Monthly State Let Construction Report For Austin District As Of Dec 07, 2021 Page 5 Of 7

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATION DISTRICTWIDE
To.
CSJ0914-00-411
Proj IDSTP 2019(381)
Work TypeINSTALL OR REBUILD TRAFFIC SIGNALS
 
0.0032524408.562839195.6599.9
Work Order02-20-19
Work Began05-20-19
Work Completed
Time Computed05-20-19
Contract Working Days300
Addl Days Granted9
Working Days Charged313
Percent Time Used101
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-411
FLASHER EQUIPMENT COMPANY (3.70)
AREA WIDE PROTECTIVE, INC. (0.57)
KYROS INDUSTRIES, LLC (0.28)
Contract #01193213
Totals2524408.568820.732839195.6599.9

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON IH 35, US 183,
ToUS 290, SH 71 & SL 1
CSJ0914-00-418
Proj IDC 914-00-418
Work TypeASPHALT PAVEMENT REPAIR
 
0.1002145700.00529401.2424.6
Work Order12-18-18
Work Began10-16-19
Work Completed
Time Computed08-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-418
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11183026
Totals2145700.0068944.48529401.2424.6

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS
To.
CSJ0914-00-420
Proj IDSTP 1902(186)
Work TypePED
 
0.1002396038.452425209.1299.9
Work Order08-13-19
Work Began03-02-20
Work Completed
Time Computed09-12-19
Contract Working Days288
Addl Days Granted20
Working Days Charged301
Percent Time Used97
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-420
AREA WIDE PROTECTIVE, INC. (1.34)
PAVEMENT MARKINGS INC. (8.82)
CLASSIC TEJAS CONSTRUCTION, INC. (8.18)
Contract #07193246
Totals2396038.4571643.192425209.1299.9

CountyTRAVIS
HighwayVA
FromIN TRAVIS, WILIAMSON, HAYS COUNTIES
To.
CSJ0914-00-427
Proj IDC 914-00-427
Work TypeTRAFFIC CONTROL DEVICES
 
0.100523663.38400142.2176.4
Work Order07-20-20
Work Began09-21-21
Work Completed
Time Computed11-17-20
Contract Working Days85
Addl Days Granted20
Working Days Charged39
Percent Time Used37
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-427
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06203028
Totals523663.38139139.12400142.2176.4

CountyTRAVIS
HighwayVA
FromIN TRAVIS, WILLIAMSON & HAYS COUNTIES
To.
CSJ0914-00-440
Proj IDSTP 2020(513)
Work TypeTRAFFIC CONTROL DEVICES
 
979738.77977194.8999.7
Work Order02-18-20
Work Began08-31-20
Work Completed
Time Computed03-19-20
Contract Working Days264
Addl Days Granted0
Working Days Charged254
Percent Time Used96
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-440
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (16.00)
ENVIRONMENTAL SAFETY SERVICES, INC. (1.62)
Contract #01203023
Totals979738.7729967.88977194.8999.7

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN HAYS, TRAVIS,
ToAND WILLIAMSON COUNTIES
CSJ0914-00-446
Proj IDSTP 2020(967)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.1002592102.001492579.4557.5
Work Order07-20-20
Work Began10-22-20
Work Completed
Time Computed08-19-20
Contract Working Days271
Addl Days Granted0
Working Days Charged218
Percent Time Used80
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-446
G. CARTER CONSTRUCTION COMPANY, INC. (13.48)
A K FUQUAY CONSTRUCTION (3.92)
FLASHER EQUIPMENT COMPANY (8.67)
Contract #06203211
Totals2592102.0066068.811492579.4557.5

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS ON US 290 & SH 71
ToIN BASTROP & LEE COUNTIES
CSJ0914-00-449
Proj IDSTP 2020(937)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
428805.00405764.3094.6
Work Order08-14-20
Work Began10-19-20
Work Completed
Time Computed09-13-20
Contract Working Days55
Addl Days Granted0
Working Days Charged36
Percent Time Used65
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-449
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.11)
Contract #07203242
Totals428805.001000.00405764.3094.6

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS IN TRAVIS COUNTY
ToSL 1, IH 35, US 290, FM 3177, FM 11
CSJ0914-00-450
Proj IDSTP 2B20(210)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5650620.002866713.8750.8
Work Order09-18-20
Work Began01-11-21
Work Completed
Time Computed10-18-20
Contract Working Days160
Addl Days Granted17
Working Days Charged185
Percent Time Used104
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-450
DIIBS SPECIALISTS, LLC (0.00)
Contract #08203264
Totals5650620.00116906.452866713.8750.8

CountyTRAVIS
HighwayVA
FromIN BLANCO, BURNET & GILLESPIE COUNTIES
ToON US 290, RM 2341 & RM 1174
CSJ0914-00-452
Proj IDSTP 2B20(137)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.1003887917.502292290.4058.9
Work Order09-18-20
Work Began10-16-20
Work Completed
Time Computed10-16-20
Contract Working Days285
Addl Days Granted0
Working Days Charged240
Percent Time Used84
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-452
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203012
Totals3887917.5091244.002292290.4058.9

CountyTRAVIS
HighwayVA
FromVARIOUS IN TRAVIS & WILLIAMSON CO
ToON FM 3405, FM 487, RM 2222, ETC.
CSJ0914-00-453
Proj IDSTP 2B20(138)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2181871.901884998.6986.8
Work Order09-24-20
Work Began01-25-21
Work Completed
Time Computed10-24-20
Contract Working Days118
Addl Days Granted0
Working Days Charged130
Percent Time Used110
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-453
BK FIELD OPERATIONS LLC (47.58)
Contract #08203031
Totals2181871.9027864.801884998.6986.8

CountyTRAVIS
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0914-00-455
Proj IDC 914-00-455
Work TypeTRAFFIC CONTROL DEVICES
 
1305817.910.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days218
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-00-455
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213218
Totals1305817.910.000.000.0

CountyWILLIAMSON
HighwayVA
FromVARIOUS ON IH 35, FM 1460 & US 79
ToIN WILLIAMSON COUNTY
CSJ0914-05-209
Proj IDC 914-5-209
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.100288957.00249444.3286.3
Work Order05-14-21
Work Began10-04-21
Work Completed
Time Computed08-12-21
Contract Working Days32
Addl Days Granted0
Working Days Charged21
Percent Time Used65
Contractor(s)
TIGHT LINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-05-209
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.60)
HURRICANE INDUSTRIAL SERVICES LLC (1.33)
Contract #04213025
Totals288957.00212014.32249444.3286.3

CountyLLANO
HighwayCR
FromON CR 103 AT LLANO RIVER
ToSTR AA0596001
CSJ0914-25-008
Proj IDBR 1802(787)
Work TypeBRIDGE REPLACEMENT
 
0.1001599439.501035178.1364.7
Work Order05-20-21
Work Began06-28-21
Work Completed
Time Computed06-19-21
Contract Working Days96
Addl Days Granted0
Working Days Charged79
Percent Time Used82
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0914-25-008
DALLAS LITE AND BARRICADE, INC. (0.00)
Contract #04213011
Totals1599439.50388722.081035178.1364.7

CountyMASON
HighwayCS
FromON POST HILL ST AT GAMELS BRANCH
ToSTR# B00320001
CSJ0914-26-009
Proj IDBR 2017(195)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
0.100173539.00203275.4199.9
Work Order05-14-21
Work Began08-03-21
Work Completed
Time Computed06-13-21
Contract Working Days47
Addl Days Granted0
Working Days Charged22
Percent Time Used46
Contractor(s)
BLACKSMITH VENTURES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-26-009
DRY CREEK CONSTRUCTION LLC (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.00)
Contract #04213027
Totals173539.002700.00203275.4199.9

CountyHAYS
HighwayVA
FromEAST OF HOPKINS ST.
ToWEST OF IH 35 SBFR
CSJ0914-33-078
Proj IDSTP 2019(348)TAPS
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
0.6911519610.001956749.2899.9
Work Order11-20-19
Work Began02-17-20
Work Completed
Time Computed12-20-19
Contract Working Days95
Addl Days Granted70
Working Days Charged147
Percent Time Used89
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 0914-33-078
ENVIRONMENTAL SAFETY SERVICES, INC. (2.81)
FLASHER EQUIPMENT COMPANY (0.27)
LONE STAR EROSION CONTROL (4.49)
VOGES DRILLING CO. (1.80)
FRANK JR REINFORCEMENT LLC (0.09)
FRANK JR REINFORCEMENT LLC (0.05)
Contract #09193218
Totals1519610.00196956.981956749.2899.9

CountyHAYS
HighwayFM 621
From0.1 MILES NW OF DE ZAVALA DRIVE
To0.1 MILES SE OF PICASSO DR.
CSJ0987-03-012
Proj IDSTP 2021(806)MM
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1.9752961992.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-27-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days111
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0987-03-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213031
Totals2961992.450.000.000.0

CountyTRAVIS
HighwayFM 812
From0.1 MI WEST OF FM 973
ToELROY RD
CSJ1149-01-030
Proj IDSTP 2022(256)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1170306.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days33
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1149-01-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12213020
Totals1170306.780.000.000.0

CountyTRAVIS
HighwayFM 969
FromFM 973
ToHUNTERS BEND RD.
CSJ1186-01-091
Proj IDPTF 2022(045)
Work TypeWIDEN NON-FREEWAY
 
1.8688953609.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1186-01-091
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.61)
VOGES DRILLING CO. (0.86)
THE LEVY COMPANY, INC. (5.43)
SCOTT DERR PAINTING CO, LLC (0.09)
R K STEPHENS CONSTRUCTION, LLC (4.79)
LONE STAR PAVING COMPANY (10.27)
GK CONSTRUCTION, LLC (0.88)
DIIBS SPECIALISTS, LLC (0.57)
D. I. J. CONSTRUCTION, INC. (1.06)
Contract #09213221
Totals8953609.720.000.000.0

CountyBASTROP
HighwayFM 969
FromTRAVIS COUNTY LINE
ToSH 21/ SH 71
CSJ1186-02-017
Proj IDSTP 2B20(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.196161836.82116499.2771.9
CountyBASTROP
HighwayFM 969
FromTRAVIS COUNTY LINE
ToSH 71
CSJ1186-02-020
Proj IDSTP 2B20(027)
Work TypeSEAL COAT
 
12.1962577489.462777767.2299.9
CountyBASTROP
HighwayFM 1441
FromSH 95
ToSH 21
CSJ2991-01-010
Proj IDSTP 2B20(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.54287006.40131680.7099.9
Work Order08-14-20
Work Began10-29-20
Work Completed
Time Computed10-29-20
Contract Working Days66
Addl Days Granted0
Working Days Charged51
Percent Time Used77
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1186-02-017
STRIPE-IT-UP (0.53)
M CO ASPHALT MILLING AND CONSTRUCTION, LLC (2.06)
TRP CONSTRUCTION GROUP, LLC (0.41)
D. I. J. CONSTRUCTION, INC. (8.50)
F. N. PLOCH CONSTRUCTION COMPANY, INC. (10.78)
Contract #07203219
Totals2826332.6847942.403025947.1999.9

CountyHAYS
HighwayRM 150
From0.18 MI SOUTH OF EDLER HILL ROAD
To0.15 MI NORTH OF RM 3237
CSJ1197-01-024
Proj IDSTP 2021(039)
Work TypeSEAL COAT
 
1256562.091360398.1099.9
Work Order10-21-20
Work Began04-05-21
Work Completed
Time Computed04-05-21
Contract Working Days40
Addl Days Granted0
Working Days Charged31
Percent Time Used77
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1197-01-024
STRIPE-IT-UP (0.79)
M CO ASPHALT MILLING AND CONSTRUCTION, LLC (3.58)
ROADWAY TRAFFIC CONTROL LLC (1.95)
TRP CONSTRUCTION GROUP, LLC (8.04)
ENVIRONMENTAL SAFETY SERVICES, INC. (7.47)
R K STEPHENS CONSTRUCTION, LLC (2.35)
Contract #09203029
Totals1256562.0916915.351360398.1099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7