Monthly State Let Construction Report For Amarillo District As Of Oct 16, 2017 Page 1 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromOKLAHOMA STATE LINE
ToSH 15
CSJ0030-01-033
Proj IDSTP 2018(160)HESG
Work TypeSAFETY IMPROVEMENT PROGRAM (HSIP)
 
159.784810357.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0030-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173005
Totals810357.030.000.000.0

CountyOCHILTREE
HighwayUS 83
FromPEER STREET
ToCOUNTY ROAD K
CSJ0030-02-044
Proj IDSTP 1602(301)
Work TypeREHAB EXISTING ROADWAY
 
1.5132999163.70872645.5529.0
Work Order03-16-17
Work Began05-23-17
Work Completed
Time Computed04-17-17
Contract Working Days131
Addl Days Granted0
Working Days Charged41
Percent Time Used31
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-044
ALAMO BROTHERS CONCRETE, INC. (9.73)
BARRICADES UNLIMITED (2.71)
WOLFE CONSTRUCTION GROUP, INC. (0.15)
Contract #02173010
Totals2999163.70171005.74872645.5529.0

CountyOCHILTREE ETC
HighwayUS 83 ETC
FromSH 15
ToPEER STREET (PERRYTON)
CSJ0030-02-047
Proj IDNH 2017(260)
Work TypeSEALCOAT
 
313.26012438153.539277080.3774.5
Work Order12-20-16
Work Began00-00-00
Work Completed
Time Computed04-15-17
Contract Working Days76
Addl Days Granted0
Working Days Charged72
Percent Time Used94
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-047
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. (14.02)
FLAT LINE, INC. (2.47)
Contract #11163003
Totals12438153.53410623.279277080.3774.5

CountyHEMPHILL ETC
HighwayUS 83 ETC
FromAT SH 33
To.
CSJ0030-06-059
Proj IDSTP 2017(858)HES
Work TypeINSTALL FLASHING BEACON
 
3.781563243.50330028.3258.5
Work Order04-24-17
Work Began00-00-00
Work Completed
Time Computed05-24-17
Contract Working Days54
Addl Days Granted7
Working Days Charged14
Percent Time Used22
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-06-059
BEAN ELECTRICAL, INC. (68.91)
Contract #03173221
Totals563243.50330028.32330028.3258.5

CountyDALLAM ETC
HighwayUS 87 ETC
FromUS 54
ToLINCOLN STREET
CSJ0040-03-059
Proj IDNH 1502(569)
Work TypeUPGRADE TO STANDARDS NON-FREEWAY
 
4.35626321210.0025085896.5095.2
Work Order02-02-16
Work Began03-14-16
Work Completed
Time Computed03-03-16
Contract Working Days443
Addl Days Granted7
Working Days Charged309
Percent Time Used68
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0040-03-059
BARRICADES UNLIMITED (0.31)
A BROTHERS MILLING, LLC (1.02)
TLJ LINING CO. (0.09)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.38)
MCL CONTRACTING, LLC (0.02)
G AND G OPERATORS, LTD. (4.59)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32)
J. LEE MILLIGAN, INC. (16.97)
PRIMATE CONSTRUCTION, INC. (0.71)
BREDA COMPANY, INC. (0.74)
KLP COMMERCIAL, LLC (4.23)
FARR FOUNDATION, INC. (0.83)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.48)
SIGNAL SERVICES GROUP INC. (2.60)
ACTION CONSTRUCTORS (5.23)
SLATON BROTHERS, INC. (1.98)
FLUHMAN BUILDERS, LLC (0.00)
URBAN INFRACONSTRUCTION, LLC. (0.22)
Contract #08153216
Totals26321210.00872859.3125085896.5095.2

CountyPOTTER
HighwayIH 40
FromWEST BOUND BRIDGE AT RM 2381
To.
CSJ0090-05-099
Proj IDBR 1702(431)
Work TypeBRIDGE REPLACEMENT
 
0.3571333510.551133032.2284.9
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days60
Addl Days Granted0
Working Days Charged33
Percent Time Used55
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0090-05-099
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.63)
BARRICADES UNLIMITED (3.00)
HJC FARMS, INC. (7.52)
HUNTER DEMOLITION & WRECKING CORPORATION (4.97)
PENHALL COMPANY (0.27)
ALAMO BROTHERS CONCRETE, INC. (0.99)
Contract #06173018
Totals1333510.55634436.341133032.2284.9

CountyPOTTER
HighwayBI 40-D
FromVARIOUS LOCATIONS ON BI 40-D
To.
CSJ0090-06-039
Proj IDSTP 1602(188)
Work TypeREHAB TRAFFIC SIGNALS
 
0.293977598.790.000.0
CountyPOTTER
HighwayIH 40
FromON IH 40 AT BELL STREET
To.
CSJ0275-01-187
Proj IDBR 2017(934)
Work TypeBRIDGE MAINT PROGRAM (BMIP)
 
0.1004718575.312823546.8059.8
CountyPOTTER
HighwayIH 40
FromWEST OF BELL STREET
ToEAST OF BELL STREET
CSJ0275-01-189
Proj IDNH 2017(935)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.3001776055.66480034.4627.0
Work Order05-22-17
Work Began00-00-00
Work Completed
Time Computed06-21-17
Contract Working Days212
Addl Days Granted0
Working Days Charged67
Percent Time Used31
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0090-06-039
QLVS, INC. DBA PHASE 3 ELECTRIC (4.01)
ALAMO BROTHERS CONCRETE, INC. (3.30)
HOLMES CONSTRUCTION CO., L.P. (11.28)
BARRICADES UNLIMITED (1.39)
DIIBS SPECIALISTS (0.46)
FARR FOUNDATION, INC. (1.06)
PENHALL COMPANY (0.08)
SCOTT DERR PAINTING CO, LLC (0.05)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.14)
WOLFE CONSTRUCTION GROUP, INC. (0.00)
BOWMAN ENGINEERING & CONSULTING, INC (0.27)
MCL CONTRACTING, LLC (0.29)
Contract #04173223
Totals7472229.761474106.923303581.2644.2

CountyRANDALL
HighwayIH 27
FromSUNDOWN LANE
ToBELL STREET
CSJ0168-09-161
Proj IDDMO 2012(757)
Work TypeREHAB EXISTING ROADWAY
 
2.17215278484.990.000.0
CountyRANDALL
HighwaySL 335
FromIH 27
ToBELL STREET
CSJ2635-02-029
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
0.4265927968.280.000.0
CountyRANDALL
HighwaySL 335
FromWEST OF COULTER
ToIH 27
CSJ2635-03-018
Proj IDNH 1702(473)
Work TypeCONVERT NONFREEWAY TO FREEWAY
 
1.07621169039.13353816.251.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days720
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-161
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07173201
Totals42375492.40353816.25353816.250.8

CountyRANDALL
HighwayIH 27
FromPOTTER COUNTY LINE
ToSOUTH OF 34TH AVENUE
CSJ0168-09-170
Proj IDNH 1702(133)
Work TypeMISCELLANOUS CONSTRUCTION
 
0.4033410133.780.000.0
CountyPOTTER
HighwayIH 27
FromON IH 27 SBL AT 26TH AVE
To.
CSJ0168-10-073
Proj IDBR 1702(132)
Work TypeBRIDGE MAINT PROGRAM (BMIP)
 
0.0763180524.8855860.001.7
CountyPOTTER
HighwayIH 27
FromNORTH OF 26TH AVENUE
ToRANDALL COUNTY LINE
CSJ0168-10-074
Proj IDNH 1702(133)
Work TypeMISCELLANOUS CONSTRUCTION
 
0.5121958921.590.000.0
CountyPOTTER
HighwayIH 40
FromGEORGIA STREET
ToCROCKETT STREET
CSJ0275-01-194
Proj IDNH 1702(133)
Work TypeMISCELLANEOUS CONSTRUCTION
 
0.4681335451.650.000.0
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed07-14-17
Contract Working Days201
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-170
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.53)
HJC FARMS, INC. (2.29)
FARR FOUNDATION, INC. (2.85)
WOLFE CONSTRUCTION GROUP, INC. (0.11)
SCR CIVIL CONSTRUCTION, LLC (3.90)
BARRICADES UNLIMITED (1.62)
S & S BRIDGE PAINTING, INC. (5.99)
QLVS, INC. DBA PHASE 3 ELECTRIC (2.20)
Contract #05173229
Totals9885031.9055860.0055860.000.5

CountyPOTTER
HighwayUS 60
FromON BUCHANAN FROM 11TH TO 6TH
ToON 6TH FROM FILLMORE TO PIERCE
CSJ0168-10-069
Proj IDSTP 2014(103)TE
Work TypeTRANSPORTION ENHANCEMENT
 
0.3632147565.302172131.4599.9
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed09-04-16
Contract Working Days95
Addl Days Granted0
Working Days Charged95
Percent Time Used100
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-10-069
QLVS, INC. DBA PHASE 3 ELECTRIC (9.34)
PARK MINNESOTA CONSTRUCTION COMPANY (9.63)
BARRICADES UNLIMITED (1.23)
GREEN PLAINS DESIGN (15.70)
SPEEDY PAVING (5.18)
Contract #05163222
Totals2147565.300.002172131.4599.9

CountyCARSON
HighwayUS 60
From0.71 MI W OF SH 207
To3.86 MI EAST OF PANHANDLE CL
CSJ0169-04-036
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
5.8385719206.160.000.0
CountyCARSON
HighwayUS 60
From3.86 MI EAST OF PAHANDLE CL
ToCR S EAST OF PANHANDLE
CSJ0169-05-043
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
0.787763361.820.000.0
CountyGRAY
HighwayUS 60
FromFM 750 WEST OF PAMPA
ToSH 70
CSJ0169-06-039
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
1.388747149.820.000.0
CountyGRAY
HighwayUS 60
FromSH 70
ToSH 152
CSJ0169-07-052
Proj IDNH 2013(611)
Work TypeREHAB EXISTING ROADWAY
 
7.5113828249.630.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days155
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-04-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173201
Totals11057967.430.000.000.0

CountyDEAF SMITH
HighwayUS 385
From.8 MILE SOUTH OF FM 1062
To1 MILE SOUTH OF OLDHAM COUNTY LINE
CSJ0226-04-025
Proj IDSTP 2016(680)
Work TypeRESTORATION
 
22.9088318208.268977692.6899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-16
Work Began00-00-00
Work Completed
Time Computed03-08-16
Contract Working Days77
Addl Days Granted0
Working Days Charged102
Percent Time Used132
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0226-04-025
BARRICADES UNLIMITED (0.99)
DUSTROL, INC. (1.14)
HJC FARMS, INC. (0.72)
DIAMOND SURFACE, INC. (0.25)
HARDY TREES, INC. (0.43)
Contract #02163229
Totals8318208.260.008977692.6899.9

CountyPOTTER
HighwayIH 40
FromSONCY
ToIH 27 INTERCHANGE
CSJ0275-01-163
Proj IDNH 2017(367)
Work TypeOVERLAY
 
5.2426982390.1043176.000.6
Work Order03-16-17
Work Began00-00-00
Work Completed
Time Computed04-15-17
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-163
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173206
Totals6982390.100.0043176.000.6

CountyPOTTER ETC
HighwayIH 40 ETC
FromHELIUM ROAD
ToEAST OF SL 335
CSJ0275-01-166
Proj IDNH 1502(372)
Work TypeRELOCATE ENTRANCE AND EXIT RAMPS
 
5.17926403959.2522830365.7985.5
Work Order10-06-15
Work Began01-25-16
Work Completed
Time Computed11-02-15
Contract Working Days560
Addl Days Granted12
Working Days Charged380
Percent Time Used66
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-166
ALAMO BROTHERS CONCRETE (4.85)
DUSTIN ALLEN, INC. (0.52)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.47)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.23)
WILLIS ELECTRIC CO., LP (10.58)
MCL CONTRACTING, LLC (0.16)
MICA CORPORATION (3.01)
L. A. FULLER & SONS CONSTRUCTION, LTD. (19.71)
SCOTT DERR PAINTING CO, LLC (0.16)
BREDA COMPANY, INC. (2.66)
BARRICADES UNLIMITED (0.95)
TRUMBLE CRANE & RIGGING (0.23)
A BROTHERS MILLING, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INC. (0.04)
TRI-STATE OILFIELD SERVICES, INC. (0.02)
JOSH FRANKLIN DRILLING, LLC (0.04)
OSCAR ORDUNO, INC. (1.84)
MCL CONTRACTING, LLC (0.01)
ALAMO BROTHERS CONCRETE (0.20)
SLATON BROTHERS, INC. (3.58)
PENHALL COMPANY (0.06)
WEBBER BARRIER SERVICES, LLC. (1.30)
Contract #07153253
Totals26403959.25650169.9822830365.7985.5

CountyPOTTER
HighwayIH 40
FromAT SL335 (LAKESIDE)
To.
CSJ0275-01-168
Proj IDNH 1502(349)
Work TypeCONSTRUCT TURNAROUNDS
 
0.3402519584.252621634.7999.9
CountyRANDALL
HighwaySL 335
From0.13 MILES EAST OF GEORGIA ST.
To0.26 MILES WEST OF FM 1541
CSJ2635-02-028
Proj IDSTP 2013(605)
Work TypeCONVERT NON-FREEWAY TO FREEWAY
 
0.80817821897.2017508790.4297.8
Work Order07-31-15
Work Began08-10-15
Work Completed
Time Computed08-10-15
Contract Working Days460
Addl Days Granted0
Working Days Charged468
Percent Time Used101
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-168
TRUMBLE CRANE & RIGGING (0.21)
DUSTIN ALLEN, INC. (1.07)
L. A. FULLER & SONS CONSTRUCTION, LTD. (22.92)
WILLIS ELECTRIC CO., LP (1.80)
OSCAR ORDUNO, INC. (3.65)
BARRICADES UNLIMITED (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67)
INDUS CONSTRUCTION, L.P. (1.34)
MCL CONTRACTING, LLC (0.13)
BREDA COMPANY, INC. (3.57)
ALAMO BROTHERS CONCRETE (0.42)
CINTEREX US, INC. (1.46)
WOLFE CONSTRUCTION GROUP, INC. (0.07)
A BROTHERS MILLING, LLC (0.64)
PENHALL COMPANY (0.09)
LLOYD D. NABORS DEMOLITION LLC (0.62)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
J. LEE MILLIGAN, INC. (0.55)
DISCOUNT FENCE COMPANY (0.10)
WEBBER BARRIER SERVICES, LLC. (1.04)
BILL AYRES LAWN & TREE SERVICE (0.12)
Contract #04153057
Totals20341481.4595966.3520130425.2198.6

CountyPOTTER
HighwayIH 40
From0.15 MILES WEST OF WASHINGTON ST
ToNELSON STREET
CSJ0275-01-177
Proj IDNH 1602(189)
Work TypeREHAB EXISTING ROADWAY
 
2.97736259776.7012484625.6234.4
Work Order09-26-16
Work Began11-01-16
Work Completed
Time Computed10-31-16
Contract Working Days332
Addl Days Granted49
Working Days Charged181
Percent Time Used47
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-177
BARRICADES UNLIMITED (1.47)
TRUMBLE CRANE & RIGGING (0.15)
HOWELL SAND CO. (1.54)
A BROTHERS MILLING, LLC (0.52)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.33)
BOWMAN ENGINEERING & CONSULTING, INC (2.70)
ER HAWKINS, LLC (1.81)
UNDER CONSTRUCTION INC. (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (12.18)
W. W. FOUNDATION DRILLING, LTD. (1.81)
HJC FARMS, INC. (2.16)
WILLIS ELECTRIC CO., LP (3.73)
OSCAR ORDUNO, INC. (1.49)
SOUTH TEXAS PAINTING COMPANY (0.59)
MICA CORPORATION (0.72)
LMN TRANSPORT (0.15)
ANTIGO CONSTRUCTION, INC. (0.04)
HOWELL SAND CO. (0.02)
COLTON GRADING & EXCAVATION (0.16)
PANHANDLE STEEL ERECTORS (0.30)
Contract #06163003
Totals36259776.70544930.9312484625.6234.4

CountyHANSFORD
HighwaySH 15
FromSH 136 IN GURVER
ToSH 207 IN SPEARMAN
CSJ0308-02-029
Proj IDSTP 1602(139)
Work TypeRESTORATION OF EXISTING ROADWAY
 
19.9009135715.422093971.6422.9
Work Order07-28-16
Work Began00-00-00
Work Completed
Time Computed08-26-16
Contract Working Days210
Addl Days Granted20
Working Days Charged99
Percent Time Used43
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
H & F TRUCKING (22.50)
WOLFE CONSTRUCTION GROUP, INC. (0.08)
DUSTROL, INC. (0.37)
BARRICADES UNLIMITED (1.27)
HJC FARMS, INC. (0.00)
Contract #05163030
Totals9135715.42319328.962093971.6422.9

CountyLIPSCOMB
HighwaySH 15
FromFM 1455
ToOKLAHOMA STATE LINE
CSJ0355-01-048
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
12.3624980635.65653100.0013.1
CountyLIPSCOMB
HighwaySH 15
FromOCHILTREE COUNTY LINE
To1000' EAST OF COUNTY ROAD 4
CSJ0355-02-031
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
3.118986876.400.000.0
CountyLIPSCOMB
HighwaySH 23
FromFM 377
To11.05 MILES NORTH OF US 83
CSJ1337-01-023
Proj IDSTP 1602(191)
Work TypeOVERLAY
 
10.0632183107.752209890.8199.9
Work Order08-05-16
Work Began00-00-00
Work Completed
Time Computed09-04-16
Contract Working Days77
Addl Days Granted0
Working Days Charged48
Percent Time Used62
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
BARRICADES UNLIMITED (2.40)
Contract #06163023
Totals8150619.8015900.002862990.8135.1

CountyROBERTS
HighwaySH 70
FromNORTH CANADIAN RIVER BRIDGE
ToOCHILTREE COUNTY LINE
CSJ0490-04-037
Proj IDSTP 2014(579)
Work TypeREHABILITATE EXISTING ROADWAY
 
5.8485139086.585158771.6599.9
Work Order06-18-14
Work Began12-10-14
Work Completed
Time Computed09-02-14
Contract Working Days197
Addl Days Granted27
Working Days Charged340
Percent Time Used151
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99)
HJC FARMS, INC. (3.77)
HUDSON, INC. (0.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.84)
WEST TEXAS RUMBLE STRIP (0.08)
W.S. CONSTRUCTION COMPANY (5.84)
E. DIAZ TRUCKING (2.85)
Contract #04143003
Totals5139086.580.005158771.6599.9

CountyMOORE
HighwaySH 152
FromDUMAS CITY LIMITS
ToHUTCHINSON COUNTY LINE
CSJ0557-01-028
Proj IDSTP 2016(683)
Work TypeRESTORATION
 
47.26315561610.5316715159.6899.9
Work Order05-24-16
Work Began07-06-16
Work Completed
Time Computed06-23-16
Contract Working Days130
Addl Days Granted20
Working Days Charged123
Percent Time Used82
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84)
DUSTROL, INC. (2.04)
W.S. CONSTRUCTION COMPANY (1.58)
CF TRUCKING, LLC (1.46)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15)
HJC FARMS, INC. (0.21)
VANCE BROTHERS, INC. (5.72)
Contract #02163003
Totals15561610.533286830.7816715159.6899.9

page 1 | page 2