Monthly State Let Construction Report For Amarillo District As Of Aug 23, 2019 Page 1 Of 3

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromSH 15
ToPEER STREET (PERRYTON)
CSJ0030-02-047
Proj IDNH 2017(260)
Work TypeSEALCOAT
 
313.26012438153.5312928229.4099.9
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed04-15-17
Contract Working Days76
Addl Days Granted0
Working Days Charged94
Percent Time Used123
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-047
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (14.02)
FLAT LINE, INC. (2.47)
Contract #11163003
Totals12438153.530.0012928229.4099.9

CountyOCHILTREE
HighwayUS 83
FromCR K SOUTH OF PERRYTON
ToWOLF CREEK
CSJ0030-02-052
Proj IDSTP 2019(603)
Work TypeOVERLAY
 
25.39613814377.4564020.000.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193005
Totals13814377.450.0064020.000.4

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193227
Totals2152762.700.000.000.0

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromLIPSCOMB COUNTY LINE
ToHORSE CREEK
CSJ0030-05-067
Proj IDSTP 2019(210)
Work TypeSEALCOAT
 
187.5829058028.422208001.2524.3
Work Order12-18-18
Work Began00-00-00
Work Completed
Time Computed01-17-19
Contract Working Days92
Addl Days Granted0
Working Days Charged62
Percent Time Used67
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-067
INNOVATIVE ROADWAY SOLUTIONS, LLC (7.24)
TRP CONSTRUCTION GROUP, LLC (6.79)
Contract #11183032
Totals9058028.42114827.852208001.2524.3

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-019
Proj IDSTP 2018(282)
Work TypeSEALCOAT
 
290.15014437253.1813866986.4196.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-22-17
Work Began00-00-00
Work Completed
Time Computed01-21-18
Contract Working Days98
Addl Days Granted0
Working Days Charged95
Percent Time Used96
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-019
BARRICADES PLUS, LLC (0.99)
STRIPE-A-ZONE, INC. (8.20)
J. LEE MILLIGAN, INC. (1.85)
Contract #11173001
Totals14437253.180.0013866986.4196.0

CountyDALLAM
HighwayUS 87
From0.804 MILES EAST OF FM 296
To7.455 MILES EAST OF FM 296
CSJ0040-01-050
Proj IDSTP 1802(176)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
42.66410092335.716648013.3565.8
Work Order07-18-18
Work Began00-00-00
Work Completed
Time Computed08-16-18
Contract Working Days120
Addl Days Granted0
Working Days Charged87
Percent Time Used72
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0040-01-050
BARRICADES UNLIMITED (1.89)
DIAMOND SURFACE, INC. (0.35)
DIIBS SPECIALISTS (0.38)
DUSTROL, INC. (0.39)
GIBSON & ASSOCIATES, INC. (1.22)
HJC FARMS, INC. (0.29)
H & F TRUCKING (8.66)
TX ENVIRONMENTAL (0.40)
G AND G OPERATORS, LTD. (2.22)
GARY A. CRAIN, INC. (0.05)
Contract #05183254
Totals10092335.712253042.366648013.3565.8

CountyDALLAM
HighwayUS 87
From0.6 MILES NW OF FM 1879
To0.5 MILES NE OF FM 1727
CSJ0040-03-064
Proj IDC 40-3-64
Work TypeOVERLAY
 
16.24417114341.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193006
Totals17114341.970.000.000.0

CountyPOTTER
HighwayUS 87
FromAMARILO CREEK
ToMOORE COUNTY LINE
CSJ0041-05-050
Proj IDNH 2018(435)
Work TypeOVERLAY
 
17.36812042105.8212976880.5299.9
CountyPOTTER
HighwayUS 287
FromIH 40
ToCARSON COUNTY LINE
CSJ0042-01-030
Proj IDNH 2018(435)
Work TypeOVERLAY
 
3.8182523248.652574940.8599.9
CountyCARSON
HighwayUS 287
FromCARSON COUNTY LINE
ToARMSTRONG COUNTY LINE
CSJ0042-02-020
Proj IDNH 2018(435)
Work TypeOVERLAY
 
0.510331656.09368728.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed03-19-18
Contract Working Days146
Addl Days Granted25
Working Days Charged196
Percent Time Used114
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-050
DUSTROL, INC. (26.03)
BARRICADES UNLIMITED (1.55)
DUSTIN ALLEN, INC. (2.12)
WOLFE CONSTRUCTION GROUP, INC. (0.31)
DK CONTRACTING, LLC (1.03)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.27)
Contract #01183203
Totals14897010.560.0015920550.3299.9

CountyPOTTER ETC
HighwayUS 87 ETC
FromAT SAND CREEK 5 MI N OF CAN RIVER
To.
CSJ0041-05-052
Proj IDBR 2019(914)
Work TypeBRIDGE MAINTENANCE
 
0.1291849686.20118850.006.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-03-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-052
BARRICADES UNLIMITED (1.52)
PANOLA SIGN & BARRICADE, INC. (1.54)
MORRIS COUNTY CONTRACTORS, L.L.C. (10.27)
WOLFE CONSTRUCTION GROUP, INC. (0.82)
Contract #05193036
Totals1849686.20118850.00118850.006.4

CountyPOTTER
HighwayUS 87
FromSBL AT BNSF RR
To.
CSJ0041-07-106
Proj IDBR 2019(457)
Work TypeREPLACE BRIDGE
 
0.8234976890.281015451.7720.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days157
Addl Days Granted0
Working Days Charged46
Percent Time Used29
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-106
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.20)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.96)
PANOLA SIGN & BARRICADE, INC. (0.49)
SOUTH TEXAS PAINTING COMPANY (0.11)
WOLFE CONSTRUCTION GROUP, INC. (0.29)
BARRICADES UNLIMITED (0.96)
RK HALL, LLC (8.98)
TEXOP CONSTRUCTION (0.67)
BOWMAN ENGINEERING & CONSULTING, INC. (0.26)
Contract #02193235
Totals4976890.28540880.561015451.7720.4

CountyPOTTER ETC
HighwayUS 87 ETC
FromNE 15TH
ToFM 1719
CSJ0041-07-107
Proj IDNH 2019(212)
Work TypeSEALCOAT
 
97.71412390506.459636267.4477.7
Work Order02-13-19
Work Began00-00-00
Work Completed
Time Computed03-15-19
Contract Working Days92
Addl Days Granted0
Working Days Charged51
Percent Time Used55
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-107
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (16.57)
INNOVATIVE ROADWAY SOLUTIONS LLC (8.85)
TEXOP CONSTRUCTION (0.80)
BARRICADES UNLIMITED (0.74)
BARRICADES UNLIMITED (6.84)
Contract #11183033
Totals12390506.454044258.449636267.4477.7

CountyARMSTRONG
HighwayUS 287
From8.6 MILES EAST OF CARSON COUNTY LIN
To.3 MILES WEST OF CLAUDE CITY LIMITS
CSJ0042-03-042
Proj IDNH 2019(052)
Work TypeOVERLAY
 
5.5873503109.000.000.0
CountyARMSTRONG
HighwayUS 287
From0.2 MILES EAST OF FM 1151
To1 MILE WEST OF FM 2889
CSJ0042-04-042
Proj IDNH 2019(052)
Work TypeOVERLAY
 
5.5373088438.920.000.0
Work Order10-16-18
Work Began00-00-00
Work Completed
Time Computed11-15-18
Contract Working Days73
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09183214
Totals6591547.920.000.000.0

CountySHERMAN
HighwayUS 287
FromUS 54 STRATFORD
ToMOORE COUNTY LINE
CSJ0066-03-041
Proj IDNH 2019(458)
Work TypeOVERLAY
 
19.58514094923.0871289.650.5
CountySHERMAN
HighwayUS 287
From0.321 MILES SOUTH OF US 54
ToMOORE COUNTY LINE
CSJ0066-03-043
Proj IDSTP 2019(459)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
38.700445275.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days147
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-03-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02193004
Totals14540198.830.0071289.650.4

CountyMOORE
HighwayUS 87
FromDIVIDED 4 LANE SOUTH OF DUMAS
ToPOTTER COUNTY LINE
CSJ0066-05-066
Proj IDC 66-5-66
Work TypeREHAB EXISTING ROADWAY
 
15.50610790483.201425358.2713.2
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-068
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.478394503.000.000.0
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-069
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.47858000.000.000.0
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed06-13-18
Contract Working Days120
Addl Days Granted0
Working Days Charged41
Percent Time Used34
Contractor(s)
HIGHWAY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-066
ALAMO BRIDGE AND ROAD, LLC (0.34)
BARRICADES UNLIMITED (2.08)
DIIBS SPECIALISTS (3.85)
HUDSON, INC. (0.94)
MARCOM"S MOWING SERVICE, LLC (0.71)
WOLFE CONSTRUCTION GROUP, INC. (0.10)
WEST TEXAS ROCK RESOURCES, LLC (0.53)
Contract #04183214
Totals11242986.20199010.931425358.2712.6

CountyDEAF SMITH
HighwayIH 40
FromVARIOUS LOCATIONS ON IH 40
To.
CSJ0090-01-032
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.0107422545.006414514.3486.4
CountyRANDALL
HighwayIH 27
FromVARIOUS LOCATIONS ON IH 27
To.
CSJ0168-09-174
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.010839417.006000.000.7
Work Order05-03-18
Work Began05-29-18
Work Completed
Time Computed06-04-18
Contract Working Days377
Addl Days Granted4
Working Days Charged274
Percent Time Used71
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-01-032
BARRICADES UNLIMITED (0.40)
THE TRUESDELL CORPORATION (5.77)
WOLFE CONSTRUCTION GROUP, INC. (0.41)
SCOTT DERR PAINTING CO, LLC (1.81)
AML ENVIRONMENTAL, LLC (0.00)
PRIMATE CONSTRUCTION, INC. (0.12)
MCL CONTRACTING, LLC (0.24)
ALAMO BROTHERS CONCRETE, INC. (0.64)
Contract #04183009
Totals8261962.0058080.006420514.3477.7

CountyPOTTER ETC
HighwaySL 279 ETC
FromAT WESTERN STREET
To.
CSJ0090-05-095
Proj IDSTP 2018(815)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.8161568719.48486161.0430.9
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed07-14-18
Contract Working Days173
Addl Days Granted0
Working Days Charged125
Percent Time Used72
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-095
ARTEX ELECTRIC, INC. (26.27)
CONCRETE CONNECTION (3.84)
BARRICADES UNLIMITED (2.13)
Contract #05183244
Totals1568719.48132839.90486161.0430.9

CountyPOTTER
HighwayIH 40
From.2 MILES EAST OF ADKISSON RD
ToBI 40-D
CSJ0090-05-098
Proj IDNH 2019(408)
Work TypeOVERLAY
 
8.0167778312.160.000.0
Work Order02-20-19
Work Began00-00-00
Work Completed
Time Computed03-22-19
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-098
DK CONTRACTING, LLC (1.07)
PRIMATE CONSTRUCTION, LP (0.81)
WOLFE CONSTRUCTION GROUP, INC. (0.06)
BARRICADES UNLIMITED (2.94)
DUSTIN ALLEN, INC. (4.45)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.34)
TEXOP CONSTRUCTION (1.73)
VANCE BROTHERS, INC. (0.64)
Contract #01193038
Totals7778312.160.000.000.0

CountyOLDHAM
HighwayBI 40--
FromEAST OF VEGA AT IH 40
To.
CSJ0090-09-006
Proj IDBR 2019(915)
Work TypeBRIDGE MAINTENANCE
 
0.3695412115.000.000.0
CountyCARSON
HighwayFM 2161
FromAT IH 40
To.
CSJ1884-02-011
Proj IDBR 2019(916)
Work TypeBRIDGE MAINTENANCE
 
0.2581792277.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days258
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-09-006
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193229
Totals7204392.000.000.000.0

CountyRANDALL
HighwayIH 27
FromSUNDOWN LANE
ToBELL STREET
CSJ0168-09-161
Proj IDDMO 2012(757)
Work TypeREHAB EXISTING ROADWAY
 
2.17215278484.998401937.2154.9
CountyRANDALL
HighwaySL 335
FromIH 27
ToBELL STREET
CSJ2635-02-029
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
0.4265927968.281313214.6522.1
CountyRANDALL
HighwaySL 335
FromWEST OF COULTER
ToIH 27
CSJ2635-03-018
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
1.07621169039.1311010040.2052.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began01-08-18
Work Completed
Time Computed00-00-00
Contract Working Days720
Addl Days Granted36
Working Days Charged396
Percent Time Used52
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-161
A BROTHERS MILLING, LLC (0.44)
BARRICADES UNLIMITED (0.88)
DIIBS SPECIALISTS (0.32)
HARDY TREES, INC. (0.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.10)
OSCAR ORDUNO, INC. (1.42)
PRIMATE CONSTRUCTION, INC. (0.05)
QLVS, INC. DBA PHASE 3 ELECTRIC (0.81)
S & S BRIDGE PAINTING, INC. (0.02)
UTILITY CONTRACTORS OF AMERICA, LTD (18.08)
WEBBER BARRIER SERVICES, LLC. (1.65)
WILLIS ELECTRIC CO., LP (6.48)
BOWMAN ENGINEERING & CONSULTING, INC. (0.07)
H & F TRUCKING (1.82)
AMARILLO UTILITY CONTRACTORS (0.14)
SCDI (0.02)
BOWMAN ENGINEERING & CONSULTING, INC. (0.07)
ADRIAN CONTRACTING (0.04)
PBX BRIDGE COMPANY (0.17)
WILLIAMS DITCHING, LLC (0.00)
MICA CORPORATION (0.87)
Contract #07173201
Totals42375492.401271691.5420725192.0648.9

CountyRANDALL
HighwayUS 60
FromIH 27 INTERCHANGE
ToSP 48 IN CANYON
CSJ0168-09-164
Proj IDNH 2019(267)
Work TypeOVERLAY
 
2.6853593547.48683345.0219.0
CountyPOTTER
HighwaySL 335
FromRANDALL COUNTY LINE
ToIH 40
CSJ2635-01-037
Proj IDNH 2019(267)
Work TypeOVERLAY
 
0.623325341.9470854.8021.7
CountyRANDALL
HighwaySL 335
FromFM 1541
ToPOTTER COUNTY LINE
CSJ2635-02-035
Proj IDNH 2019(267)
Work TypeOVERLAY
 
9.5526790088.562340167.7934.4
Work Order01-11-19
Work Began00-00-00
Work Completed
Time Computed02-11-19
Contract Working Days150
Addl Days Granted0
Working Days Charged72
Percent Time Used48
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-164
ALAMO BROTHERS CONCRETE INC (12.48)
BARRICADES UNLIMITED (1.95)
WILLIS ELECTRIC CO., LP (0.52)
WOLFE CONSTRUCTION GROUP, INC. (0.06)
SCR CIVIL CONSTRUCTION, LLC (0.79)
HJC FARMS, INC. (4.18)
DUSTROL, INC. (9.08)
Contract #12183207
Totals10708977.981565844.653094367.6128.8

page 1 | page 2 | page 3