Monthly State Let Maintenance Report For Atlanta District As Of Feb 14, 2020 Page 1 Of 2

Last Update: Friday, February 14, 2020
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCASS
Highway0000000
From701 EAST MAIN STREET ATLANTA, TX 75551
To701 EAST MAIN STREET ATLANTA, TX 75551
CSJ4704-01-645
Proj IDCBC - 470401645
Work TypeRENOVATION OR REPAIR
 
0.001379500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTEGRITY ELECTRICAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-645
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164219
Totals379500.000.000.000.0

CountyBOWIE
HighwayUS0082
FromDISTRICTWIDE
ToVARIOUS
CSJ6288-86-001
Proj IDRMC - 628886001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001671713.97371116.4055.2
Work Order00-00-00
Work Began10-22-19
Work Completed
Time Computed09-23-19
Contract Working Days39
Addl Days Granted0
Working Days Charged34
Percent Time Used87
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6288-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194218
Totals671713.97121523.46371116.4055.2

CountyCASS
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-98-001
Proj IDRMC - 631098001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0015646100.007817900.2199.9
Work Order00-00-00
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days730
Addl Days Granted731
Working Days Charged884
Percent Time Used60
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174013
Totals5646100.00273024.257817900.2199.9

CountyHARRISON
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6316-00-001
Proj IDRMC - 631600001
Work TypeCALLOUT CONCRETE PAVEMENT REPAIR
 
0.0014189000.001457526.4934.7
Work Order06-04-18
Work Began06-11-18
Work Completed
Time Computed06-11-18
Contract Working Days240
Addl Days Granted0
Working Days Charged231
Percent Time Used96
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184011
Totals4189000.00131748.631457526.4934.7

CountyBOWIE
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTH ATL DIST
To.
CSJ6324-84-001
Proj IDRMC - 632484001
Work TypeCALLOUT MILL & INLAY (NORTH)
 
0.0014231200.002865625.4067.7
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged41
Percent Time Used27
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-84-001
STRIPING TECHNOLOGY, L.P. (0.43)
Contract #09184021
Totals4231200.00570928.252865625.4067.7

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATION IN SOUTH ATL DIST
To.
CSJ6324-85-001
Proj IDRMC - 632485001
Work TypeCALLOUT MILL & INLAY (SOUTH)
 
0.0013931850.001761235.9944.7
Work Order12-06-18
Work Began12-11-18
Work Completed
Time Computed12-11-18
Contract Working Days150
Addl Days Granted0
Working Days Charged13
Percent Time Used8
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-85-001
STRIPING TECHNOLOGY, L.P. (0.58)
Contract #09184218
Totals3931850.000.001761235.9944.7

CountyPANOLA
HighwayFM0031
FromVARIOUS ROADWAYS IN THE ATL DISTRICT
To.
CSJ6330-15-001
Proj IDRMC - 633015001
Work TypeCULVERT REPLACEMENT - DISTRICTWIDE
 
0.001472593.00247153.4852.2
Work Order12-02-19
Work Began12-09-19
Work Completed
Time Computed12-09-19
Contract Working Days35
Addl Days Granted0
Working Days Charged18
Percent Time Used51
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194202
Totals472593.0080156.48247153.4852.2

CountyBOWIE
HighwayUS0059
FromVARIOUS
To.
CSJ6332-57-001
Proj IDRMC - 633257001
Work TypeCALLOUT PREFABRICATED PAVEMENT MARKINGS
 
0.001503830.00176287.7034.9
Work Order00-00-00
Work Began12-18-18
Work Completed
Time Computed11-01-18
Contract Working Days254
Addl Days Granted254
Working Days Charged292
Percent Time Used57
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6332-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184015
Totals503830.000.00176287.7034.9

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS -ATL DISTRICT
ToDISTRICT WIDE
CSJ6333-11-001
Proj IDRMC - 633311001
Work TypeINSTALLATION OF TRAFFIC SIGNALS
 
0.001899825.00662994.2273.6
Work Order00-00-00
Work Began12-19-18
Work Completed
Time Computed12-19-18
Contract Working Days254
Addl Days Granted254
Working Days Charged257
Percent Time Used50
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-11-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22)
CATOCON, INC. (2.33)
Contract #09184013
Totals899825.0056956.90662994.2273.6

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-44-001
Proj IDRMC - 633344001
Work TypeCALLOUT PAVEMENT MARKINGS
 
0.0011281188.00715032.6155.8
Work Order00-00-00
Work Began10-18-18
Work Completed
Time Computed11-01-18
Contract Working Days254
Addl Days Granted254
Working Days Charged305
Percent Time Used60
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184010
Totals1281188.000.00715032.6155.8

CountyHARRISON
HighwayUS0080
FromDISTRICTWIDE
ToVARIOUS
CSJ6333-67-001
Proj IDRMC - 633367001
Work TypeINSTALLATION OF PAVEMENT MARKINGS
 
0.001612674.74552241.36100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-21-19
Work Completed08-09-19
Time Computed11-01-18
Contract Working Days43
Addl Days Granted0
Working Days Charged65
Percent Time Used151
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184011
Totals612674.740.00552241.36100.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToVARIOUS LOCATIONS - ATLANTA DISTRICT
CSJ6333-91-001
Proj IDRMC - 633391001
Work TypeCALLOUT RAISED PAVEMENT MARKERS
 
0.001286695.00210128.8173.2
Work Order00-00-00
Work Began02-04-19
Work Completed
Time Computed12-10-18
Contract Working Days254
Addl Days Granted254
Working Days Charged234
Percent Time Used46
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09184213
Totals286695.000.00210128.8173.2

CountyBOWIE
HighwayUS0059
FromBOWIE AND CASS COUNTIES
To.
CSJ6334-35-001
Proj IDRMC - 633435001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR-N
 
0.001373546.00239731.0064.1
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged257
Percent Time Used83
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184002
Totals373546.0027189.00239731.0064.1

CountyHARRISON
HighwayUS0059
FromMARION, HARRISON & PANOLA COUNTIES
To.
CSJ6334-36-001
Proj IDRMC - 633436001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(S)
 
0.001412252.00229612.9055.6
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged294
Percent Time Used96
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184003
Totals412252.0026609.50229612.9055.6

CountyTITUS
HighwayUS0271
FromUPSHUR, CAMP, TITUS & MORRIS COUNTIES
To.
CSJ6334-37-001
Proj IDRMC - 633437001
Work TypeCALLOUT METAL BEAM GUARD FENCE REPAIR(W)
 
0.001304044.00116780.7038.4
Work Order00-00-00
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days306
Addl Days Granted0
Working Days Charged299
Percent Time Used97
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184004
Totals304044.0013525.00116780.7038.4

CountyUPSHUR
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToUPSHUR,CAMP,TITUS,CASS,MARION & MORRIS
CSJ6334-45-001
Proj IDRMC - 633445001
Work TypeTREE & STUMP REMOVAL (W)
 
0.001494994.00494982.00100.0
Work Order00-00-00
Work Began02-04-19
Work Completed01-04-20
Time Computed02-04-19
Contract Working Days150
Addl Days Granted0
Working Days Charged116
Percent Time Used77
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-45-001
HX FARMS, INC. (39.99)
Contract #10184217
Totals494994.0019987.00494982.00100.0

CountyBOWIE
HighwayUS0059
FromVARIOUS LOCATIONS IN THE
ToATLANTA DISTRICT
CSJ6338-78-001
Proj IDBPM - 633878001
Work TypeCALLOUT BRIDGE PREVENTATIVE MAINTENANCE
 
0.0012098950.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11194002
Totals2098950.000.000.000.0

CountyBOWIE
HighwayUS0059
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6339-46-001
Proj IDRMC - 633946001
Work TypeGUIDE & CALL-OUT SIGN INSTALLATION
 
0.001576575.00354701.2561.5
Work Order00-00-00
Work Began05-06-19
Work Completed
Time Computed04-01-19
Contract Working Days254
Addl Days Granted254
Working Days Charged185
Percent Time Used36
Contractor(s)
CREATIVE DESIGN CONCEPTS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6339-46-001
TIME STRIPING, INC. (6.06)
Contract #12184202
Totals576575.0018863.00354701.2561.5

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToBOWIE & CASS COUNTIES
CSJ6348-25-001
Proj IDRMC - 634825001
Work TypeTREE & STUMP REMOVAL (N)
 
0.001316004.0059948.0018.9
Work Order00-00-00
Work Began12-02-19
Work Completed
Time Computed12-02-19
Contract Working Days150
Addl Days Granted0
Working Days Charged23
Percent Time Used15
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6348-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194222
Totals316004.0040248.0059948.0018.9

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS IN
ToHARRISON, MARION, PANOLA & UPSHUR
CSJ6348-26-001
Proj IDRMC - 634826001
Work TypeTREE & STUMP REMOVAL (S)
 
0.001554654.0018918.003.4
Work Order12-10-19
Work Began12-17-19
Work Completed
Time Computed12-16-19
Contract Working Days175
Addl Days Granted0
Working Days Charged20
Percent Time Used11
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6348-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09194223
Totals554654.0015813.0018918.003.4

page 1 | page 2