Monthly Local Let Maintenance Report For Austin District As Of Sep 18, 2019 Page 1 Of 4

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6182-61-001
Proj IDSUP - 618261001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001280300.44887401.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-25-08
Work Began07-01-08
Work Completed
Time Computed07-01-08
Contract Working Days365
Addl Days Granted0
Working Days Charged1,157
Percent Time Used316
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES OF CENTRAL TEXAS
SUBCONTRACTOR(S) FOR CCSJ: 6182-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06081431
Totals280300.440.00887401.3899.9

CountyMASON
HighwaySH0029
FromMASON COUNTY MAINTENANCE OFFICE
To.
CSJ6231-23-001
Proj IDSUP - 623123001
Work TypeJANITORIAL MAINTENANCE IN MASON COUNTY
 
0.00113355.3212900.5321.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-11
Work Began08-16-11
Work Completed
Time Computed08-16-11
Contract Working Days730
Addl Days Granted0
Working Days Charged747
Percent Time Used102
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6231-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08111430
Totals13355.320.0012900.5321.6

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6235-86-001
Proj IDSUP - 623586001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001719997.41625964.0187.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-12-11
Work Began08-15-11
Work Completed
Time Computed08-15-11
Contract Working Days1,048
Addl Days Granted0
Working Days Charged1,051
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6235-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08111432
Totals719997.410.00625964.0187.8

CountyTRAVIS
HighwayFM0969
FromTRAVIS EAST MAINTENANCE OFFICE
To.
CSJ6260-08-001
Proj IDSUP - 626008001
Work TypeJANITORIAL MAINTENANCE
 
0.0018147.768147.76100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-13
Work Began06-03-13
Work Completed07-14-15
Time Computed06-03-13
Contract Working Days730
Addl Days Granted0
Working Days Charged721
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6260-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05131432
Totals8147.760.008147.76100.0

CountyTRAVIS
HighwayUS0183
FromVARIOUS LOCATIONS IN
ToTRAVIS AND HAYS COUNTY
CSJ6264-02-001
Proj IDRMC - 626402001
Work TypeREMOVAL AND DISPOSAL OF TREES & BRUSH
 
0.010184732.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FST CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6264-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10131403
Totals184732.000.000.000.0

CountyTRAVIS
HighwayRM2322
FromSH 71
ToEND STATE MAINTENANCE
CSJ6268-21-001
Proj IDRMC - 626821001
Work TypeTIER 1 SEAL
 
4.564298395.12329641.98100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-23-14
Work Began05-05-14
Work Completed08-08-14
Time Computed05-05-14
Contract Working Days18
Addl Days Granted0
Working Days Charged19
Percent Time Used105
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6268-21-001
FLASHER EQUIPMENT COMPANY (23.70)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.93)
Contract #03141402
Totals298395.120.00329641.98100.0

CountyGILLESPIE
HighwayUS0290
FromVARIOUS LOCATIONS IN GILLESPIE
To.
CSJ6269-64-001
Proj IDSUP - 626964001
Work TypeLITTER REMOVAL
 
0.00184585.8260167.55100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-14
Work Began04-01-14
Work Completed01-28-16
Time Computed04-07-14
Contract Working Days60
Addl Days Granted0
Working Days Charged32
Percent Time Used53
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6269-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02141430
Totals84585.820.0060167.55100.0

CountyMASON
HighwayUS0087
FromVARIOUS LOCATIONS IN MASON, LLANO AND
ToGILLESPIE COUNTIES
CSJ6271-62-001
Proj IDRMC - 627162001
Work TypeLITTER REMOVAL
 
0.00192146.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLAGSHIP SWEEPING SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04141404
Totals92146.200.000.000.0

CountyTRAVIS
HighwayLP0001
FromTRAVIS AND WILLIAMSON COUNTIES
To.
CSJ6274-83-001
Proj IDSUP - 627483001
Work TypeJANITORIAL SERVICES FOR TOLL ROADS
 
0.001299990.94495378.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged315
Percent Time Used43
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL TEMPORARY SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141432
Totals299990.940.00495378.0299.9

CountyWILLIAMSON
HighwayFM0970
FromAT BERRY CREEK
To.
CSJ6276-22-001
Proj IDBPM - 627622001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.02486740.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days39
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-22-001
AREA WIDE PROTECTIVE, INC. (0.00)
Contract #01171405
Totals86740.000.000.000.0

CountyMASON
HighwayUS0087
FromVARIOUS LOCATIONS IN MASON, LLANO
ToAND GILLESPIE COUNTIES
CSJ6276-88-001
Proj IDRMC - 627688001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001221836.00221712.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged37
Percent Time Used71
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141406
Totals221836.000.00221712.0099.9

CountyHAYS
HighwayRM0012
FromBLANCO RIVER
ToBLANCO RIVER
CSJ6289-77-001
Proj IDEMC - 628977001
Work TypeBRIDGE RAIL REPAIR
 
0.100724979.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CAPITAL EXCAVATION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6289-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151430
Totals724979.000.000.000.0

CountyTRAVIS
HighwayUS0290
FromVARIOUS PONDS
ToIN THE TRAVIS SOUTH MO AREA
CSJ6313-76-001
Proj IDSUP - 631376001
Work TypeDETENTION POND LITTER PICK UP REMOVAL
 
0.00126364.760.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-19-17
Work Completed03-06-17
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
EASTER-SEALS CENTRAL TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161433
Totals26364.760.000.00100.0

CountyBURNET
HighwayUS0281
FromVARIOUS LOCATIONS
ToIN BURNET COUNTY
CSJ6322-84-001
Proj IDRMC - 632284001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001256024.00224163.0087.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-04-17
Contract Working Days48
Addl Days Granted0
Working Days Charged28
Percent Time Used58
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6322-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10171401
Totals256024.000.00224163.0087.5

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS
ToIN THE AUSTIN DISTRICT
CSJ6326-85-001
Proj IDRMC - 632685001
Work TypeREFLECTORIZED PAVEMENT MARKINGS/MARKERS
 
0.001263974.50253101.8895.8
Work Order00-00-00
Work Began06-01-18
Work Completed
Time Computed06-01-18
Contract Working Days520
Addl Days Granted0
Working Days Charged457
Percent Time Used87
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02181401
Totals263974.500.00253101.8895.8

CountyBURNET
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6327-08-001
Proj IDRMC - 632708001
Work TypeCRACK SEALING OF ASPHALT PAVEMENT
 
109.693138728.95138550.24100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-19
Work Completed02-26-19
Time Computed00-00-00
Contract Working Days48
Addl Days Granted0
Working Days Charged12
Percent Time Used25
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6327-08-001
FYL ENTERPRISES, LLC (100.00)
Contract #07181401
Totals138728.950.00138550.24100.0

CountyCALDWELL
HighwaySH0080
FromSH 80 AT CALLAHAN CREEK
ToSTR ID 14-028-0286-03-009
CSJ6327-11-001
Proj IDBPM - 632711001
Work TypeREPAIR BACKWALL
 
0.001160040.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days32
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JMT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6327-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11181403
Totals160040.000.000.000.0

CountyBURNET
HighwayUS0281
FromVARIOUS
ToVARIOUS
CSJ6327-20-001
Proj IDRMC - 632720001
Work TypeLITTER REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6327-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08181401
Totals0.000.000.000.0

CountyHAYS
HighwayIH0035
FromVARIOUS LOCATIONS IN HAYS COUNTY
To.
CSJ6327-36-001
Proj IDSUP - 632736001
Work TypeLITTER PICK UP AND REMOVAL
 
0.00129130.4026745.0091.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-26-18
Work Completed
Time Computed01-26-18
Contract Working Days22
Addl Days Granted120
Working Days Charged29
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6327-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171431
Totals29130.400.0026745.0091.8

CountyTRAVIS
HighwayUS0290
FromVARIOUS LOCATIONS IN TRAVIS
ToAND HAYS
CSJ6329-89-001
Proj IDSUP - 632989001
Work TypeLITTER PICK UP AND REMOVAL
 
0.001170340.00101813.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-18
Work Completed01-22-19
Time Computed04-01-18
Contract Working Days101
Addl Days Granted0
Working Days Charged66
Percent Time Used65
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6329-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03181432
Totals170340.000.00101813.00100.0

page 1 | page 2 | page 3 | page 4