Monthly State Let Maintenance Report For Atlanta District As Of Sep 18, 2019 Page 1 Of 2

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyBOWIE
HighwayUS0082
FromDISTRICTWIDE
ToVARIOUS
CSJ6288-86-001
Proj IDRMC - 628886001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001671713.970.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6288-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194218
Totals671713.970.000.000.0

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.006490335.2199.9
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged731
Percent Time Used50
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.00269830.756490335.2199.9

CountyHARRISON
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6316-00-001
Proj IDRMC - 631600001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0014189000.001259992.2730.0
Work Order06-04-18
Work Began06-11-18
Work Completed
Time Computed06-11-18
Contract Working Days240
Addl Days Granted0
Working Days Charged214
Percent Time Used89
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184011
Totals4189000.000.001259992.2730.0

CountyBOWIE
HighwayUS0067
FromDISTRICTWIDE
ToVARIOUS
CSJ6322-28-001
Proj IDRMC - 632228001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001738087.47697871.49100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-23-18
Work Completed02-15-19
Time Computed04-02-18
Contract Working Days85
Addl Days Granted0
Working Days Charged118
Percent Time Used138
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6322-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174211
Totals738087.470.00697871.49100.0

CountyBOWIE
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTH ATL DIST
To.
CSJ6324-84-001
Proj IDRMC - 632484001
Work TypeCALLOUT MILL & INLAY (NORTH)
 
0.0014231200.001825605.6543.1
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged18
Percent Time Used12
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-84-001
STRIPING TECHNOLOGY, L.P. (0.43)
Contract #09184021
Totals4231200.000.001825605.6543.1

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATION IN SOUTH ATL DIST
To.
CSJ6324-85-001
Proj IDRMC - 632485001
Work TypeCALLOUT MILL & INLAY (SOUTH)
 
0.0013931850.001761235.9944.7
Work Order12-06-18
Work Began12-11-18
Work Completed
Time Computed12-11-18
Contract Working Days150
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-85-001
STRIPING TECHNOLOGY, L.P. (0.58)
Contract #09184218
Totals3931850.00426093.151761235.9944.7

CountyPANOLA
HighwayFM0031
FromVARIOUS ROADWAYS IN THE ATL DISTRICT
To.
CSJ6330-15-001
Proj IDRMC - 633015001
Work TypeCULVERT REPLACEMENT - DISTRICTWIDE
 
0.001472593.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days35
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194202
Totals472593.000.000.000.0

CountyTITUS
HighwayUS0067
FromVARIOUS LOCATIONS IN THE
ToATLANTA DISTRICT
CSJ6331-53-001
Proj IDBPM - 633153001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.001623721.00637467.3599.9
Work Order12-26-18
Work Began01-09-19
Work Completed
Time Computed01-02-19
Contract Working Days165
Addl Days Granted8
Working Days Charged109
Percent Time Used63
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6331-53-001
PANOLA SIGN & BARRICADE, INC. (2.11)
DUSTIN ALLEN, INC. (30.82)
J. H. ODEN CONTRACTING COMPANY (0.08)
Contract #11184001
Totals623721.000.00637467.3599.9

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6332-57-001
Proj IDRMC - 633257001
Work TypeCALLOUT PREFABRICATED PAVEMENT MARKINGS
 
0.001503830.00137086.5427.2
Work Order00-00-00
Work Began12-18-18
Work Completed
Time Computed11-01-18
Contract Working Days254
Addl Days Granted0
Working Days Charged192
Percent Time Used75
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6332-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184015
Totals503830.000.00137086.5427.2

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS -ATL DISTRICT
ToDISTRICT WIDE
CSJ6333-11-001
Proj IDRMC - 633311001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001899825.00437178.3948.5
Work Order00-00-00
Work Began12-19-18
Work Completed
Time Computed12-19-18
Contract Working Days254
Addl Days Granted0
Working Days Charged160
Percent Time Used62
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-11-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
Contract #09184013
Totals899825.0075469.14437178.3948.5

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-44-001
Proj IDRMC - 633344001
Work TypeCALLOUT PAVEMENT MARKINGS
 
0.0011281188.00481825.6437.6
Work Order00-00-00
Work Began10-18-18
Work Completed
Time Computed11-01-18
Contract Working Days254
Addl Days Granted0
Working Days Charged204
Percent Time Used80
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184010
Totals1281188.00140864.48481825.6437.6

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS LOCATIONS - ATLANTA DISTRICT
CSJ6333-91-001
Proj IDRMC - 633391001
Work TypeCALLOUT RAISED PAVEMENT MARKERS
 
0.001286695.0071755.6825.0
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed12-10-18
Contract Working Days254
Addl Days Granted0
Working Days Charged131
Percent Time Used51
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184213
Totals286695.000.0071755.6825.0

CountyBOWIE
HighwayUS0059
FromBOWIE AND CASS COUNTIES
To.
CSJ6334-35-001
Proj IDRMC - 633435001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR-N
 
0.001373546.00116702.0031.2
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged155
Percent Time Used50
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184002
Totals373546.0029760.00116702.0031.2

CountyHARRISON
HighwayUS0059
FromMARION, HARRISON & PANOLA COUNTIES
To.
CSJ6334-36-001
Proj IDRMC - 633436001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(S)
 
0.001412252.0076604.2018.5
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged171
Percent Time Used55
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184003
Totals412252.0012548.2076604.2018.5

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.0061841.5020.3
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged168
Percent Time Used54
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0015688.0061841.5020.3

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToBOWIE AND CASS COUNTIES
CSJ6334-43-001
Proj IDRMC - 633443001
Work TypeTREE AND STUMP REMOVAL (N)
 
0.001312170.00287199.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-19
Work Completed06-01-19
Time Computed02-01-19
Contract Working Days150
Addl Days Granted0
Working Days Charged60
Percent Time Used40
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184022
Totals312170.000.00287199.00100.0

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS IN
ToMARION, HARRISON, UPSHUR & PANOLA
CSJ6334-44-001
Proj IDRMC - 633444001
Work TypeTREE & STUMP REMOVAL (S)
 
0.001454500.00495514.99100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-02-19
Work Began01-14-19
Work Completed05-31-19
Time Computed01-14-19
Contract Working Days150
Addl Days Granted0
Working Days Charged84
Percent Time Used56
Contractor(s)
T.F.R. ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-44-001
LYELLCO, INC. (49.14)
Contract #10184216
Totals454500.000.00495514.99100.0

CountyUPSHUR
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToUPSHUR,CAMP,TITUS,CASS,MARION & MORRIS
CSJ6334-45-001
Proj IDRMC - 633445001
Work TypeTREE & STUMP REMOVAL (W)
 
0.001494994.00258188.0052.1
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged54
Percent Time Used36
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-45-001
HX FARMS, INC. (39.99)
Contract #10184217
Totals494994.000.00258188.0052.1

page 1 | page 2