Monthly Local Let Maintenance Report For Atlanta District As Of Aug 15, 2022 Page 4 Of 4

Last Update: Monday, August 15, 2022
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6396-62-001
Proj IDMMC - 639662001
Work TypeHOT-MIX COLD-LAID
 
0.01084250.000.000.0
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed07-01-22
Contract Working Days120
Addl Days Granted0
Working Days Charged31
Percent Time Used25
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6396-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03221902
Totals84250.000.000.000.0

CountyMORRIS
HighwayUS0259
From.
To.
CSJ6399-69-001
Proj IDSUP - 639969001
Work TypeGROUNDS MAINTENANCE
 
0.0107440.002170.0029.1
Work Order03-30-22
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6399-69-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #02221931
Totals7440.00310.002170.0029.1

CountyCASS
HighwayFM0249
From.
To.
CSJ6399-70-001
Proj IDSUP - 639970001
Work TypeJANITORIAL MAINTENANCE
 
0.01089666.0022002.0024.5
Work Order03-30-22
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6399-70-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #02221932
Totals89666.005500.5022002.0024.5

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6401-14-001
Proj IDSUP - 640114001
Work TypeJANITORIAL MAINTENANCE
 
0.01020120.004680.0023.2
Work Order04-25-22
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-14-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03221934
Totals20120.001560.004680.0023.2

CountyTITUS
HighwayUS0271
From.
To.
CSJ6401-16-001
Proj IDSUP - 640116001
Work TypeJANITORIAL MAINTENANCE
 
0.01010900.001950.0017.8
Work Order04-25-22
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-16-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03221933
Totals10900.00650.001950.0017.8

CountyCASS
HighwaySH0008
From.
To.
CSJ6401-18-001
Proj IDSUP - 640118001
Work TypeJANITORIAL MAINTENANCE
 
0.0108330.001845.0022.1
Work Order04-25-22
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-18-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.01)
Contract #03221931
Totals8330.00615.001845.0022.1

CountyBOWIE
HighwayIH0369
From.
To.
CSJ6401-20-001
Proj IDSUP - 640120001
Work TypeGROUNDS MAINTENANCE
 
0.01015201.003083.5020.2
Work Order04-25-22
Work Began05-01-22
Work Completed
Time Computed05-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6401-20-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #03221932
Totals15201.00550.003083.5020.2

CountyMARION
HighwaySH0049
From.
To.
CSJ6406-45-001
Proj IDSUP - 640645001
Work TypeGROUNDS MAINTENANCE
 
0.01035075.044384.3812.5
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-45-001
RUCON, INC. (100.00)
Contract #04221931
Totals35075.041461.464384.3812.5

CountyCASS
HighwaySH0008
From.
To.
CSJ6406-47-001
Proj IDSUP - 640647001
Work TypeGROUNDS MAINTENANCE
 
0.01016412.64683.864.1
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-47-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04221932
Totals16412.640.00683.864.1

CountyBOWIE
HighwaySH0008
From.
To.
CSJ6406-51-001
Proj IDSUP - 640651001
Work TypeGROUNDS MAINTENANCE
 
0.01026460.003858.7514.5
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged61
Percent Time Used8
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04221933
Totals26460.001102.503858.7514.5

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6406-53-001
Proj IDSUP - 640653001
Work TypeLITTER REMOVAL
 
0.010159221.3728255.6417.7
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6406-53-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #04221934
Totals159221.3716884.3228255.6417.7

CountyBOWIE
HighwayIH0030
FromIH0030/US0059
ToIH0030/US0059
CSJ6408-16-001
Proj IDRMC - 640816001
Work TypeLANDSCAPE MAINTENANCE
 
0.010115478.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days358
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
T&R LAWN SYSTEMS
SUBCONTRACTOR(S) FOR CCSJ: 6408-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06221901
Totals115478.800.000.000.0

CountyPANOLA
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6410-09-001
Proj IDRMC - 641009001
Work TypeTREE REMOVAL
 
0.010180264.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6410-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08221902
Totals180264.000.000.000.0

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6410-11-001
Proj IDRMC - 641011001
Work TypeTREE REMOVAL
 
0.010194969.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08221901
Totals194969.000.000.000.0

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6411-91-001
Proj IDSUP - 641191001
Work TypeLITTER REMOVAL
 
0.010119265.660.000.0
Work Order07-01-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6411-91-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #06221932
Totals119265.660.000.000.0

CountyUPSHUR
HighwayUS0271
From.
To.
CSJ6411-99-001
Proj IDSUP - 641199001
Work TypeJANITORIAL MAINTENANCE
 
0.01013400.04716.675.3
Work Order06-15-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-99-001
A LIFT FOR LIFE OUTREACH, INC. (64.17)
Contract #06221931
Totals13400.04716.67716.675.3

CountyBOWIE
HighwaySH0008
From.
To.
CSJ6414-13-001
Proj IDSUP - 641413001
Work TypeJANITORIAL MAINTENANCE
 
0.01013500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-15-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6414-13-001
A LIFT FOR LIFE OUTREACH, INC. (64.44)
Contract #07221931
Totals13500.000.000.000.0

CountyPANOLA
HighwayBU0059D
From.
To.
CSJ6414-19-001
Proj IDSUP - 641419001
Work TypeGROUNDS MAINTENANCE
 
0.01020027.640.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6414-19-001
RUCON, INC. (100.00)
Contract #07221932
Totals20027.640.000.000.0

CountyHARRISON
HighwaySL0390
From.
To.
CSJ6416-45-001
Proj IDSUP - 641645001
Work TypeJANITORIAL MAINTENANCE
 
0.01028520.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6416-45-001
A LIFT FOR LIFE OUTREACH, INC. (100.00)
Contract #07221933
Totals28520.000.000.000.0

page 1 | page 2 | page 3 | page 4