Monthly State Let Construction Report For Austin District As Of Aug 23, 2019 Page 1 Of 7

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWILLIAMSON
HighwayIH 35
FromAT CR 305
To.
CSJ0015-08-140
Proj IDNH 1802(398)
Work TypeSTRCT, GRADING, HMACP
 
0.1006028948.613780543.8162.7
Work Order08-15-18
Work Began10-01-18
Work Completed
Time Computed09-14-18
Contract Working Days260
Addl Days Granted0
Working Days Charged191
Percent Time Used73
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-140
AUSTIN WOOD RECYCLING (0.32)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.98)
HOUSTON SAWING & DRILLING (0.11)
J. R. (JOE) RAMON & SONS, INC. (0.74)
THE LEVY COMPANY, INC. (1.79)
LONE STAR PAVING COMPANY (12.78)
ROADWAY SPECIALTIES, INC. (2.50)
TEXOP CONSTRUCTION (0.42)
VOGES DRILLING CO. (2.12)
FLASHER EQUIPMENT COMPANY (1.59)
Contract #07183221
Totals6028948.6179095.523780543.8162.7

CountyWILLIAMSON
HighwayIH 35
FromAT THEON ROAD (RONALD REAGAN BLVD)
To.
CSJ0015-08-141
Proj IDNH 2019(683)
Work TypeGRADING, STRUCT, BASE, HMACP_& PVMK
 
0.02312273229.931623980.1313.2
Work Order04-08-19
Work Began06-17-19
Work Completed
Time Computed05-08-19
Contract Working Days390
Addl Days Granted0
Working Days Charged26
Percent Time Used6
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-141
BREDA COMPANY, INC. (0.51)
AARON CONCRETE CONTRACTORS, L.P. (2.16)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.83)
FLASHER EQUIPMENT COMPANY (1.06)
G. CARTER CONSTRUCTION COMPANY, INC. (1.61)
LONE STAR PAVING COMPANY (11.55)
PENHALL COMPANY (AUSTIN) (0.09)
SOUTH TEXAS PAINTING COMPANY (0.18)
TEXAS HIGHWAY WALLS (13.17)
VOGES DRILLING CO. (0.46)
Contract #03193210
Totals12273229.93671091.761623980.1313.2

CountyWILLIAMSON
HighwayIH 35
FromCORN HILL (BUD STOCKTON LP) UNDRPSS
ToFM 972 OVERPASS
CSJ0015-08-142
Proj IDNH 2019(605)
Work TypeGRADING, BASE, HMACP, PVMRK & SIGNS
 
6.17810670762.512144149.3920.0
Work Order02-13-19
Work Began04-15-19
Work Completed
Time Computed04-15-19
Contract Working Days350
Addl Days Granted0
Working Days Charged69
Percent Time Used19
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-142
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.90)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.85)
FLASHER EQUIPMENT COMPANY (1.91)
LONE STAR PAVING COMPANY (26.29)
PANTHER CREEK TRANSPORTATION, INC. (0.00)
ACME BARRICADES, LLC (0.03)
KRL CONSTRUCTION INC. (0.20)
Contract #01193206
Totals10670762.51180389.462144149.3920.0

CountyWILLIAMSON
HighwayIH 35
From1310 FT. SOUTH OF LAKEWAY DRIVE
To2250 FT. NORTH OF LAKEWAY DRIVE
CSJ0015-08-146
Proj IDNH 1602(279)
Work TypeLANDSCAPING AND IRRIGATION
 
1.115730891.76706306.5696.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-16
Work Began12-13-16
Work Completed
Time Computed09-23-16
Contract Working Days120
Addl Days Granted0
Working Days Charged102
Percent Time Used85
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-146
FLASHER EQUIPMENT COMPANY (1.00)
J & V UTILTIY (0.31)
CHOICE BUILDERS, LLC (0.46)
Contract #07163233
Totals730891.760.00706306.5696.6

CountyWILLIAMSON
HighwayIH 35
FromLAKEWAY DRIVE UNDERPASS
ToBELL COUNTY LINE
CSJ0015-08-151
Proj IDNH 2019(793)
Work TypeMILL, SEAL AND OVERLAY SBML
 
13.3605984750.13560175.419.3
Work Order04-16-19
Work Began07-08-19
Work Completed
Time Computed06-18-19
Contract Working Days78
Addl Days Granted0
Working Days Charged22
Percent Time Used28
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-151
TRP CONSTRUCTION GROUP, LLC (3.99)
AREA WIDE PROTECTIVE, INC. (0.02)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.08)
PERFORMANCE EQUIPMENT SERVICE (7.76)
CHEROKEE SERVICES (0.73)
SAN ANTONIO SWEEPING SERVICES, INC. (0.52)
TEXOP CONSTRUCTION (0.30)
Contract #03193242
Totals5984750.13560175.41560175.419.3

CountyWILLIAMSON
HighwayIH 35
From1500 FT NORTH OF LAKEWAY DRIVE
To3872 FT SOUTH OF SH 195
CSJ0015-08-153
Proj IDNH 1802(196)
Work TypeLANDSCAPING AND IRRIGATION
 
1.0231495000.001332037.1989.0
Work Order07-20-18
Work Began11-26-18
Work Completed
Time Computed10-18-18
Contract Working Days160
Addl Days Granted0
Working Days Charged72
Percent Time Used45
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-08-153
FLASHER EQUIPMENT COMPANY (1.15)
Contract #06183047
Totals1495000.005100.001332037.1989.0

CountyWILLIAMSON
HighwayIH 35
FromUS 79
ToSH 45N
CSJ0015-09-173
Proj IDSTP 2016(384)MM
Work TypeNORTHBOUND OPERATIONAL IMPROVEMENTS
 
2.29327970898.8330059787.5499.9
CountyWILLIAMSON
HighwayIH 35
FromUS 79
ToSH 45N
CSJ0015-09-182
Proj IDROW 15-9-182
Work TypeUTILITY ADJUSTMENTS
 
1.760156105.00155155.0099.3
Work Order05-25-16
Work Began06-20-16
Work Completed
Time Computed06-20-16
Contract Working Days555
Addl Days Granted111
Working Days Charged645
Percent Time Used96
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-09-173
N-LINE TRAFFIC MAINTENANCE, L.P. (0.38)
J. R. (JOE) RAMON & SONS, INC. (1.02)
ROADWAY SPECIALTIES, INC. (0.87)
TEXAS STEEL INDUSTRIAL PLACING, LLC (1.71)
ACU CONSTRUCTION LLC (0.46)
BRYANT & FREY CONSTRUCTION (0.06)
AARON CONCRETE CONTRACTORS, L.P. (1.67)
FLASHER EQUIPMENT COMPANY (1.03)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.25)
TEXAS TRUCKING COMPANY, INC. (0.00)
LONE STAR PAVING COMPANY (13.80)
AUSTIN WOOD RECYCLING (0.08)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.26)
RUSSO CORPORATION (0.88)
TEXAS TRUCKING COMPANY, INC. (0.00)
MCL CONTRACTING, LLC (0.07)
EARTH REINFORCEMENTS LLC (1.89)
ANCORTEX, INC. (1.02)
HERZOG FOUNDATION DRILLING, INC. (0.03)
HEARN CO. (0.00)
BEAIRD DRILLING (0.05)
FOUR J TRAFFIC CONTROLS, INC. (0.00)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.82)
PRIMATE CONSTRUCTION, INC. (0.07)
SOUTH TEXAS PAINTING COMPANY (0.04)
Contract #12153201
Totals28127003.83880675.6530214942.5499.9

CountyWILLIAMSON
HighwayIH 35
FromAT FM 3406
To.
CSJ0015-09-179
Proj IDC 15-9-179
Work TypeSTRCT, GR, BASE, HMACP, SGNL & MRKS
 
0.41712359959.7014988484.1599.9
CountyWILLIAMSON
HighwayIH 35
FromAT FM 3406
To.
CSJ0015-09-190
Proj IDROW 15-9-190
Work TypeUTILITIES
 
0.4172046.261420.0069.3
Work Order11-03-16
Work Began03-06-17
Work Completed
Time Computed03-06-17
Contract Working Days440
Addl Days Granted13
Working Days Charged427
Percent Time Used100
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-09-179
APAC-TEXAS, INC. (12.80)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (7.02)
DUSTROL, INC. (1.06)
FLASHER EQUIPMENT COMPANY (0.83)
GK CONSTRUCTION, LLC (0.39)
HOUSTON SAWING & DRILLING (0.06)
MCKINLEY DRILLING CO. (1.64)
OSCAR ORDUNO, INC. (1.76)
ROADWAY SPECIALTIES, INC. (1.10)
SCOTT DERR PAINTING CO, LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.55)
KRL CONSTRUCTION INC. (0.62)
BRADCO, LLC (5.18)
TIKI TRUCKING, L.P. (0.00)
AARON CONCRETE CONTRACTORS, L.P. (3.95)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.09)
TEXAS CUTTING & CORING, INC. (0.04)
LLOYD D. NABORS DEMOLITION LLC (2.47)
AREA WIDE PROTECTIVE, INC. (0.43)
SWEEP ACROSS TEXAS (0.13)
BADGER DAYLIGHTING CORP. (0.00)
TEXOP CONSTRUCTION (0.07)
Z & L CONCRETE CONTRACTORS, INC. (0.17)
Contract #09163204
Totals12362005.9651056.5014989904.1599.9

CountyWILLIAMSON
HighwayIH 35
FromFM 3406
ToRM 1431
CSJ0015-09-193
Proj IDNH 2019(747)
Work TypeFreeway Operational Improvements
 
1.2878847542.480.000.0
CountyWILLIAMSON
HighwayIH 35
FromFM 3406
ToRM 1431
CSJ0015-09-197
Proj IDROW 15-9-197
Work TypeFreeway Operational Improvements
 
1.2871858457.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-09-193
AUSTIN WOOD RECYCLING (0.13)
BRYANT & FREY CONSTRUCTION CO. (2.30)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.69)
FLASHER EQUIPMENT COMPANY (0.26)
GK CONSTRUCTION, LLC (0.18)
TEXAS HIGHWAY WALLS (5.45)
TEXAS MATERIALS GROUP, INC. (15.00)
THE LEVY COMPANY, INC. (21.14)
VOGES DRILLING CO. (0.42)
ABC EROSION CONTROL, INC (1.12)
JPC CONSTRUCTION, INC. (7.68)
Contract #04193010
Totals10705999.480.000.000.0

CountyTRAVIS
HighwayIH 35
FromRIVERSIDE DRIVE
ToMLK
CSJ0015-13-377
Proj IDC 15-13-377
Work TypeMILL, SEAL AND INLAY ON ML
 
10.3805984425.716328156.8299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-27-17
Work Began10-02-17
Work Completed
Time Computed10-02-17
Contract Working Days85
Addl Days Granted0
Working Days Charged82
Percent Time Used96
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-377
THE LEVY COMPANY, L.P. (4.49)
MPB, INC. (6.82)
TRP CONSTRUCTION GROUP, LLC (9.49)
GREEN MILLING GROUP LLC (7.34)
STRIPE-IT-UP (1.83)
Contract #06173015
Totals5984425.710.006328156.8299.9

CountyTRAVIS
HighwayIH 35
FromNORTH OF OLTORF
ToSOUTH OF OLTORF
CSJ0015-13-378
Proj IDNH 2016(108)
Work TypeOPERATIONAL IMPROVEMENTS
 
1.34638225002.0135426793.2492.0
CountyTRAVIS
HighwayIH 35
FromNORTH OF OLTORF
ToSOUTH OF OLTORF
CSJ0015-13-395
Proj IDNH 1602(361)
Work TypeUTILITY ADJUSTMENTS
 
1.0304392263.204470877.4899.9
Work Order11-15-16
Work Began02-01-17
Work Completed
Time Computed01-14-17
Contract Working Days594
Addl Days Granted16
Working Days Charged704
Percent Time Used115
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-378
AARON CONCRETE CONTRACTORS, L.P. (2.78)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.39)
BRICK PAVING PLUS, INC. (0.07)
AREA WIDE PROTECTIVE, INC. (1.42)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.53)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (7.11)
ROADWAY SPECIALTIES, INC. (0.38)
AUSTIN UNDERGROUND INCORPORATED (13.12)
RUCKIT, INC. (2.63)
LONE STAR PAVING COMPANY (14.32)
GULF COAST GROUTING, INC. (0.03)
W. W. FOUNDATION DRILLING, LTD. (1.12)
K.L. DURHAM CONSTRUCTION, LLC (0.09)
A & R DEMOLITION (0.28)
TEXAS STEEL INDUSTRIAL PLACING, LLC (0.31)
CENTRAL TEXAS ROAD BORING (0.58)
THE LEVY COMPANY, L.P. (3.57)
J.C. COMMUNICATION (2.88)
DAKOTA UTILITY CONTRACTORS, INC. (0.82)
HEARN CO. (0.27)
BEAIRD DRILLING (0.21)
CHLOR-SERV, INC. (0.00)
GK CONSTRUCTION, LLC (0.07)
ANCORTEX, INC. (3.71)
MCKINNEY DRILLING__(BUDA) (0.07)
MCKINNEY DRILLING__(BUDA) (0.25)
CENTRAL TEXAS REINFORCEMENT (0.01)
FOUR J TRAFFIC CONTROLS, INC. (0.00)
SOUTHERN CUTTING & CORING, LLC (0.00)
W.O.E. CONSTRUCTION (1.19)
PRIMATE CONSTRUCTION, INC. (0.25)
HB FARMER FOUNDATION, LLC (0.13)
STRIPE-IT-UP (0.06)
Contract #07163203
Totals42617265.211210933.8939897670.7293.0

CountyTRAVIS
HighwayIH 35
FromNORTH OF STASSNEY LANE
ToSOUTH OF WILLIAM CANNON DRIVE
CSJ0015-13-379
Proj IDSTP 1502(521)MM
Work TypeOPERATIONAL IMPROVEMENTS
 
4.88873779000.2461381516.5483.1
CountyTRAVIS
HighwayIH 35
FromNORTH OF STASSNEY LANE
ToSOUTH OF WILLIAM CANNON DRIVE
CSJ0015-13-390
Proj IDNH 2016(344)
Work TypeUTILITY ADJUSTMENTS ONLY
 
1.6555054226.504461457.1688.2
Work Order04-18-16
Work Began07-18-16
Work Completed
Time Computed07-18-16
Contract Working Days1,000
Addl Days Granted0
Working Days Charged872
Percent Time Used87
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-379
N-LINE TRAFFIC MAINTENANCE, L.P. (1.52)
RAMMING PAVING COMPANY (16.03)
TEXAS HIGHWAY WALLS (7.77)
EARTH REINFORCEMENTS LLC (4.32)
ROADWAY SPECIALTIES, INC. (1.33)
THE LEVY COMPANY, L.P. (12.07)
TRP CONSTRUCTION GROUP, LLC (1.23)
LIGHT IT UP ELECTRIC (0.15)
J.C. COMMUNICATION (1.81)
J.C. COMMUNICATION (2.52)
MCKINNEY DRILLING__(BUDA) (0.81)
CENTRAL TEXAS REINFORCEMENT (0.12)
AUSTIN UNDERGROUND INCORPORATED (7.06)
CENTRAL TEXAS ROAD BORING (0.27)
DAKOTA UTILITY CONTRACTORS, INC. (0.44)
TEXAS STEEL INDUSTRIAL PLACING, LLC (0.21)
BMP SPECIALIST, LLC (0.07)
BREDA COMPANY, INC. (0.02)
AARON CONCRETE CONTRACTORS, L.P. (1.88)
ACTION CONSTRUCTORS (1.44)
INDUS CONSTRUCTION, L.P. (0.10)
GRYPHON DRILLNG SERVICES, LLC (0.26)
TEXAS CUTTING & CORING, INC. (0.00)
A & A CONSTRUCTION (0.29)
K.L. DURHAM CONSTRUCTION, LLC (0.11)
A & R DEMOLITION (0.24)
C2 CONCRETE, INC. (1.05)
Contract #11153001
Totals78833226.741469479.4265842973.7083.5

CountyTRAVIS
HighwayIH 35
FromRUNDBERG LANE
ToUS 183
CSJ0015-13-382
Proj IDNH 1702(650)
Work TypeSTR, GR, BASE, ACP, SGNS & PVT MKS
 
2.675114072840.8544955129.4739.4
CountyTRAVIS
HighwayIH 35
FromRUNDBERG LANE
ToUS 183
CSJ0015-13-393
Proj IDNH 2017(232)
Work TypeACQUISITION, RELOCATION AND UTILITY
 
1.4787630125.256384752.8383.6
CountyTRAVIS
HighwayIH 35
FromUS 183
ToUS 290 E
CSJ0015-13-394
Proj IDNH 2017(291)
Work TypeACQUISITION, RELOCATION AND UTILITY
 
1.1972503564.45845806.2133.7
Work Order10-26-17
Work Began01-15-18
Work Completed
Time Computed12-25-17
Contract Working Days1,028
Addl Days Granted0
Working Days Charged452
Percent Time Used43
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-382
SPEEDY PAVING (0.08)
MOBILE ENTERPRISES, INC. (0.07)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.02)
CHOCTAW ERECTORS, INC. (3.58)
EARTH REINFORCEMENTS LLC (1.14)
STREET SMARTS, INC. (0.31)
THE LEVY COMPANY, L.P. (3.03)
D GUERRA CONSTRUCTION LLC (4.98)
TEXAS HIGHWAY WALLS (2.26)
TRP CONSTRUCTION GROUP, LLC (0.84)
PIONEER UTILITIES, INC. (2.98)
ROADWAY SPECIALTIES, INC. (0.64)
UNDER CONSTRUCTION INC. (0.05)
SCOTT DERR PAINTING CO, LLC (0.01)
HOUSTON SAWING & DRILLING (0.03)
GK CONSTRUCTION, LLC (1.00)
MICA CORPORATION (6.86)
BEAIRD DRILLING (0.96)
LONE STAR PAVING CO. (8.81)
J.A. ROAD BORING, INC. (0.21)
AUSTIN WOOD RECYCLING (0.01)
DURABLE SPECIALTIES, INC. (0.39)
BOWMAN ENGINEERING & CONSULTING, INC (0.06)
JPC CONSTRUCTION INC DBA JC COMMUNICATIONS (2.63)
BRYANT & FREY CONSTRUCTION (0.09)
AAR INCORPORATED (0.00)
ENCINO LANDSCAPE, INC. (0.02)
PANTHER CREEK TRANSPORTATION, INC. (1.81)
NATIONAL POWER RODDING CORPORATION (0.05)
Contract #08173201
Totals124206530.554888712.7952185688.5142.0

CountyTRAVIS
HighwayIH 35
FromAT PARMER LN
To.
CSJ0015-13-396
Proj IDNH 2018(907)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.81823054488.500.000.0
CountyTRAVIS
HighwayIH 35
FromAT PARMER LN
To.
CSJ0015-13-407
Proj IDROW 15-13-407
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.8181536440.900.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days376
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-396
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (15.99)
VOGES DRILLING CO. (0.12)
AREA WIDE PROTECTIVE, INC. (1.53)
PANTHER CREEK TRANSPORTATION, INC. (0.01)
C2 CONCRETE, INC. (2.01)
TEXAS MATERIALS GROUP, INC. (15.08)
R K STEPHENS CONSTRUCTION, LLC (2.94)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.02)
JPC CONSTRUCTION, INC. (4.49)
BEAIRD DRILLING (0.14)
KRL CONSTRUCTION INC. (1.51)
PERFORMANCE EQUIPMENT SERVICE (0.75)
SPEEDY PAVING (0.88)
GK CONSTRUCTION, LLC (0.17)
ROADWAY SPECIALTIES, INC. (1.03)
EARTH REINFORCEMENTS LLC (1.65)
TRP CONSTRUCTION GROUP, LLC (0.98)
ELITE CURB & CONCRETE, LLC (2.50)
Contract #04193005
Totals24590929.400.000.000.0

CountyTRAVIS
HighwayIH 35
FromAT 6TH STREET
To.
CSJ0015-13-401
Proj IDSTP 1702(308)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.300188299.00218053.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-17
Work Began11-20-17
Work Completed
Time Computed10-09-17
Contract Working Days109
Addl Days Granted0
Working Days Charged62
Percent Time Used56
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-401
KRL CONSTRUCTION INC. (5.94)
Contract #06173032
Totals188299.000.00218053.2899.9

CountyTRAVIS ETC
HighwayIH 35 ETC
FromIH 35 NBFR AND 8TH STREET INTER.
To.
CSJ0015-13-402
Proj IDSTP 1702(651)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
2.7001127245.941160100.2199.9
Work Order09-14-17
Work Began03-14-18
Work Completed
Time Computed12-11-17
Contract Working Days286
Addl Days Granted0
Working Days Charged212
Percent Time Used74
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-402
KRL CONSTRUCTION INC. (4.28)
D. I. J. CONSTRUCTION, INC. (1.21)
DARRELL STIFFLEMIRE (2.43)
ROADWAY TRAFFIC CONTROL LLC (0.34)
Contract #08173042
Totals1127245.942444.411160100.2199.9

CountyTRAVIS
HighwayIH 35
From51ST STREET
To0.14 MILES NORTH OF 51ST STREET
CSJ0015-13-414
Proj IDNH 2019(992)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.148246618.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days63
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS ROAD CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0015-13-414
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193051
Totals246618.000.000.000.0

CountyTRAVIS
HighwaySL 275
FromFOREMOST DR.
ToSLAUGHTER LN.
CSJ0016-01-125
Proj IDSTP 2019(380)
Work TypeTOM OVERLAY
 
2.3041030069.64210713.7320.4
Work Order02-20-19
Work Began07-22-19
Work Completed
Time Computed07-22-19
Contract Working Days26
Addl Days Granted0
Working Days Charged4
Percent Time Used15
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-01-125
AREA WIDE PROTECTIVE, INC. (1.75)
ENVIRONMENTAL SAFETY SERVICES, INC. (4.44)
FLASHER EQUIPMENT COMPANY (2.23)
SWEEP ACROSS TEXAS (0.00)
SAN ANTONIO SWEEPING SERVICES, INC. (0.00)
Contract #01193222
Totals1030069.64210713.73210713.7320.4

CountyHAYS
HighwayIH 35
FromOLD HWY 81 SOUTH OF KYLE
ToROBERT S LIGHT BLVD
CSJ0016-02-160
Proj IDNH 2018(401)
Work TypeMILL, SEAL & PFC
 
11.1343187981.523186277.8999.9
Work Order03-15-18
Work Began05-21-18
Work Completed
Time Computed05-21-18
Contract Working Days98
Addl Days Granted0
Working Days Charged84
Percent Time Used85
Contractor(s)
AUSTIN MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-02-160
ROADWAY SPECIALTIES, INC. (3.80)
TRP CONSTRUCTION GROUP, LLC (0.38)
FLASHER LIMITED (4.63)
PERFORMANCE EQUIPMENT SERVICE (8.02)
ACME BARRICADES, LLC (1.45)
PENHALL COMPANY (0.18)
TURNKEY OPERATIONS (0.14)
Contract #01183219
Totals3187981.52116782.053186277.8999.9

CountyHAYS
HighwayIH 35
From0.741 MI. N. OF POSEY ROAD
ToCOMAL COUNTY LINE
CSJ0016-03-103
Proj IDNH 1802(535)
Work TypeREPLACE BRIDGE & APPROACHES
 
2.27130043802.317381840.2724.5
CountyHAYS
HighwayIH 35
From0.741 MI. N. OF POSEY ROAD
ToCOMAL COUNTY LINE
CSJ0016-03-117
Proj IDROW 16-3-117
Work TypeROW ACQUISITION
 
2.271712687.250.000.0
CountyCOMAL
HighwayIH 35
FromHAYS COUNTY LINE
To0.5 MI S OF HAYS COUNTY LINE
CSJ0016-04-113
Proj IDNH 1802(610)
Work TypeRAMP CONSTRUCTION
 
0.497980487.67115892.2711.8
Work Order02-06-19
Work Began02-18-19
Work Completed
Time Computed02-18-19
Contract Working Days531
Addl Days Granted0
Working Days Charged112
Percent Time Used21
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0016-03-103
A K FUQUAY CONSTRUCTION (0.29)
AUSTIN MATERIALS, LLC (8.45)
BUYERS BARRICADES SAN ANTONIO, LLC (0.44)
AUSTIN UNDERGROUND INCORPORATED (0.89)
BLACKTOP INDUSTRIES LLC (0.30)
ADCOCK 4 INVESTMENTS, LLC (3.21)
EGGEMEYER LAND CLEARING, LLC (0.04)
GK CONSTRUCTION, LLC (0.12)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
MICA CORPORATION (8.45)
PAVEMENT MARKINGS INC. (0.06)
ROADWAY SPECIALTIES, INC. (1.19)
STRAIGHT LINE SAWING & SEALING, INC. (0.31)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.65)
FLASHER EQUIPMENT COMPANY (1.10)
TWISTED CX, LLC (0.21)
CND CONTRACTING (0.39)
LONE STAR PAVING COMPANY (0.00)
BREDA COMPANY, INC. (0.05)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (2.04)
BEAIRD DRILLING (0.39)
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (0.66)
GK CONSTRUCTION, LLC (0.03)
Contract #08183006
Totals31736977.232199026.767497732.5423.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7