9612826.11169025.769216235.4195.8

page 1 | page 2