Monthly State Let Construction Report For Amarillo District As Of Nov 12, 2021 Page 1 Of 3

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE
HighwayUS 83
FromCR K SOUTH OF PERRYTON
ToWOLF CREEK
CSJ0030-02-052
Proj IDSTP 2019(603)
Work TypeOVERLAY
 
25.39613814377.452459705.7218.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began05-18-20
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged229
Percent Time Used170
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03193005
Totals13814377.45235428.082459705.7218.6

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromAT 15TH AVE
To.
CSJ0030-02-053
Proj IDSTP 2019(602)HES
Work Type2017 FEDERAL HSIP PROGRAM
 
2.1522152762.701693926.6778.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-19
Work Began09-29-20
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted0
Working Days Charged111
Percent Time Used60
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-053
CONCRETE CONNECTION (5.15)
FC TRAFFIC CONTROL, INC. (1.57)
LINEAR TRAFFIC MARKINGS LLC (1.67)
CONCRETE CONNECTION, LLC (5.15)
CIRCLE FOUR ENTERPRISES, LLC (1.15)
MEDELLIN HDD LLC (0.07)
Contract #03193227
Totals2152762.70634718.011693926.6778.6

CountyOCHILTREE
HighwayUS 83
FromAT SL 143 (PERRYTON)
To.
CSJ0030-02-054
Proj IDSTP 2B20(146)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200203492.560.000.0
CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-192
Proj IDSTP 2B20(146)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
770371.60185400.4224.0
Work Order09-08-20
Work Began00-00-00
Work Completed
Time Computed12-07-20
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-054
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203042
Totals973864.160.00185400.4219.0

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromAT WEST FORK HORSE CREEK (NORTH)
To.
CSJ0030-05-069
Proj IDBR 2020(634)
Work TypeBRIDGE REPLACEMENT
 
0.59216941869.8016802776.6796.2
Work Order04-28-20
Work Began00-00-00
Work Completed
Time Computed08-26-20
Contract Working Days253
Addl Days Granted0
Working Days Charged173
Percent Time Used68
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-069
BARRICADES UNLIMITED (0.21)
G & L REBAR (0.35)
J. H. ODEN CONTRACTING COMPANY (1.27)
PENHALL COMPANY (0.25)
S & S BRIDGE PAINTING, INC. (0.71)
TEXOP CONSTRUCTION (0.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.46)
G & L REBAR (0.22)
WAYNE BRYANT LOGISTICS, LLC (0.38)
J. LEE MILLIGAN, INC. (3.30)
HJC FARMS, INC. (2.02)
UHPC SOLUTIONS NORTH AMERICA LLC (3.12)
Contract #03203205
Totals16941869.80517072.7116802776.6796.2

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromUS 60
ToFM 277
CSJ0030-06-064
Proj IDSTP 2021(129)
Work TypeSEAL COAT
 
300.69114748006.6315668541.9299.9
Work Order01-14-21
Work Began00-00-00
Work Completed
Time Computed02-13-21
Contract Working Days93
Addl Days Granted0
Working Days Charged93
Percent Time Used100
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-064
CENTERLINE TECHNOLOGIES, LLC (6.37)
COX PAVING OF TEXAS, INC. (19.35)
FC TRAFFIC CONTROL, INC. (0.63)
INNOVATIVE ROADWAY SOLUTIONS, LLC (10.71)
RED SIXTEEN CONSTRUCTION, INC (0.42)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.29)
LINEAR TRAFFIC MARKINGS LLC (0.11)
Contract #11203022
Totals14748006.6392439.4215668541.9299.9

CountyDALLAM
HighwayUS 87
From0.6 MILES NW OF FM 1879
To0.5 MILES NE OF FM 1727
CSJ0040-03-064
Proj IDC 40-3-64
Work TypeOVERLAY
 
16.24417114341.9718288105.8899.9
Work Order06-17-19
Work Began04-28-20
Work Completed
Time Computed04-15-20
Contract Working Days150
Addl Days Granted0
Working Days Charged178
Percent Time Used118
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-064
BARRICADES UNLIMITED (2.01)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.00)
HJC FARMS, INC. (0.00)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
TEXOP CONSTRUCTION (0.00)
Contract #04193006
Totals17114341.970.0018288105.8899.9

CountyDALLAM
HighwayUS 87
FromAT BU 87-B (7TH STREET)
To.
CSJ0040-03-068
Proj IDF 2021(646)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.222354993.200.000.0
CountyHARTLEY
HighwayUS 87
FromAT 16TH STREET
To.
CSJ0041-01-048
Proj IDSTP 2021(647)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200248962.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06213032
Totals603955.810.000.000.0

CountyHARTLEY
HighwayUS 385
FromUS 87 IN HARTLEY
ToCHANNING
CSJ0041-02-016
Proj IDF 2021(441)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.9249656579.2259768.000.6
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed06-19-21
Contract Working Days327
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-02-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213207
Totals9656579.220.0059768.000.6

CountyPOTTER
HighwayUS 87
FromCANADIAN RIVER BRIDGE
To0.56 MILES SOUTH
CSJ0041-05-053
Proj IDF 2021(391)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5601149484.511165767.0699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-21
Work Began07-07-21
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged70
Percent Time Used97
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-05-053
ALAMO BROTHERS CONCRETE INC (9.50)
BARRICADES UNLIMITED (1.38)
FC TRAFFIC CONTROL, INC. (0.68)
HJC FARMS, INC. (5.14)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.66)
Contract #03213027
Totals1149484.51343370.111165767.0699.9

CountyPOTTER ETC
HighwayUS 87 ETC
FromAMARILLO CREEK
ToSL 335
CSJ0041-07-111
Proj IDF 2022(118)
Work TypeSEAL COAT
 
213.69814719115.650.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-111
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213002
Totals14719115.650.000.000.0

CountyDALLAM
HighwayUS 287
FromOKLAHOMA STATE LINE
ToSHERMAN COUNTY LINE
CSJ0066-01-021
Proj IDNH 2020(203)
Work TypeREHABILITATION OF EXISTING ROAD
 
12.4647973152.828672150.3799.9
CountySHERMAN
HighwayUS 287
From2 MILES NORTH OF PURNELL STREET
ToPURNELL STREET
CSJ0066-02-034
Proj IDHP 2020(515)
Work TypeWIDEN NON-FREEWAY
 
2.0004004876.834030546.9099.9
Work Order03-05-20
Work Began04-06-20
Work Completed
Time Computed04-06-20
Contract Working Days183
Addl Days Granted0
Working Days Charged185
Percent Time Used101
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-01-021
FC TRAFFIC CONTROL, INC. (0.40)
HJC FARMS, INC. (1.15)
DK CONTRACTING, LLC (0.52)
BARRICADES UNLIMITED (1.17)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.26)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.11)
DUSTROL, INC. (2.44)
ALAMO BROTHERS CONCRETE INC (2.77)
Contract #11193004
Totals11978029.6556719.1712702697.2799.9

CountyMOORE
HighwayUS 287
FromSOUTH OF FM 281
ToDUMAS
CSJ0066-04-079
Proj IDF 2021(699)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
8.9064229617.380.000.0
Work Order08-25-21
Work Began00-00-00
Work Completed
Time Computed09-24-21
Contract Working Days137
Addl Days Granted0
Working Days Charged4
Percent Time Used2
Contractor(s)
VECTOR UTILITIES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0066-04-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213217
Totals4229617.380.000.000.0

CountyMOORE
HighwayUS 87
FromSOUTH CITY LIMITS OF DUMAS
ToSH 152
CSJ0066-05-065
Proj IDNH 2013(606)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.56336473058.284647488.6912.7
CountyMOORE
HighwayUS 87
FromAT SH 152
To.
CSJ0066-05-070
Proj IDSTP 2021(393)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.100327315.700.000.0
Work Order05-20-21
Work Began07-06-21
Work Completed
Time Computed06-19-21
Contract Working Days838
Addl Days Granted0
Working Days Charged87
Percent Time Used10
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0066-05-065
BARRICADES UNLIMITED (1.97)
JR WEST TEXAS CONCRETE LLC (8.60)
L&H ELECTRICAL, LLC (2.71)
DUSTROL, INC. (0.89)
L A FULLER & SONS CONSTRUCTION, LTD. (15.00)
PRIMATE CONSTRUCTION, LP (0.51)
Contract #04213202
Totals36800373.981695443.794647488.6912.6

CountyOLDHAM
HighwayIH 40 ETC
From10 MILES EAST OF NEW MEXICO STATE LINE
To0.23 MILES WEST OF FM 2858
CSJ0090-02-053
Proj IDSTP 2020(777)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
76.6523945747.003626469.0292.4
Work Order06-09-20
Work Began08-04-20
Work Completed
Time Computed08-03-20
Contract Working Days233
Addl Days Granted0
Working Days Charged230
Percent Time Used98
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0090-02-053
ALAMO BROTHERS CONCRETE INC (0.00)
STRIPE-A-ZONE, INC. (19.38)
FC TRAFFIC CONTROL, INC. (0.00)
Contract #04203014
Totals3945747.004946.803626469.0292.4

CountyPOTTER ETC
HighwaySL 279 ETC
FromAT WESTERN STREET
To.
CSJ0090-05-095
Proj IDSTP 2018(815)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
0.8161568719.481371492.0999.9
Work Order06-14-18
Work Began00-00-00
Work Completed
Time Computed07-14-18
Contract Working Days173
Addl Days Granted3
Working Days Charged480
Percent Time Used272
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-095
ARTEX ELECTRIC, INC. (26.27)
CONCRETE CONNECTION (3.84)
BARRICADES UNLIMITED (2.13)
MEDELLIN HDD LLC (0.08)
Contract #05183244
Totals1568719.4815700.001371492.0999.9

CountyPOTTER
HighwayBI 40-D
FromON BI 40-D EB
ToAT BNSF RR
CSJ0090-06-044
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482915940.53931593.2731.9
CountyPOTTER
HighwayBI 40-D
FromON BI 40-D WB
ToAT BNSF RR
CSJ0090-06-045
Proj IDBR 2021(281)
Work TypeBRIDGE REPLACEMENT
 
0.2482291335.60152081.376.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days364
Addl Days Granted0
Working Days Charged108
Percent Time Used29
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-044
PINNACLE GRINDING AND GROOVING LLC (0.20)
HUNTER DEMOLITION & WRECKING CORPORATION (3.49)
BARRICADES UNLIMITED (1.90)
FC TRAFFIC CONTROL, INC. (0.47)
L&H ELECTRICAL, LLC (1.54)
RK HALL, LLC (6.23)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.41)
HJC FARMS, INC. (1.85)
A BROTHERS MILLING, LLC (0.35)
Contract #01213007
Totals5207276.13224281.631083674.6420.8

CountyOLDHAM
HighwayBI 40--
FromEAST OF VEGA AT IH 40
To.
CSJ0090-09-006
Proj IDBR 2019(915)
Work TypeBRIDGE MAINTENANCE
 
0.3695412115.005061182.5093.3
CountyCARSON
HighwayFM 2161
FromAT IH 40
To.
CSJ1884-02-011
Proj IDBR 2019(916)
Work TypeBRIDGE MAINTENANCE
 
0.2581792277.001924732.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-02-19
Work Began09-16-19
Work Completed
Time Computed00-00-00
Contract Working Days258
Addl Days Granted30
Working Days Charged331
Percent Time Used114
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-09-006
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.32)
ALAMO BROTHERS CONCRETE INC (10.86)
BARRICADES UNLIMITED (2.43)
MCL CONTRACTING, LLC (0.51)
BLACKTOP INDUSTRIES LLC (1.64)
PENHALL COMPANY (0.16)
L A FULLER & SONS CONSTRUCTION, LTD. (16.07)
Contract #05193229
Totals7204392.00273198.836985914.5096.8

CountyDEAF SMITH
HighwayUS 60
FromTIERRA BLANCA CREEK
ToCASTRO COUNTY LINE
CSJ0168-05-041
Proj IDF 2022(056)
Work TypeOVERLAY
 
5.4645275866.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-05-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213203
Totals5275866.950.000.000.0

CountyDEAF SMITH
HighwayUS 60
From.9 MILES SW OF FM 2943
To.5 MILES NE OF FM 2943
CSJ0168-07-047
Proj IDF 2021(869)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1.7403379277.550.000.0
CountyDEAF SMITH
HighwayUS 60
FromAT FM 2943
To.
CSJ0168-07-048
Proj IDSTP 2021(870)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200310437.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213239
Totals3689714.800.000.000.0

CountyDEAF SMITH
HighwayUS 60
FromEAST OF FM 2943 SOUTH
ToRANDALL COUNTY LINE
CSJ0168-07-049
Proj IDF 2021(708)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5647434.2068020.751.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days181
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213016
Totals5647434.2068020.7568020.751.2

page 1 | page 2 | page 3