Monthly State Let Construction Report For Amarillo District As Of Feb 14, 2020 Page 1 Of 3

Last Update: Friday, February 14, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE
HighwayUS 83
FromCR K SOUTH OF PERRYTON
ToWOLF CREEK
CSJ0030-02-052
Proj IDSTP 2019(603)
Work TypeOVERLAY
 
25.39613814377.4564020.000.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193005
Totals13814377.450.0064020.000.4

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.7042097.001.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
BARRICADES UNLIMITED (11.92)
CONCRETE CONNECTION (5.15)
Contract #03193227
Totals2152762.700.0042097.001.9

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromLIPSCOMB COUNTY LINE
ToHORSE CREEK
CSJ0030-05-067
Proj IDSTP 2019(210)
Work TypeSEALCOAT
 
187.5829058028.426015935.8666.5
Work Order12-18-18
Work Began00-00-00
Work Completed
Time Computed01-17-19
Contract Working Days92
Addl Days Granted0
Working Days Charged100
Percent Time Used108
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-067
INNOVATIVE ROADWAY SOLUTIONS, LLC (7.24)
TRP CONSTRUCTION GROUP, LLC (6.79)
Contract #11183032
Totals9058028.420.006015935.8666.5

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-019
Proj IDSTP 2018(282)
Work TypeSEALCOAT
 
290.15014437253.1814337582.3399.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-22-17
Work Began00-00-00
Work Completed
Time Computed01-21-18
Contract Working Days98
Addl Days Granted0
Working Days Charged140
Percent Time Used142
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-019
BARRICADES PLUS, LLC (0.99)
STRIPE-A-ZONE, INC. (8.20)
J. LEE MILLIGAN, INC. (1.85)
BARRICADES UNLIMITED (0.13)
Contract #11173001
Totals14437253.180.0014337582.3399.6

CountyDALLAM
HighwayUS 87
From0.804 MILES EAST OF FM 296
To7.455 MILES EAST OF FM 296
CSJ0040-01-050
Proj IDSTP 1802(176)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
42.66410092335.7110544394.0399.9
Work Order07-18-18
Work Began00-00-00
Work Completed
Time Computed08-16-18
Contract Working Days120
Addl Days Granted15
Working Days Charged139
Percent Time Used102
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0040-01-050
BARRICADES UNLIMITED (1.89)
DIAMOND SURFACE, INC. (0.35)
DIIBS SPECIALISTS (0.38)
DUSTROL, INC. (0.39)
GIBSON & ASSOCIATES, INC. (1.22)
HJC FARMS, INC. (0.29)
H & F TRUCKING (8.66)
TX ENVIRONMENTAL (0.40)
G AND G OPERATORS, LTD. (2.22)
GARY A. CRAIN, INC. (0.05)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.40)
Contract #05183254
Totals10092335.714478.1110544394.0399.9

CountyDALLAM
HighwayUS 87
From0.6 MILES NW OF FM 1879
To0.5 MILES NE OF FM 1727
CSJ0040-03-064
Proj IDC 40-3-64
Work TypeOVERLAY
 
16.24417114341.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193006
Totals17114341.970.000.000.0

CountyHARTLEY
HighwayUS 87
FromAT FM 281
To.
CSJ0041-01-047
Proj IDSTP 2020(511)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20099805.000.000.0
CountyHARTLEY
HighwayFM 281
FromFM 807 NORTH
ToMOORE COUNTY LINE
CSJ1727-01-016
Proj IDSTP 2020(512)
Work TypeREHABILITATION OF EXISTING ROAD
 
9906204.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203008
Totals10006009.450.000.000.0

CountyPOTTER ETC
HighwayUS 87 ETC
FromAT SAND CREEK 5 MI N OF CAN RIVER
To.
CSJ0041-05-052
Proj IDBR 2019(914)
Work TypeBRIDGE MAINTENANCE
 
0.1291849686.20973858.1452.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-03-19
Work Began07-30-19
Work Completed
Time Computed00-00-00
Contract Working Days160
Addl Days Granted0
Working Days Charged105
Percent Time Used65
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-052
BARRICADES UNLIMITED (1.52)
PANOLA SIGN & BARRICADE, INC. (1.54)
MORRIS COUNTY CONTRACTORS, L.L.C. (10.27)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.82)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.43)
Contract #05193036
Totals1849686.20102847.50973858.1452.6

CountyPOTTER
HighwayUS 87
FromSBL AT BNSF RR
To.
CSJ0041-07-106
Proj IDBR 2019(457)
Work TypeREPLACE BRIDGE
 
0.8234976890.282473772.7349.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-02-19
Work Began05-21-19
Work Completed
Time Computed00-00-00
Contract Working Days157
Addl Days Granted0
Working Days Charged150
Percent Time Used95
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-106
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.20)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.96)
PANOLA SIGN & BARRICADE, INC. (0.49)
SOUTH TEXAS PAINTING COMPANY (0.11)
WOLFE CONSTRUCTION GROUP, INC. (0.29)
BARRICADES UNLIMITED (0.96)
RK HALL, LLC (8.98)
TEXOP CONSTRUCTION (0.67)
BOWMAN ENGINEERING & CONSULTING, INC. (0.26)
L A FULLER & SONS CONSTRUCTION, LTD. (0.13)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
DUSTIN ALLEN, INC. (0.00)
BOWMAN ENGINEERING & CONSULTING, INC. (0.30)
Contract #02193235
Totals4976890.28294673.112473772.7349.7

CountyPOTTER ETC
HighwayUS 87 ETC
FromNE 15TH
ToFM 1719
CSJ0041-07-107
Proj IDNH 2019(212)
Work TypeSEALCOAT
 
97.71412390506.4513449804.3499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-13-19
Work Began00-00-00
Work Completed
Time Computed03-15-19
Contract Working Days92
Addl Days Granted0
Working Days Charged74
Percent Time Used80
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-107
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (16.57)
INNOVATIVE ROADWAY SOLUTIONS LLC (8.85)
TEXOP CONSTRUCTION (0.80)
BARRICADES UNLIMITED (0.74)
BARRICADES UNLIMITED (6.84)
Contract #11183033
Totals12390506.450.0013449804.3499.9

CountyPOTTER ETC
HighwaySL 434 ETC
FromUS 87
ToCHEERY AVE
CSJ0041-08-004
Proj IDSTP 2020(202)
Work TypeSEAL COAT
 
223.07112785668.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-28-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-08-004
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11193002
Totals12785668.360.000.000.0

CountyARMSTRONG
HighwayUS 287
From8.6 MILES EAST OF CARSON COUNTY LIN
To.3 MILES WEST OF CLAUDE CITY LIMITS
CSJ0042-03-042
Proj IDNH 2019(052)
Work TypeOVERLAY
 
5.5873503109.003852373.5099.9
CountyARMSTRONG
HighwayUS 287
From0.2 MILES EAST OF FM 1151
To1 MILE WEST OF FM 2889
CSJ0042-04-042
Proj IDNH 2019(052)
Work TypeOVERLAY
 
5.5373088438.923157746.1399.9
Work Order10-16-18
Work Began09-11-19
Work Completed
Time Computed11-15-18
Contract Working Days73
Addl Days Granted0
Working Days Charged60
Percent Time Used82
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-042
BARRICADES UNLIMITED (2.18)
HUDSON, INC. SOUTH (1.39)
MARCOM"S MOWING SERVICE, LLC (1.30)
ALAMO BROTHERS CONCRETE INC (0.23)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.28)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.12)
Contract #09183214
Totals6591547.9295265.787010119.6399.9

CountyARMSTRONG
HighwayUS 287
From1 MILE WEST OF FM 2889
ToFM 294
CSJ0042-04-043
Proj IDNH 2020(352)
Work TypeOVERLAY
 
10.1028973976.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0042-04-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12193207
Totals8973976.410.000.000.0

CountyDALLAM
HighwayUS 287
FromOKLAHOMA STATE LINE
ToSHERMAN COUNTY LINE
CSJ0066-01-021
Proj IDNH 2020(203)
Work TypeREHABILITATION OF EXISTING ROAD
 
12.4647973152.820.000.0
CountySHERMAN
HighwayUS 287
From2 MILES NORTH OF PURNELL STREET
ToPURNELL STREET
CSJ0066-02-034
Proj IDHP 2020(515)
Work TypeWIDEN NON-FREEWAY
 
2.0004004876.830.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-01-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11193004
Totals11978029.650.000.000.0

CountySHERMAN
HighwayUS 287
FromUS 54 STRATFORD
ToMOORE COUNTY LINE
CSJ0066-03-041
Proj IDNH 2019(458)
Work TypeOVERLAY
 
19.58514094923.08951386.106.7
CountySHERMAN
HighwayUS 287
From0.321 MILES SOUTH OF US 54
ToMOORE COUNTY LINE
CSJ0066-03-043
Proj IDSTP 2019(459)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
38.700445275.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days147
Addl Days Granted0
Working Days Charged72
Percent Time Used48
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-03-041
BARRICADES UNLIMITED (1.95)
DUSTROL, INC. (2.13)
ALAMO BROTHERS CONCRETE INC (0.43)
GIBSON & ASSOCIATES, INC. (0.65)
HJC FARMS, INC. (2.29)
DK CONTRACTING, LLC (2.97)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.15)
Contract #02193004
Totals14540198.8386135.59951386.106.5

CountyMOORE
HighwayUS 87
FromDIVIDED 4 LANE SOUTH OF DUMAS
ToPOTTER COUNTY LINE
CSJ0066-05-066
Proj IDC 66-5-66
Work TypeREHAB EXISTING ROADWAY
 
15.50610790483.204014487.2737.2
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-068
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.478394503.0023354.005.9
CountyMOORE
HighwayUS 87
From0.863 MILES SOUTH OF FM 722
ToPOTTER COUNTY LINE
CSJ0066-05-069
Proj IDSTP 2018(776)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
15.47858000.000.000.0
Work Order05-14-18
Work Began00-00-00
Work Completed
Time Computed06-13-18
Contract Working Days120
Addl Days Granted0
Working Days Charged123
Percent Time Used102
Contractor(s)
HIGHWAY CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-066
ALAMO BRIDGE AND ROAD, LLC (0.34)
BARRICADES UNLIMITED (2.08)
DIIBS SPECIALISTS (3.85)
HUDSON, INC. (0.94)
MARCOM"S MOWING SERVICE, LLC (0.71)
WOLFE CONSTRUCTION GROUP, INC. (0.10)
WEST TEXAS ROCK RESOURCES, LLC (0.53)
VARGAS JR. TRUCKING (0.00)
Contract #04183214
Totals11242986.2050472.884037841.2735.9

CountyDEAF SMITH
HighwayIH 40
FromVARIOUS LOCATIONS ON IH 40
To.
CSJ0090-01-032
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.0107422545.007271444.3797.9
CountyRANDALL
HighwayIH 27
FromVARIOUS LOCATIONS ON IH 27
To.
CSJ0168-09-174
Proj IDBR 2018(777)
Work Type2018 BMIP PROGRAM
 
0.010839417.00203585.0024.2
Work Order05-03-18
Work Began05-29-18
Work Completed
Time Computed06-04-18
Contract Working Days377
Addl Days Granted4
Working Days Charged376
Percent Time Used98
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-01-032
BARRICADES UNLIMITED (0.40)
THE TRUESDELL CORPORATION (5.77)
WOLFE CONSTRUCTION GROUP, INC. (0.41)
SCOTT DERR PAINTING CO, LLC (1.81)
AML ENVIRONMENTAL, LLC (0.00)
PRIMATE CONSTRUCTION, INC. (0.12)
MCL CONTRACTING, LLC (0.24)
ALAMO BROTHERS CONCRETE, INC. (0.64)
Contract #04183009
Totals8261962.00265596.037475029.3790.4

CountyPOTTER ETC
HighwaySL 279 ETC
FromAT WESTERN STREET
To.
CSJ0090-05-095
Proj IDSTP 2018(815)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.8161568719.481143153.0675.2
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed07-14-18
Contract Working Days173
Addl Days Granted0
Working Days Charged221
Percent Time Used127
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-095
ARTEX ELECTRIC, INC. (26.27)
CONCRETE CONNECTION (3.84)
BARRICADES UNLIMITED (2.13)
Contract #05183244
Totals1568719.4880617.151143153.0675.2

CountyPOTTER
HighwayIH 40
From.2 MILES EAST OF ADKISSON RD
ToBI 40-D
CSJ0090-05-098
Proj IDNH 2019(408)
Work TypeOVERLAY
 
8.0167778312.165043517.7764.8
Work Order02-20-19
Work Began08-13-19
Work Completed
Time Computed03-22-19
Contract Working Days85
Addl Days Granted10
Working Days Charged45
Percent Time Used47
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-098
DK CONTRACTING, LLC (1.07)
PRIMATE CONSTRUCTION, LP (0.81)
WOLFE CONSTRUCTION GROUP, INC. (0.06)
BARRICADES UNLIMITED (2.94)
DUSTIN ALLEN, INC. (4.45)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.34)
TEXOP CONSTRUCTION (1.73)
VANCE BROTHERS, INC. (0.64)
Contract #01193038
Totals7778312.160.005043517.7764.8

CountyOLDHAM
HighwayBI 40--
FromEAST OF VEGA AT IH 40
To.
CSJ0090-09-006
Proj IDBR 2019(915)
Work TypeBRIDGE MAINTENANCE
 
0.3695412115.001087805.0020.0
CountyCARSON
HighwayFM 2161
FromAT IH 40
To.
CSJ1884-02-011
Proj IDBR 2019(916)
Work TypeBRIDGE MAINTENANCE
 
0.2581792277.00681880.0038.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-19
Work Began09-16-19
Work Completed
Time Computed00-00-00
Contract Working Days258
Addl Days Granted30
Working Days Charged83
Percent Time Used28
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-09-006
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.32)
ALAMO BROTHERS CONCRETE INC (10.86)
BARRICADES UNLIMITED (2.43)
MCL CONTRACTING, LLC (0.51)
BLACKTOP INDUSTRIES LLC (1.64)
PENHALL COMPANY (0.16)
L A FULLER & SONS CONSTRUCTION, LTD. (16.07)
Contract #05193229
Totals7204392.00225015.001769685.0024.5

page 1 | page 2 | page 3