Monthly State Let Construction Report For Amarillo District As Of Mar 13, 2024 Page 1 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE
HighwayUS 83
FromCR K SOUTH OF PERRYTON
ToWOLF CREEK
CSJ0030-02-052
Proj IDSTP 2019(603)
Work TypeOVERLAY
 
25.39613814377.4516281746.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began05-18-20
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted35
Working Days Charged224
Percent Time Used132
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-052
BARRICADES UNLIMITED (1.98)
HJC FARMS, INC. (2.34)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.33)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.07)
GIBSON & ASSOCIATES, INC. (1.23)
Contract #03193005
Totals13814377.450.0016281746.4699.9

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.701693926.6778.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began09-29-20
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged111
Percent Time Used60
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
CONCRETE CONNECTION (5.15)
FC TRAFFIC CONTROL, INC. (1.57)
LINEAR TRAFFIC MARKINGS LLC (1.67)
CONCRETE CONNECTION, LLC (5.15)
CIRCLE FOUR ENTERPRISES, LLC (1.15)
MEDELLIN HDD LLC (0.86)
BARRICADES UNLIMITED (1.80)
TURKEY CREEK HDD, LLC (0.83)
Contract #03193227
Totals2152762.70634718.011693926.6778.6

CountyHEMPHILL ETC
HighwayUS 60 ETC
FromAT CANADIAN RIVER
To.
CSJ0030-05-073
Proj IDBR 2022(398)
Work TypeBRIDGE MAINTENANCE
 
4.5658566511.528936285.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-19-22
Work Began03-27-23
Work Completed
Time Computed00-00-00
Contract Working Days188
Addl Days Granted0
Working Days Charged178
Percent Time Used94
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-073
ALAMO BROTHERS CONCRETE INC (0.84)
BARRICADES UNLIMITED (0.88)
FC TRAFFIC CONTROL, INC. (0.48)
HJC FARMS, INC. (0.75)
S & S BRIDGE PAINTING, INC. (1.93)
TRP CONSTRUCTION GROUP, LLC (0.88)
A-CORE CONCRETE CUTTING, INC. (2.31)
NELSON INDUSTRIAL SERVICES, INC. (0.28)
Contract #03223005
Totals8566511.5251321.008936285.3999.9

CountyHEMPHILL
HighwayUS 60
FromBIRCH STREET IN CANADIAN
ToFM 2388
CSJ0030-06-060
Proj IDF 2023(455)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.85013300304.663367896.8525.3
CountyHEMPHILL
HighwayUS 60
FromFM 2388
ToC&G N OF CANADIAN
CSJ0030-06-067
Proj IDC 30-6-67
Work TypeSAFETY IMPROVEMENT PROJECTS
 
105295.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-23
Work Began05-11-23
Work Completed
Time Computed00-00-00
Contract Working Days305
Addl Days Granted0
Working Days Charged144
Percent Time Used47
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-060
DK CONTRACTING, LLC (0.37)
HJC FARMS, INC. (0.47)
PBJ CONSTRUCTION (1.66)
APOLLO CONSTRUCTORS, INC. (6.98)
FC TRAFFIC CONTROL, INC. (0.36)
L A FULLER & SONS CONSTRUCTION, LTD. (28.16)
TRP CONSTRUCTION GROUP, LLC (2.48)
TORO BRAVO CONSTRUCTION, LLC (0.68)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
Contract #02233209
Totals13405600.41115520.583367896.8525.1

CountyHEMPHILL ETC
HighwayUS 60 ETC
FromUS 83/ US 60 INTERCHANGE
ToBIRCH ST IN CANADIAN
CSJ0030-06-066
Proj IDF 2023(179)
Work TypeSEAL COAT
 
233.87221819571.0421089332.8096.6
Work Order01-26-23
Work Began06-02-23
Work Completed
Time Computed06-02-23
Contract Working Days97
Addl Days Granted0
Working Days Charged78
Percent Time Used80
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-066
CENTERLINE TECHNOLOGIES, LLC (6.53)
FC TRAFFIC CONTROL, INC. (0.73)
INNOVATIVE ROADWAY SOLUTIONS, LLC (8.20)
BRANNAN PAVING CO., LTD. (33.76)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (5.25)
RED SIXTEEN CONSTRUCTION, INC (0.27)
Contract #11223002
Totals21819571.04244575.9221089332.8096.6

CountyHEMPHILL
HighwayUS 83
FromFM 277
ToWHEELER COUNTY LINE
CSJ0030-07-022
Proj IDF 2023(180)
Work TypeOVERLAY
 
6.9285382629.985592378.7599.9
Work Order12-05-22
Work Began07-17-23
Work Completed
Time Computed01-04-23
Contract Working Days71
Addl Days Granted0
Working Days Charged62
Percent Time Used87
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-022
BARRICADES UNLIMITED (1.65)
DIIBS SPECIALISTS, LLC (6.57)
DK CONTRACTING, LLC (0.91)
DUSTROL, INC. (0.68)
H & F TRUCKING (0.18)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.34)
TRP CONSTRUCTION GROUP, LLC (1.28)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.17)
W. S. CONSTRUCTION COMPANY (3.05)
MOBILE ENTERPRISES, INC. (0.26)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.08)
Contract #11223025
Totals5382629.980.005592378.7599.9

CountyDALLAM
HighwayUS 87
FromAT BU 87-B (7TH STREET)
To.
CSJ0040-03-068
Proj IDF 2021(646)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.222354993.20381220.8399.9
CountyHARTLEY
HighwayUS 87
FromAT 16TH STREET
To.
CSJ0041-01-048
Proj IDSTP 2021(647)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200248962.61267050.9599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-03-23
Work Began04-24-23
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged140
Percent Time Used159
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-068
TURKEY CREEK HDD, LLC (2.40)
CONCRETE CONNECTION, LLC (23.69)
FC TRAFFIC CONTROL, INC. (0.33)
LINEAR TRAFFIC MARKINGS LLC (6.16)
Contract #06213032
Totals603955.810.00648271.7899.9

CountyHARTLEY ETC
HighwayUS 87 ETC
FromDALHART CURB AND GUTTER
ToUS 87/385 SPLIT
CSJ0041-01-050
Proj IDF 2B23(294)
Work TypeSEAL COAT
 
107.39319650397.700.000.0
Work Order01-11-24
Work Began00-00-00
Work Completed
Time Computed07-22-24
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-01-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233003
Totals19650397.700.000.000.0

CountyHARTLEY
HighwayUS 385
FromUS 87 IN HARTLEY
ToCHANNING
CSJ0041-02-016
Proj IDF 2021(441)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.9249656579.228638331.2590.8
Work Order05-20-21
Work Began11-01-21
Work Completed
Time Computed06-19-21
Contract Working Days327
Addl Days Granted0
Working Days Charged450
Percent Time Used137
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-02-016
W. S. CONSTRUCTION COMPANY (14.84)
BARRICADES UNLIMITED (2.44)
HJC FARMS, INC. (7.32)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.17)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
Contract #04213207
Totals9656579.221094911.988638331.2590.8

CountyPOTTER
HighwayUS 87
From1.75 MI NORTH OF CANADIAN RIVER
To5.0 MI NORTH OF FM 1719
CSJ0041-05-055
Proj IDSTP 2024(780)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.3271814586.800.000.0
CountyPOTTER
HighwayUS 87
From5.0 MI NORTH OF FM 1719
ToFM 1719
CSJ0041-07-122
Proj IDSTP 2024(780)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0041080198.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days163
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243025
Totals2894785.300.000.000.0

CountyPOTTER
HighwayUS 87
FromCENTRAL AVE. NB BRIDGE
To.
CSJ0041-07-113
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.0723086684.05789488.0725.5
CountyPOTTER
HighwayUS 87
FromCENTRAL AVE. SB BRIDGE
To.
CSJ0041-07-114
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.0722901074.20515004.3917.7
CountyPOTTER
HighwayUS 87
FromHASTINGS AVE. NB BRIDGE
To.
CSJ0041-07-115
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.1252834563.95462965.4916.3
CountyPOTTER
HighwayUS 87
FromHASTINGS AVE. SB BRIDGE
To.
CSJ0041-07-116
Proj IDBR 2023(597)
Work TypeBRIDGE REPLACEMENT
 
0.1252843410.15358543.1312.6
Work Order05-17-23
Work Began12-01-23
Work Completed
Time Computed06-15-23
Contract Working Days302
Addl Days Granted0
Working Days Charged49
Percent Time Used16
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-113
ALAMO BROTHERS CONCRETE INC (20.46)
APOLLO CONSTRUCTORS, INC. (2.38)
BARRICADES UNLIMITED (0.44)
HARDY HOLE DRILLING (3.70)
HJC FARMS, INC. (3.07)
PRIMATE CONSTRUCTION, LP (0.67)
TRP CONSTRUCTION GROUP, LLC (0.62)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
Contract #04233208
Totals11665732.35441577.002126001.0818.2

CountyPOTTER
HighwayUS 87
FromUS 87 AT S 15TH AVE BRIDGE
To.
CSJ0041-07-117
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0371343373.75966202.4571.9
CountyPOTTER
HighwayUS 87
FromUS 87 AT 15TH AVE NB BRIDGE
To.
CSJ0041-07-118
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.0371346900.50927723.4568.8
CountyPOTTER
HighwayIH 40
FromIH 40 AT CROCKETT ST EB BRIDGE
To.
CSJ0275-01-232
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.1042160190.35139000.006.4
CountyPOTTER
HighwayIH 40
FromIH 40 AT CROCKETT ST WB BRIDGE
To.
CSJ0275-01-233
Proj IDBR 2023(503)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.1042117950.05169500.008.0
Work Order04-25-23
Work Began08-29-23
Work Completed
Time Computed05-25-23
Contract Working Days240
Addl Days Granted0
Working Days Charged129
Percent Time Used53
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-117
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (1.43)
BARRICADES UNLIMITED (0.68)
DUKE ELECTRIC CO., INC. (0.92)
DUSTIN ALLEN, INC. (0.86)
DUSTROL, INC. (0.83)
H & F TRUCKING (0.10)
TORO BRAVO CONSTRUCTION, LLC (2.03)
ALAMO BROTHERS CONCRETE INC (4.98)
TRP CONSTRUCTION GROUP, LLC (1.69)
PENHALL COMPANY (0.36)
Contract #03233043
Totals6968414.65121318.002202425.9031.6

CountyMOORE
HighwayUS 287
FromSOUTH OF FM 281
ToDUMAS
CSJ0066-04-079
Proj IDF 2021(699)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.9064229617.382379321.9359.1
Work Order08-25-21
Work Began03-30-22
Work Completed
Time Computed09-24-21
Contract Working Days137
Addl Days Granted0
Working Days Charged265
Percent Time Used193
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-079
MARCOM"S MOWING SERVICE, LLC (3.01)
DUSTROL, INC. (0.25)
TOTAL HIGHWAY MAINTENANCE, LLC (8.57)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.48)
LYNCO CONSTRUCTION (5.06)
LONE STAR EROSION CONTROL (2.34)
TEXAS GUARDRAIL CONTRACTORS LLC (9.90)
Contract #07213217
Totals4229617.38124924.322379321.9359.1

CountyMOORE
HighwayUS 87
FromSOUTH CITY LIMITS OF DUMAS
ToSH 152
CSJ0066-05-065
Proj IDNH 2013(606)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.56336473058.2837138944.1098.2
CountyMOORE
HighwayUS 87
FromAT SH 152
To.
CSJ0066-05-070
Proj IDSTP 2021(393)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.100327315.70728220.9599.9
Work Order05-20-21
Work Began07-06-21
Work Completed
Time Computed06-19-21
Contract Working Days838
Addl Days Granted0
Working Days Charged694
Percent Time Used82
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-065
BARRICADES UNLIMITED (1.97)
JR WEST TEXAS CONCRETE LLC (8.60)
L&H ELECTRICAL, LLC (2.71)
DUSTROL, INC. (0.89)
L A FULLER & SONS CONSTRUCTION, LTD. (15.00)
PRIMATE CONSTRUCTION, LP (0.51)
RK HALL, LLC (15.08)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.04)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.10)
DK CONTRACTING, LLC (0.29)
REINHOLD ELECTRIC, INC (2.69)
TRP CONSTRUCTION GROUP, LLC (0.77)
Contract #04213202
Totals36800373.9827609.0037867165.0599.4

CountyRANDALL
HighwayUS 87
FromRUSSELL LONG BLVD
To4 LANE DIVIDED
CSJ0067-01-087
Proj IDF 2024(460)
Work TypeOVERLAY
 
3.8359542615.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-21-24
Work Began00-00-00
Work Completed
Time Computed08-23-24
Contract Working Days167
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0067-01-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233012
Totals9542615.340.000.000.0

CountyPOTTER
HighwayIH 40
FromIH 40/HOPE RD BRIDGE
To.
CSJ0090-05-107
Proj IDBR 2024(779)
Work TypeBRIDGE REPLACEMENT
 
10246889.620.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243010
Totals10246889.620.000.000.0

CountyPOTTER
HighwayIH 40
FromIH 40/ADKISSON RD BRIDGE
To.
CSJ0090-05-108
Proj IDBR 2024(730)
Work TypeBRIDGE REPLACEMENT
 
9782900.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243011
Totals9782900.980.000.000.0

CountyPOTTER
HighwayIH 40
From0.715 MI WEST OF BI-40D
ToBI-40D
CSJ0090-05-111
Proj IDSTP 2023(598)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.774804518.25790811.9598.2
CountyPOTTER
HighwayIH 40
FromBI-40D
To0.690 MI EAST OF BI-40D
CSJ0275-01-230
Proj IDSTP 2023(598)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.092822012.75832586.3599.9
CountyPOTTER
HighwayIH 40
FromFM 1258
To0.747 MI EAST OF US 287 INTERCHANGE
CSJ0275-01-231
Proj IDSTP 2023(598)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.2771476439.651454002.9598.4
CountyPOTTER
HighwayIH 40
FromSL 335
ToFM 2590 (SONCY)
CSJ0275-01-241
Proj IDSTP 2023(598)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.0611018408.75971842.8595.4
Work Order07-19-23
Work Began09-14-23
Work Completed
Time Computed11-24-23
Contract Working Days107
Addl Days Granted0
Working Days Charged100
Percent Time Used93
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-111
BARRICADES UNLIMITED (0.00)
WILLIS ELECTRIC CO., LP (0.00)
FIBERTEX, LLC (0.00)
HJC FARMS, INC. (0.00)
Contract #06233012
Totals4121379.4079604.004049244.1098.2

CountyPOTTER
HighwayBI 40-D
FromON BI 40-D EB
ToAT BNSF RR
CSJ0090-06-044
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482915940.532045438.4175.7
CountyPOTTER
HighwayBI 40-D
FromON BI 40-D WB
ToAT BNSF RR
CSJ0090-06-045
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482291335.601937980.5584.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began05-03-21
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted13
Working Days Charged522
Percent Time Used138
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-044
PINNACLE GRINDING AND GROOVING LLC (0.20)
HUNTER DEMOLITION & WRECKING CORPORATION (3.49)
BARRICADES UNLIMITED (1.90)
FC TRAFFIC CONTROL, INC. (0.47)
L&H ELECTRICAL, LLC (1.54)
RK HALL, LLC (6.23)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.41)
HJC FARMS, INC. (1.85)
A BROTHERS MILLING, LLC (0.35)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.36)
TORO BRAVO CONSTRUCTION, LLC (0.32)
TORO BRAVO CONSTRUCTION, LLC (0.91)
AARON CONCRETE CONTRACTORS, L.P. (3.17)
PENHALL COMPANY (0.16)
TRP CONSTRUCTION GROUP, LLC (0.87)
Contract #01213007
Totals5207276.1359878.303983418.9679.6

CountyDEAF SMITH
HighwayUS 60
FromUS 385
ToTIERRA BLANCA CREEK BRIDGE
CSJ0168-05-039
Proj IDC 168-5-39
Work TypeREHABILITATION OF EXISTING ROAD
 
17171995.500.000.0
CountyDEAF SMITH
HighwayUS 60
FromDIVIDED 4 LANE
ToUS 385
CSJ0168-07-043
Proj IDC 168-7-43
Work TypeREHABILITATION OF EXISTING ROAD
 
2.47356684682.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days599
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-05-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243003
Totals73856677.900.000.000.0

page 1 | page 2 | page 3 | page 4