Monthly State Let Construction Report For Austin District As Of Dec 07, 2021 Page 7 Of 7

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBASTROP
HighwayFM 2336
FromUS 290
ToSH 95
CSJ2190-01-007
Proj IDSTP 1902(006)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.7963987883.563876481.5997.2
Work Order12-11-20
Work Began02-03-21
Work Completed
Time Computed01-10-21
Contract Working Days162
Addl Days Granted0
Working Days Charged146
Percent Time Used90
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2190-01-007
ACME BARRICADES, LLC (0.41)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.21)
AREA WIDE PROTECTIVE, INC. (0.63)
BATTERSON, LLP (2.18)
COLD CREEK CONSTRUCTION, LTD (1.96)
LONE STAR EROSION CONTROL (6.83)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
Contract #11203217
Totals3987883.5660121.953876481.5997.2

CountyWILLIAMSON
HighwayRM 2338
FromAT RONALD REAGAN INTERSECTION
To.
CSJ2211-01-026
Proj IDSTP 2021(620)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2007570067.83837607.4811.0
Work Order07-20-21
Work Began10-05-21
Work Completed
Time Computed08-19-21
Contract Working Days171
Addl Days Granted0
Working Days Charged36
Percent Time Used21
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2211-01-026
G. CARTER CONSTRUCTION COMPANY, INC. (0.00)
DIIBS SPECIALISTS, LLC (0.00)
BEAIRD DRILLING (0.00)
LONE STAR PAVING COMPANY (0.00)
JL3 CONSTRUCTION SERVICES LLC (0.00)
PRIMATE CONSTRUCTION, LP (0.00)
PIONEER UTILITIES, INC. (0.00)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
TEXAS HIGHWAY WALLS (0.00)
GK CONSTRUCTION, LLC (0.29)
Contract #06213008
Totals7570067.83427900.40837607.4811.0

CountyWILLIAMSON
HighwayFM 1460
FromOLD SETTLERS BOULEVARD
ToUS 79
CSJ2211-02-031
Proj IDSTP 2021(365)
Work TypeOVERLAY
 
976594.31916186.3493.8
Work Order03-19-21
Work Began09-27-21
Work Completed
Time Computed08-01-21
Contract Working Days47
Addl Days Granted0
Working Days Charged34
Percent Time Used72
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2211-02-031
ACME BARRICADES, LLC (0.51)
FLASHER EQUIPMENT COMPANY (4.41)
STRIPE-IT-UP (1.02)
TEXAS SITE SERVICES, LLC (1.27)
Contract #02213029
Totals976594.31358337.16916186.3493.8

CountyTRAVIS
HighwayFM 2304
FromRAVENSCROFT
ToFM 1626
CSJ2689-01-023
Proj IDSTP 1902(245)MM
Work TypeWIDEN NON-FREEWAY
 
1.13711941333.7811714432.0296.9
CountyTRAVIS
HighwayFM 2304
FromRAVENSCROFT
ToFM 1626
CSJ2689-01-028
Proj IDROW 2689-1-28
Work TypeRIGHT OF WAY
 
1.137210650.00152384.7672.3
Work Order11-26-19
Work Began12-17-19
Work Completed
Time Computed12-17-19
Contract Working Days288
Addl Days Granted75
Working Days Charged372
Percent Time Used102
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2689-01-023
ENVIRONMENTAL SAFETY SERVICES, INC. (1.54)
TRP CONSTRUCTION GROUP, LLC (0.68)
SCOTT DERR PAINTING CO, LLC (0.28)
R K STEPHENS CONSTRUCTION, LLC (3.29)
UNDERGROUND WATER SOLUTIONS, CO. (1.30)
VOGES DRILLING CO. (1.84)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.41)
AUSTIN MATERIALS, LLC (17.83)
KLP COMMERCIAL, L.L.C. (2.50)
PIPE WHOLESALERS OF TEXAS, INC. (5.80)
GK CONSTRUCTION, LLC (0.12)
C&M PRECAST CONCRETE COMPANY (0.00)
LONE STAR PAVING COMPANY (8.07)
M CO ASPHALT MILLING AND CONSTRUCTION, LLC (0.12)
STRIPE-IT-UP (0.08)
DELA LAGUNA CONTRACTING (0.02)
Contract #08193058
Totals12151983.78836435.7711866816.7896.4

CountyWILLIAMSON
HighwayFM 971
FromSH 130
To6.704 MILES EAST OF SH 130
CSJ2690-01-036
Proj IDSTP 2021(366)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.7048428384.672762836.0932.7
Work Order03-12-21
Work Began04-26-21
Work Completed
Time Computed04-11-21
Contract Working Days410
Addl Days Granted0
Working Days Charged115
Percent Time Used28
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2690-01-036
EGGEMEYER LAND CLEARING, LLC (0.34)
FLASHER EQUIPMENT COMPANY (1.02)
JB PINNACLE GROUP, LLC (0.91)
LONE STAR EROSION CONTROL (5.74)
LONE STAR PAVING COMPANY (8.56)
ROADWAY SPECIALTIES, INC. (0.64)
RUCOBA & MAYA CONSTRUCTION, LLC (14.60)
Contract #02213011
Totals8428384.67632189.272762836.0932.7

CountyWILLIAMSON
HighwayFM 971
FromSS 158 AUSTIN AVENUE!
ToGANN STREET/RIVER HAVEN DRIVE
CSJ2690-01-037
Proj IDCC 2690-1-37
Work TypeWIDEN NON-FREEWAY
 
0.2704059995.001915373.9047.1
Work Order07-20-21
Work Began09-07-21
Work Completed
Time Computed08-01-21
Contract Working Days124
Addl Days Granted0
Working Days Charged50
Percent Time Used40
Contractor(s)
CHASCO CONSTRUCTORS
SUBCONTRACTOR(S) FOR CCSJ: 2690-01-037
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (8.51)
AUSTIN WOOD RECYCLING (0.24)
ENVIRONMENTAL SAFETY SERVICES, INC. (3.78)
FLASHER EQUIPMENT COMPANY (1.13)
ROSCH COMPANY (1.78)
TEXAS MATERIALS GROUP, INC. (11.56)
TEXAS HIGHWAY WALLS (5.27)
Contract #06213219
Totals4059995.00830197.901915373.9047.1

CountyCALDWELL
HighwayFM 2984
FromFM 671
To0.463 MILES WEST OF US 183
CSJ3006-01-007
Proj IDSTP 2B20(041)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.5722961403.111282547.4043.3
Work Order09-18-20
Work Began12-01-20
Work Completed
Time Computed12-01-20
Contract Working Days191
Addl Days Granted0
Working Days Charged174
Percent Time Used91
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3006-01-007
LONE STAR PAVING COMPANY (19.98)
D. I. J. CONSTRUCTION, INC. (2.62)
PINNACLE GRINDING AND GROOVING LLC (0.49)
EGGEMEYER LAND CLEARING, LLC (1.41)
DIIBS SPECIALISTS, LLC (2.37)
FLASHER EQUIPMENT COMPANY (0.59)
TEXAS ICON CONSTRUCTION, LLC (7.80)
Contract #08203028
Totals2961403.11117249.451282547.4043.3

CountyTRAVIS
HighwaySL 1
FromDUVAL ROAD
To0.8 MILES WEST OF DUVAL ROAD
CSJ3136-01-191
Proj IDC 3136-1-191
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1067706.11456374.8142.9
CountyTRAVIS
HighwayFM 734
From0.23 MI. WEST OF HARRIS RIDGE BLVD.
To0.08 MI. EAST OF HARRIS RIDGE BLVD.
CSJ3417-03-025
Proj IDCC 3417-3-25
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.311457873.15117877.5025.7
Work Order05-06-21
Work Began07-07-21
Work Completed
Time Computed06-05-21
Contract Working Days64
Addl Days Granted0
Working Days Charged67
Percent Time Used104
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-191
FLASHER EQUIPMENT COMPANY (1.62)
AREA WIDE PROTECTIVE, INC. (0.62)
AUSTIN MATERIALS, LLC (22.15)
ENVIRONMENTAL SAFETY SERVICES, INC. (6.31)
G. CARTER CONSTRUCTION COMPANY, INC. (16.78)
LONE STAR PAVING COMPANY (22.15)
Contract #04213232
Totals1525579.26107753.15574252.3137.7

CountyTRAVIS
HighwaySL 1
FromSLAUGHTER LANE
ToSOUTH BAY LANE
CSJ3136-01-194
Proj IDC 3136-1-194
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
1369463.75705878.6251.5
Work Order05-20-21
Work Began09-07-21
Work Completed
Time Computed06-19-21
Contract Working Days172
Addl Days Granted0
Working Days Charged51
Percent Time Used29
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3136-01-194
FLASHER EQUIPMENT COMPANY (0.40)
Contract #04213219
Totals1369463.75396447.37705878.6251.5

CountyBLANCO
HighwayRM 473
FromUS 281
ToRM 32
CSJ3278-01-003
Proj IDSTP 2020(929)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.6683837576.304058826.3099.9
Work Order07-27-20
Work Began09-12-20
Work Completed
Time Computed08-01-20
Contract Working Days180
Addl Days Granted40
Working Days Charged229
Percent Time Used104
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3278-01-003
COLD CREEK CONSTRUCTION, LTD (2.13)
D. I. J. CONSTRUCTION, INC. (2.04)
FLASHER EQUIPMENT COMPANY (1.35)
A K FUQUAY CONSTRUCTION (2.65)
HILL COUNTRY BRIDGE, INC. (23.29)
LONE STAR EROSION CONTROL (3.27)
Contract #06203206
Totals3837576.30123215.724058826.3099.9

CountyTRAVIS
HighwayFM 734
From0.1 M. NW OF YAGER LANE
To0.1 M. SE OF YAGER LANE
CSJ3417-03-030
Proj IDSTP 2B20(135)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
552366.52592015.7499.9
Work Order09-16-20
Work Began03-15-21
Work Completed
Time Computed03-15-21
Contract Working Days180
Addl Days Granted0
Working Days Charged143
Percent Time Used79
Contractor(s)
JOE BLAND CONSTRUCTION, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 3417-03-030
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (41.18)
TEXAS MATERIALS GROUP, INC. (15.47)
FLASHER EQUIPMENT COMPANY (3.11)
ENVIRONMENTAL SAFETY SERVICES, INC. (5.92)
KRL CONSTRUCTION INC. (0.00)
Contract #08203254
Totals552366.525472.19592015.7499.9

CountyHAYS
HighwayFM 110
FromSH 21
ToEAST OF IH 35
CSJ3545-01-005
Proj IDSTP 2021(810)MM
Work TypeNEW LOCATION NON-FREEWAY
 
4.32015724881.540.000.0
CountyCALDWELL
HighwayFM 110
FromSH 80
ToSH 21
CSJ3545-03-003
Proj IDSTP 2021(811)MM
Work TypeNEW LOCATION NON-FREEWAY
 
1.99019792779.890.000.0
CountyCALDWELL
HighwayFM 110
FromSH 80
ToSH 21
CSJ3545-03-006
Proj IDROW 3545-3-6
Work TypeRIGHT OF WAY
 
1.9901038738.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days475
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3545-01-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213204
Totals36556399.930.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7