Monthly State Let Maintenance Report For Amarillo District As Of Oct 16, 2017 Page 1 Of 1

Last Update: Monday, October 16, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRAY
Highway0000000
From12139 E FREDERIC AVE (US 60)
ToPAMPA TX
CSJ4704-01-629
Proj IDCBC - 470401629
Work TypeRENOVATION AND REPAIR
 
0.001315000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-629
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164220
Totals315000.000.000.000.0

CountyPOTTER
Highway0000000
From5715 CANYON DRIVE
ToAMARILLO TX
CSJ4704-01-641
Proj IDCBC - 470401641
Work TypeRENOVATION OR REPAIR
 
0.001598750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUKE ELECTRIC CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-641
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164227
Totals598750.000.000.000.0

CountyDALLAM
Highway0000000
From121900 US HWY 87
ToDALHART TX
CSJ4704-01-735
Proj IDCBC - 470401735
Work TypeRENOVATION OR REPAIR
 
0.001375000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-735
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164221
Totals375000.000.000.000.0

CountyRANDALL
HighwayIH0027
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-54-001
Proj IDRMC - 626954001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001335091.24489342.1399.9
Work Order09-29-14
Work Began11-03-14
Work Completed
Time Computed09-15-14
Contract Working Days179
Addl Days Granted179
Working Days Charged79
Percent Time Used22
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6269-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144004
Totals335091.240.00489342.1399.9

CountyDALLAM
HighwayUS0087
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-56-001
Proj IDRMC - 626956001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001452668.80664848.7699.9
Work Order00-00-00
Work Began10-23-14
Work Completed
Time Computed09-15-14
Contract Working Days227
Addl Days Granted227
Working Days Charged39
Percent Time Used8
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144006
Totals452668.800.00664848.7699.9

CountyMOORE
HighwayUS0287
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-57-001
Proj IDRMC - 626957001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001303096.00430414.7099.9
Work Order00-00-00
Work Began10-31-14
Work Completed
Time Computed09-15-14
Contract Working Days166
Addl Days Granted166
Working Days Charged42
Percent Time Used12
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144014
Totals303096.000.00430414.7099.9

CountyHUTCHINSON
HighwaySH0207
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-58-001
Proj IDRMC - 626958001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001327186.00486441.1099.9
Work Order00-00-00
Work Began11-09-14
Work Completed
Time Computed09-15-14
Contract Working Days181
Addl Days Granted181
Working Days Charged43
Percent Time Used11
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05144015
Totals327186.000.00486441.1099.9

CountyHEMPHILL
HighwayUS0083
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-59-001
Proj IDRMC - 626959001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001488572.98726723.1399.9
Work Order00-00-00
Work Began12-16-14
Work Completed
Time Computed10-01-14
Contract Working Days219
Addl Days Granted234
Working Days Charged166
Percent Time Used36
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08144002
Totals488572.980.00726723.1399.9

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6269-60-001
Proj IDRMC - 626960001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001499681.60786984.0099.9
Work Order00-00-00
Work Began11-05-14
Work Completed
Time Computed09-15-14
Contract Working Days251
Addl Days Granted0
Working Days Charged196
Percent Time Used78
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07144003
Totals499681.600.00786984.0099.9

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6286-41-001
Proj IDRMC - 628641001
Work TypeMISC ROADWAY REPAIR & MAINTENANCE
 
0.0014182652.604152758.1599.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-11-15
Work Completed
Time Computed06-22-15
Contract Working Days720
Addl Days Granted0
Working Days Charged720
Percent Time Used100
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05154203
Totals4182652.600.004152758.1599.2

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6290-44-001
Proj IDRMC - 629044001
Work TypeMOWING HIGHWAY RIGHT OF WAY (URBAN)
 
0.001696827.28527204.8575.6
Work Order10-19-15
Work Began12-05-15
Work Completed
Time Computed11-01-15
Contract Working Days263
Addl Days Granted0
Working Days Charged69
Percent Time Used26
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154011
Totals696827.2831551.39527204.8575.6

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6296-09-001
Proj IDRMC - 629609001
Work TypeDISTRICT WIDE ON CALL STRIPING
 
0.001900061.131021637.8499.9
Work Order00-00-00
Work Began11-16-16
Work Completed
Time Computed02-08-16
Contract Working Days730
Addl Days Granted730
Working Days Charged343
Percent Time Used23
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12154003
Totals900061.130.001021637.8499.9

CountyCARSON
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6312-12-001
Proj IDBPM - 631212001
Work TypeMISC. BRIDGE REPAIRS
 
0.001430115.00378076.4387.9
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed05-15-17
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6312-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174201
Totals430115.0041387.68378076.4387.9

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6313-52-001
Proj IDRMC - 631352001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001950535.00665801.1770.0
Work Order00-00-00
Work Began06-12-17
Work Completed
Time Computed04-03-17
Contract Working Days730
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6313-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174201
Totals950535.000.00665801.1770.0

CountyPOTTER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6313-53-001
Proj IDRMC - 631353001
Work TypeMISC ROADWAY REPAIRS
 
0.0012347860.004675686.2099.9
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed06-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged124
Percent Time Used16
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174006
Totals2347860.000.004675686.2099.9

page 1