Monthly State Let Construction Report For Austin District As Of Jul 13, 2018 Page 2 Of 5

Last Update: Friday, July 13, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGILLESPIE
HighwayUS 87
From0.394 MI N OF EQUESTRIAN DR
To0.086 MI SO OF HITCHIN POST TR
CSJ0072-01-052
Proj IDSTP 2017(940)HES
Work TypeINSTALL CONTINUOUS TURN LANE
 
0.684963063.12904858.3493.9
Work Order05-11-17
Work Began07-27-17
Work Completed
Time Computed07-10-17
Contract Working Days240
Addl Days Granted0
Working Days Charged175
Percent Time Used72
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-01-052
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.62)
FLASHER EQUIPMENT COMPANY (4.44)
M.V. HENKE ENTERPRISES, INC. (0.40)
ROADWAY SPECIALTIES, INC. (3.56)
HILL COUNTRY BRIDGE, INC. (22.92)
Contract #04173007
Totals963063.1221708.96904858.3493.9

CountyGILLESPIE
HighwayUS 87
FromUS 87 AT MAIN STREET
ToUS 87 AT FREDERICKSBURG CITY LIMITS
CSJ0072-01-053
Proj IDSTP 2018(270)
Work TypeMILL, SEAL & TOM
 
2.778885285.24758767.8785.7
Work Order12-14-17
Work Began05-07-18
Work Completed
Time Computed05-07-18
Contract Working Days37
Addl Days Granted0
Working Days Charged21
Percent Time Used56
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-01-053
FLASHER LIMITED (4.72)
GREEN MILLING GROUP (1.51)
Contract #11173210
Totals885285.24272277.10758767.8785.7

CountyTRAVIS
HighwayUS 290
FromCIRCLE DR EAST/SOUTHVIEW RD
ToEL REY BLVD
CSJ0113-08-077
Proj IDSTP 1702(036)HES
Work TypeADD CONT. TURN LN&PAVED SHLDRS(5FT)
 
0.9731856165.102216412.4099.9
Work Order06-14-17
Work Began07-05-17
Work Completed
Time Computed07-05-17
Contract Working Days87
Addl Days Granted0
Working Days Charged149
Percent Time Used171
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0113-08-077
AUSTIN WOOD RECYCLING (1.88)
AUSTIN MATERIALS, LLC (33.40)
FLASHER EQUIPMENT COMPANY (2.16)
ROADWAY SPECIALTIES, INC. (2.83)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.73)
DAVEY TREE & LAWN CARE (0.16)
TEXAS TRUCKING COMPANY, INC. (0.00)
Contract #05173023
Totals1856165.1022422.702216412.4099.9

CountyTRAVIS
HighwaySH 71
FromWOODWARD STREET
To533' WEST OF US 183
CSJ0113-13-165
Proj IDNH 1702(325)
Work TypeLANDSCAPING AND IRRIGATION
 
3.698737000.00641136.8086.9
Work Order07-20-17
Work Began09-05-17
Work Completed
Time Computed09-05-17
Contract Working Days120
Addl Days Granted0
Working Days Charged38
Percent Time Used31
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0113-13-165
FLASHER EQUIPMENT COMPANY (1.36)
Contract #06173012
Totals737000.003400.00641136.8086.9

CountyTRAVIS
HighwayUS 290
FromUS 183
ToFM 734
CSJ0114-02-100
Proj IDNH 1502(382)
Work TypeLANDSCAPING AND IRRIGATION
 
5.751834000.00791365.3094.8
Work Order10-20-15
Work Began02-09-16
Work Completed
Time Computed12-19-15
Contract Working Days120
Addl Days Granted0
Working Days Charged109
Percent Time Used90
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-02-100
ENVIRONMENTAL SAFETY SERVICES, INC. (6.37)
FLASHER EQUIPMENT COMPANY (0.78)
AMAYA UTILITY (2.15)
Contract #07153061
Totals834000.003400.00791365.3094.8

CountyLEE
HighwayUS 290
From5.7 MI E OF FM 141
To5.8 MI E OF FM 141
CSJ0114-07-080
Proj IDBR 2018(271)
Work TypeBRIDGE REHAB
 
0.200844010.32753744.3189.3
Work Order12-04-17
Work Began02-19-18
Work Completed
Time Computed01-03-18
Contract Working Days100
Addl Days Granted0
Working Days Charged52
Percent Time Used52
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-07-080
ENVIRONMENTAL SAFETY SERVICES, INC. (3.93)
S & S BRIDGE PAINTING, INC. (7.70)
FLASHER LIMITED (2.11)
OLDCASTLE MATERIALS TEXAS, INC. (33.85)
TEX OP CONSTRUCTION, LP (1.95)
Contract #11173010
Totals844010.32131268.08753744.3189.3

CountyLEE
HighwayUS 290
From0.690 MI EAST OF CR 226
ToLEE/FAYETTE COUNTY LINE
CSJ0114-07-082
Proj IDSTP 1702(665)HES
Work TypeINSTALL MEDIAN BARRIER
 
13.6301336982.721301422.0497.3
Work Order09-12-17
Work Began01-08-18
Work Completed
Time Computed11-11-17
Contract Working Days118
Addl Days Granted0
Working Days Charged85
Percent Time Used72
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-07-082
ENVIRONMENTAL SAFETY SERVICES, INC. (2.91)
Contract #08173208
Totals1336982.7293961.691301422.0497.3

CountyTRAVIS
HighwaySL 212
FromUS 290
ToFM 973
CSJ0114-20-011
Proj IDSTP 2018(529)
Work TypeMILL AND INLAY
 
8.7691158086.0060095.595.1
Work Order06-05-18
Work Began06-06-18
Work Completed
Time Computed06-06-18
Contract Working Days58
Addl Days Granted0
Working Days Charged9
Percent Time Used15
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0114-20-011
RUCOBA & MAYA CONSTRUCTION (10.89)
ROADWAY SPECIALTIES, INC. (6.28)
TRP CONSTRUCTION GROUP, LLC (4.32)
Contract #02183228
Totals1158086.0060095.5960095.595.1

CountyLLANO
HighwaySH 29
FromMASON COUNTY LINE
ToSH 71
CSJ0150-02-035
Proj IDSTP 2017(944)HESG
Work TypeTEXTURIZE SHLDRS- PROF PAVE MRKRS
 
44.514214228.810.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0150-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04173013
Totals214228.810.000.000.0

CountyLLANO ETC
HighwaySH 29 ETC
From0.049 MILES SOUTH OF CR 102
To0.166 MILES SOUTH OF CR 403
CSJ0150-02-038
Proj IDSTP 1702(326)HES
Work TypeINST CURVE WARN SGNS, HFST ON CURVE
 
1.432514230.77478058.3394.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-17
Work Began10-30-17
Work Completed
Time Computed10-18-17
Contract Working Days53
Addl Days Granted0
Working Days Charged66
Percent Time Used124
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0150-02-038
THE LEVY COMPANY, L.P. (18.74)
D.I.J. CONSTRUCTION, INC (3.85)
Contract #06173028
Totals514230.770.00478058.3394.5

CountyLLANO
HighwaySH 29
From0.1 MI E OF RM 2768
To0.2 MI E OF RM 2768
CSJ0150-02-039
Proj IDBR 2018(073)
Work TypeBRG REHAB- EROSION REPAIR
 
0.300890245.00364501.5040.9
Work Order11-16-17
Work Began04-03-18
Work Completed
Time Computed04-03-18
Contract Working Days68
Addl Days Granted0
Working Days Charged55
Percent Time Used80
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0150-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173227
Totals890245.00154479.00364501.5040.9

CountyLLANO
HighwaySH 29
FromMASON COUNTY LINE
ToSH 71
CSJ0150-02-040
Proj IDSTP 2018(465)
Work TypeLEVEL-UP AND SEAL COAT
 
14.6421617038.570.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0150-02-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173223
Totals1617038.570.000.000.0

CountyBURNET
HighwaySH 29
From0.284 MILES WEST OF RM 690
To0.173 MI E OF RM 690
CSJ0150-05-047
Proj IDSTP 1702(547)HES
Work TypeWIDEN SHLDER & CONTINUOUS TURN LN
 
0.4571003924.501157551.3999.9
Work Order08-23-17
Work Began09-18-17
Work Completed
Time Computed09-07-17
Contract Working Days97
Addl Days Granted0
Working Days Charged92
Percent Time Used94
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0150-05-047
LONE STAR PAVING (30.04)
D.I.J. CONSTRUCTION, INC (1.98)
WOLFE CONSTRUCTION GROUP, INC. (2.31)
F & W ELECTRICAL CONTRACTORS, INC. (7.23)
Contract #07173029
Totals1003924.50118895.701157551.3999.9

CountyBURNET
HighwaySH 29 ETC
FromFANNIN ST
ToUS 281
CSJ0150-05-048
Proj IDSTP 2018(466)
Work TypeEDGE MILL, REPAIR & TOM
 
9.6503931925.98120481.533.0
Work Order03-15-18
Work Began06-24-18
Work Completed
Time Computed05-29-18
Contract Working Days65
Addl Days Granted0
Working Days Charged16
Percent Time Used24
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0150-05-048
ROADWAY TRAFFIC CONTROL LLC (0.38)
D. I. J. CONSTRUCTION, INC. (2.89)
TEXAS OPERATIONS (3.27)
FLASHER LIMITED (0.23)
Contract #12173221
Totals3931925.98120481.53120481.533.0

CountyBURNET
HighwaySH 29
From0.862 MI WEST OF RM 243
To0.230 MI WEST OF RM 243
CSJ0151-01-051
Proj IDSTP 2018(180)
Work TypeCONSTRUCTION OF CONTINUOUS LTL
 
0.632612820.24483416.0578.8
Work Order11-10-17
Work Began01-29-18
Work Completed
Time Computed01-09-18
Contract Working Days70
Addl Days Granted0
Working Days Charged67
Percent Time Used95
Contractor(s)
DENBOW COMPANY INC.
SUBCONTRACTOR(S) FOR CCSJ: 0151-01-051
TEX OP CONSTRUCTION, LP (1.86)
STATEWIDE MATERIALS TRANSPORT LTD (2.25)
ROADWAY SPECIALTIES, INC. (2.59)
R K STEPHENS CONSTRUCTION, LLC (5.82)
LONE STAR PAVING (33.39)
FLASHER LIMITED (3.65)
D. I. J. CONSTRUCTION, INC. (3.17)
Contract #10173007
Totals612820.24238943.50483416.0578.8

CountyCALDWELL
HighwayUS 183
FromINTERSECTION OF US 183 AND IH 10
To.
CSJ0153-01-013
Proj IDNH 2018(469)
Work TypeINTERSECTION IMPROVEMENTS
 
0.1001769284.151054713.5359.6
Work Order01-10-18
Work Began04-23-18
Work Completed
Time Computed03-11-18
Contract Working Days83
Addl Days Granted0
Working Days Charged36
Percent Time Used43
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0153-01-013
GEOSOURCE, INC. (1.45)
THE LEVY COMPANY, INC. (9.47)
ROADWAY SPECIALTIES, INC. (2.78)
MURRAY CONSTRUCTION (0.75)
FLASHER LIMITED (2.23)
Contract #12173013
Totals1769284.15331207.791054713.5359.6

CountyWILLIAMSON
HighwayUS 79
From0.4 MI W OF NOLAN RYAN BLVD
To0.53 MI W OF NOLAN RYAN BLVD
CSJ0204-01-070
Proj IDCC 204-1-70
Work TypeLENGTHEN LEFT TURN LANE
 
0.130110817.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX COMMERCIAL CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0204-01-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183032
Totals110817.600.000.000.0

CountyLEE
HighwayUS 77 ETC
From3.5 MI S OF MILAM C/L
ToSL 123
CSJ0211-02-026
Proj IDNH 2018(531)
Work TypeLEVEL-UP, FULL DEPTH REPAIR AND TOM
 
17.5575387885.79814795.3815.1
Work Order03-14-18
Work Began05-21-18
Work Completed
Time Computed04-13-18
Contract Working Days86
Addl Days Granted0
Working Days Charged31
Percent Time Used36
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0211-02-026
CHEROKEE SERVICES (0.23)
D. I. J. CONSTRUCTION, INC. (4.46)
M.V. HENKE ENTERPRISES, INC. (1.59)
TRP CONSTRUCTION GROUP, LLC (0.18)
WEST TEXAS RUMBLE STRIP (0.08)
NIXON ENGINEERING (0.00)
Contract #02183021
Totals5387885.79641950.98814795.3815.1

CountyTRAVIS
HighwaySH 71
From0.120 MI. EAST OF NAVARRO CREEK RD.
To0.316 MI EACH OF NAVARRO CREEK RD.
CSJ0265-02-035
Proj IDCC 265-2-35
Work TypeGRADING, BASE, HMACP & PVMT MRKNGS
 
0.196184200.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AARON CONCRETE CONTRACTORS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0265-02-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183046
Totals184200.600.000.000.0

CountyBASTROP
HighwaySH 71
From0.40 MI E OF LP 150
To1.514 MI E OF LP 230
CSJ0265-05-079
Proj IDNH 2017(788)
Work TypeLEVEL-UP & TOM
 
15.9665983021.724972783.9983.1
Work Order04-24-17
Work Began07-10-17
Work Completed
Time Computed05-24-17
Contract Working Days95
Addl Days Granted0
Working Days Charged86
Percent Time Used90
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0265-05-079
DUSTROL, INC. (3.76)
TRP CONSTRUCTION GROUP, LLC (5.73)
Contract #03173034
Totals5983021.72674298.244972783.9983.1

page 1 | page 2 | page 3 | page 4 | page 5