Monthly State Let Maintenance Report For Atlanta District As Of Nov 12, 2021 Page 1 Of 2

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.0013522201.21100.0
Work Order00-00-00
Work Began09-01-17
Work Completed08-31-21
Time Computed09-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged1,460
Percent Time Used99
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.00338887.5013522201.21100.0

CountyBOWIE
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTH ATL DIST
To.
CSJ6324-84-001
Proj IDRMC - 632484001
Work TypeCALLOUT MILL & INLAY (NORTH)
 
0.0014231200.004178138.73100.0
Work Order00-00-00
Work Began02-04-19
Work Completed09-30-21
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged58
Percent Time Used38
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-84-001
STRIPING TECHNOLOGY, L.P. (0.43)
Contract #09184021
Totals4231200.000.004178138.73100.0

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATION IN SOUTH ATL DIST
To.
CSJ6324-85-001
Proj IDRMC - 632485001
Work TypeCALLOUT MILL & INLAY (SOUTH)
 
0.0013931850.007937050.9399.9
Work Order12-06-18
Work Began12-11-18
Work Completed
Time Computed12-11-18
Contract Working Days150
Addl Days Granted0
Working Days Charged61
Percent Time Used40
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-85-001
STRIPING TECHNOLOGY, L.P. (0.58)
Contract #09184218
Totals3931850.000.007937050.9399.9

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.00139005.70100.0
Work Order00-00-00
Work Began02-12-19
Work Completed06-30-20
Time Computed02-12-19
Contract Working Days306
Addl Days Granted123
Working Days Charged376
Percent Time Used87
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0017895.00139005.70100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE
ToATLANTA DISTRICT
CSJ6338-78-001
Proj IDBPM - 633878001
Work TypeCALLOUT BRIDGE PREVENTATIVE MAINTENANCE
 
0.0012098950.001644391.9878.3
Work Order00-00-00
Work Began02-06-20
Work Completed
Time Computed02-03-20
Contract Working Days200
Addl Days Granted0
Working Days Charged198
Percent Time Used99
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-78-001
PANOLA SIGN & BARRICADE, INC. (0.17)
STRIPING TECHNOLOGY, L.P. (0.55)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.14)
Contract #11194002
Totals2098950.005770.001644391.9878.3

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE ATL DISTRICT
ToDISTRICTWIDE
CSJ6349-19-001
Proj IDRMC - 634919001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.0011061430.00480039.5045.2
Work Order00-00-00
Work Began02-12-21
Work Completed
Time Computed02-02-21
Contract Working Days254
Addl Days Granted0
Working Days Charged186
Percent Time Used73
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6349-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204001
Totals1061430.00110377.30480039.5045.2

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN THE NORTH AREA
To.
CSJ6351-00-001
Proj IDRMC - 635100001
Work TypeTREE TRIMMING - NORTH
 
180.149334370.92203111.1360.7
Work Order00-00-00
Work Began12-18-20
Work Completed
Time Computed12-14-20
Contract Working Days182
Addl Days Granted0
Working Days Charged52
Percent Time Used28
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6351-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204001
Totals334370.925813.17203111.1360.7

CountyHARRISON
HighwayUS0080
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6351-01-001
Proj IDRMC - 635101001
Work TypeTREE TRIMMING
 
404011.990.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days161
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ROAD SOLUTIONS L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6351-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214002
Totals404011.990.000.000.0

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS IN DISTRICT 19
ToVARIOUS ROADWAYS IN DISTRICT 19
CSJ6356-67-001
Proj IDRMC - 635667001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0015399700.003378018.7462.5
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days300
Addl Days Granted0
Working Days Charged171
Percent Time Used57
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6356-67-001
GHB EQUIPMENT COMPANY, L.L.C. (1.24)
Contract #03204001
Totals5399700.00330707.503378018.7462.5

CountyBOWIE
HighwayUS0059
FromBOWIE & CASS COUNTIES
To.
CSJ6357-08-001
Proj IDRMC - 635708001
Work TypeCALLOUT MBGF REPAIR - NORTH
 
0.001702035.00263170.5037.4
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged338
Percent Time Used55
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204013
Totals702035.000.00263170.5037.4

CountyHARRISON
HighwayUS0059
FromHARRISON, PANOLA & MARION COUNTIES
To.
CSJ6357-09-001
Proj IDRMC - 635709001
Work TypeCALLOUT MBGF REPAIR - SOUTH
 
0.001852050.00628966.6073.8
Work Order06-26-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged339
Percent Time Used55
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6357-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204014
Totals852050.0023214.50628966.6073.8

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6357-10-001
Proj IDRMC - 635710001
Work TypeCALLOUT MBGF REPAIR - WEST
 
0.001713880.00520398.6072.8
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days613
Addl Days Granted0
Working Days Charged408
Percent Time Used66
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6357-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04204015
Totals713880.0039521.50520398.6072.8

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6362-04-001
Proj IDRMC - 636204001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0108486300.00405179.254.7
Work Order09-01-21
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days730
Addl Days Granted0
Working Days Charged30
Percent Time Used4
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6362-04-001
NIXON ENGINEERING (0.00)
Contract #07214001
Totals8486300.00405179.25405179.254.7

CountyBOWIE
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6363-87-001
Proj IDRMC - 636387001
Work TypePAVEMENT MARKINGS
 
0.010378145.86414741.8599.9
Work Order00-00-00
Work Began05-24-21
Work Completed
Time Computed05-24-21
Contract Working Days254
Addl Days Granted0
Working Days Charged95
Percent Time Used37
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6363-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03214001
Totals378145.860.00414741.8599.9

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6367-55-001
Proj IDRMC - 636755001
Work TypeCALLOUT PAVEMENT MARKINGS (VARIOUS)
 
0.001773200.00317242.3241.0
Work Order00-00-00
Work Began04-12-21
Work Completed
Time Computed02-01-21
Contract Working Days254
Addl Days Granted0
Working Days Charged188
Percent Time Used74
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6367-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204002
Totals773200.00160487.15317242.3241.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS ROADWAYS
CSJ6367-56-001
Proj IDRMC - 636756001
Work TypeCALLOUT PREFABRICATED PAVEMENT MARKINGS
 
0.001447950.00113024.8025.2
Work Order00-00-00
Work Began02-01-21
Work Completed
Time Computed02-01-21
Contract Working Days254
Addl Days Granted0
Working Days Charged187
Percent Time Used73
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6367-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204009
Totals447950.0028179.70113024.8025.2

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToBOWIE & CASS COUNTIES
CSJ6369-70-001
Proj IDRMC - 636970001
Work TypeTREE & STUMP REMOVAL (NORTH)
 
0.001296454.00301957.0099.9
Work Order00-00-00
Work Began02-25-21
Work Completed
Time Computed02-25-21
Contract Working Days150
Addl Days Granted100
Working Days Charged67
Percent Time Used26
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204010
Totals296454.000.00301957.0099.9

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS IN
ToHARRISON, MARION, PANOLA & UPSHUR
CSJ6369-71-001
Proj IDRMC - 636971001
Work TypeTREE & STUMP REMOVAL (S)
 
0.001445429.00374611.00100.0
Work Order00-00-00
Work Began01-26-21
Work Completed08-20-21
Time Computed01-11-21
Contract Working Days175
Addl Days Granted0
Working Days Charged78
Percent Time Used44
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6369-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11204011
Totals445429.000.00374611.00100.0

page 1 | page 2