Monthly State Let Maintenance Report For Abilene District As Of Mar 13, 2024 Page 2 Of 2

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToABILENE DISTRICT
CSJ6424-10-001
Proj IDMMC - 642410001
Work TypeHOT-MIX COLD-LAID
 
0.010802100.002425688.0699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-21-23
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted366
Working Days Charged405
Percent Time Used73
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6424-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224201
Totals802100.0096484.602425688.0699.9

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS
ToIN ABILENE DISTRICT
CSJ6424-16-001
Proj IDMMC - 642416001
Work TypeEMULSION
 
0.010769260.00691242.6389.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-17-23
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted366
Working Days Charged409
Percent Time Used74
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224202
Totals769260.0016906.69691242.6389.8

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToTHE ABILENE DISTRICT
CSJ6427-47-001
Proj IDRMC - 642747001
Work TypeCULVERT CLEANING
 
0.010710250.0084300.0011.8
Work Order02-20-24
Work Began02-20-24
Work Completed
Time Computed02-20-24
Contract Working Days153
Addl Days Granted0
Working Days Charged7
Percent Time Used4
Contractor(s)
STX CIVIL
SUBCONTRACTOR(S) FOR CCSJ: 6427-47-001
FC TRAFFIC CONTROL, INC. (1.06)
Contract #11234001
Totals710250.0041024.0084300.0011.8

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToTHE ABILENE DISTRICT
CSJ6430-79-001
Proj IDBPM - 643079001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010850490.00871800.00100.0
Work Order10-06-23
Work Began10-18-23
Work Completed02-15-24
Time Computed10-16-23
Contract Working Days119
Addl Days Granted0
Working Days Charged34
Percent Time Used28
Contractor(s)
PATHFIELD INVESTMENTS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6430-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08234202
Totals850490.000.00871800.00100.0

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS IN THE
ToABILENE AREA
CSJ6440-20-001
Proj IDRMC - 644020001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010637265.0086999.5013.6
Work Order10-30-23
Work Began00-00-00
Work Completed
Time Computed11-06-23
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234003
Totals637265.0016581.0086999.5013.6

CountyHOWARD
HighwayIH0020
FromVARIOUS LOCATIONS IN THE
ToBIG SPRING AREA
CSJ6440-22-001
Proj IDRMC - 644022001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010468605.00192838.7541.1
Work Order10-30-23
Work Began00-00-00
Work Completed
Time Computed11-06-23
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09234002
Totals468605.0085461.25192838.7541.1

CountyHOWARD
HighwayIH0020
FromVARIOUS LOCATIONS IN BORDEN, HOWARD,
ToMITCHELL, AND NOLAN COUNTIES
CSJ6451-89-001
Proj IDRMC - 645189001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.0101384501.00529566.0038.2
Work Order12-12-23
Work Began00-00-00
Work Completed
Time Computed12-12-23
Contract Working Days365
Addl Days Granted0
Working Days Charged80
Percent Time Used21
Contractor(s)
AUSTIN BARRICADE COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6451-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10234201
Totals1384501.00267142.00529566.0038.2

CountyTAYLOR
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToTHE ABILENE DISTRICT
CSJ6454-99-001
Proj IDRMC - 645499001
Work TypeCONCRETE STRUCTURE REPAIR
 
0.010855754.00152661.6017.8
Work Order02-05-24
Work Began02-05-24
Work Completed
Time Computed02-05-24
Contract Working Days365
Addl Days Granted0
Working Days Charged25
Percent Time Used6
Contractor(s)
DCC CONSTRUCTION AND SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6454-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234003
Totals855754.00152661.60152661.6017.8

CountyCALLAHAN
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToCALLAHAN COUNTY
CSJ6457-41-001
Proj IDRMC - 645741001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010391555.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOSE ERNESTO SALAZAR, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244216
Totals391555.000.000.000.0

CountyNOLAN
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToNOLAN COUNTY
CSJ6457-73-001
Proj IDRMC - 645773001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010278679.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOSE ERNESTO SALAZAR, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6457-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02244218
Totals278679.000.000.000.0

page 1 | page 2