Monthly Local Let Maintenance Report For Atlanta District As Of Dec 07, 2021 Page 3 Of 5

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyUPSHUR
HighwayUS0271
FromVARIOUS ROADWAYS
ToGILMER MAINTENANCE
CSJ6374-79-001
Proj IDMMC - 637479001
Work TypeHOT MIX
 
0.010246087.50439174.8799.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211903
Totals246087.500.00439174.8799.9

CountyMARION
HighwayUS0059
FromVARIOUS ROADWAYS
ToJEFFERSON MAINTENANCE
CSJ6374-80-001
Proj IDMMC - 637480001
Work TypeHOT MIX
 
253700.00657517.0099.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211904
Totals253700.000.00657517.0099.9

CountyCASS
HighwaySH0155
FromVARIOUS ROADWAYS
ToLINDEN MAINTENANCE
CSJ6374-81-001
Proj IDMMC - 637481001
Work TypeHOT MIX
 
289800.00751182.0699.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged187
Percent Time Used51
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6374-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211905
Totals289800.0025181.10751182.0699.9

CountyHARRISON
HighwayIH0020
FromVARIOUS ROADWAYS
ToMARSHALL MAINTENANCE
CSJ6374-82-001
Proj IDMMC - 637482001
Work TypeHOT MIX
 
253700.00351635.3199.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
LONGVIEW ASPHALT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6374-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211906
Totals253700.000.00351635.3199.9

CountyTITUS
HighwayIH0030
FromVARIOUS ROADWAYS
ToMT. PLEASANT MAINTENANCE
CSJ6374-83-001
Proj IDMMC - 637483001
Work TypeHOT MIX
 
253140.00350350.4799.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6374-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211907
Totals253140.000.00350350.4799.9

CountyBOWIE
HighwayUS0082
FromVARIOUS ROADWAYS
ToNEW BOSTON MAINTENANCE
CSJ6374-84-001
Proj IDMMC - 637484001
Work TypeHOT MIX
 
286900.00817193.7099.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6374-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211908
Totals286900.0059062.50817193.7099.9

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToTEXARKANA MAINTENANCE
CSJ6374-85-001
Proj IDMMC - 637485001
Work TypeHOT MIX
 
0.010275300.00395203.5599.9
Work Order00-00-00
Work Began04-26-21
Work Completed
Time Computed04-26-21
Contract Working Days120
Addl Days Granted240
Working Days Charged219
Percent Time Used60
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6374-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02211909
Totals275300.001260.00395203.5599.9

CountyBOWIE
HighwayUS0059
From.
To.
CSJ6375-27-001
Proj IDMMC - 637527001
Work TypeEMULSION
 
0.010235500.00204313.1286.7
Work Order00-00-00
Work Began05-27-21
Work Completed
Time Computed05-27-21
Contract Working Days120
Addl Days Granted120
Working Days Charged188
Percent Time Used78
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6375-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03211901
Totals235500.005826.50204313.1286.7

CountyTITUS
HighwayUS0271
From.
To.
CSJ6375-28-001
Proj IDMMC - 637528001
Work TypeHOT-MIX COLD-LAID
 
0.01078187.50113213.1299.9
Work Order00-00-00
Work Began05-03-21
Work Completed
Time Computed05-03-21
Contract Working Days120
Addl Days Granted120
Working Days Charged212
Percent Time Used88
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03211902
Totals78187.5036271.67113213.1299.9

CountyHARRISON
HighwayUS0059
From.
To.
CSJ6376-04-001
Proj IDSUP - 637604001
Work TypePICNIC AREA MAINTENANCE
 
0.01074130.0059680.0080.5
Work Order01-27-21
Work Began02-01-21
Work Completed
Time Computed02-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-04-001
RUCON, INC. (100.00)
Contract #01211931
Totals74130.002880.0059680.0080.5

CountyUPSHUR
HighwayUS0271
From.
To.
CSJ6376-69-001
Proj IDSUP - 637669001
Work TypeGROUNDS MAINTENANCE
 
0.01012395.247067.4657.0
Work Order01-27-21
Work Began02-01-21
Work Completed
Time Computed02-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6376-69-001
RUCON, INC. (100.00)
Contract #01211932
Totals12395.24278.417067.4657.0

CountyHARRISON
HighwaySL0390
From.
To.
CSJ6377-07-001
Proj IDSUP - 637707001
Work TypeGROUNDS MAINTENANCE
 
0.01021697.1612814.0559.0
Work Order01-27-21
Work Began02-01-21
Work Completed
Time Computed02-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6377-07-001
RUCON, INC. (100.00)
Contract #01211933
Totals21697.161349.2712814.0559.0

CountyBOWIE
HighwayIH0030
FromIH0030/US0059
ToIH0030/US0059
CSJ6377-96-001
Proj IDRMC - 637796001
Work TypeLANDSCAPE MAINTENANCE
 
0.010104620.6432990.8831.5
Work Order00-00-00
Work Began06-16-21
Work Completed
Time Computed06-16-21
Contract Working Days358
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
KYVER CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6377-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04211901
Totals104620.644113.3632990.8831.5

CountyMORRIS
HighwayUS0259
From.
To.
CSJ6379-21-001
Proj IDSUP - 637921001
Work TypeGROUNDS MAINTENANCE
 
0.0107440.004030.0054.1
Work Order04-01-21
Work Began04-01-21
Work Completed
Time Computed04-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6379-21-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #03211931
Totals7440.00310.004030.0054.1

CountyMARION
HighwaySH0049
From.
To.
CSJ6379-65-001
Proj IDSUP - 637965001
Work TypeGROUNDS MAINTENANCE
 
0.01017026.807094.5041.6
Work Order05-28-21
Work Began06-01-21
Work Completed
Time Computed06-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged183
Percent Time Used50
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6379-65-001
RUCON, INC. (100.00)
Contract #05211934
Totals17026.80709.457094.5041.6

CountyCASS
HighwayFM0249
From.
To.
CSJ6380-28-001
Proj IDSUP - 638028001
Work TypeJANITORIAL MAINTENANCE
 
0.01087000.0045100.0051.8
Work Order03-31-21
Work Began04-01-21
Work Completed
Time Computed04-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged244
Percent Time Used66
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6380-28-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03211933
Totals87000.005300.0045100.0051.8

CountyTITUS
HighwayUS0271
From.
To.
CSJ6380-51-001
Proj IDSUP - 638051001
Work TypeJANITORIAL MAINTENANCE
 
0.01018700.006970.0037.2
Work Order04-29-21
Work Began05-01-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6380-51-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04211931
Totals18700.00650.006970.0037.2

CountyCASS
HighwaySH0008
From.
To.
CSJ6381-07-001
Proj IDSUP - 638107001
Work TypeJANITORIAL MAINTENANCE
 
0.01014890.004680.0031.4
Work Order04-29-21
Work Began05-01-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6381-07-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04211934
Totals14890.00585.004680.0031.4

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6381-08-001
Proj IDSUP - 638108001
Work TypeJANITORIAL MAINTENANCE
 
0.01038840.0011700.0030.1
Work Order04-29-21
Work Began05-01-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6381-08-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04211933
Totals38840.001560.0011700.0030.1

CountyBOWIE
HighwayIH0030
From.
To.
CSJ6381-33-001
Proj IDSUP - 638133001
Work TypeGROUNDS MAINTENANCE
 
0.01015201.008917.0058.6
Work Order04-29-21
Work Began05-01-21
Work Completed
Time Computed05-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6381-33-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04211932
Totals15201.000.008917.0058.6