Monthly State Let Construction Report For Beaumont District As Of Feb 14, 2020 Page 1 Of 3

Last Update: Friday, February 14, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY ETC
HighwayUS 90 ETC
From0.100 MI W OF SH 321
To0.103 MI E OF MAIN
CSJ0028-03-105
Proj IDSTP 2018(654)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.523965542.25841762.2287.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-18
Work Began07-09-19
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged116
Percent Time Used81
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-03-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183033
Totals965542.2537595.50841762.2287.1

CountyLIBERTY ETC
HighwayUS 90 ETC
FromAT LAYL DR
To0.1 MI E OF LAYL DR
CSJ0028-04-078
Proj IDSTP 2020(138)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.0501018096.50256987.3025.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began01-06-20
Work Completed
Time Computed00-00-00
Contract Working Days340
Addl Days Granted0
Working Days Charged13
Percent Time Used3
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0028-04-078
L&M INFRASTRUCTURE, LLC. (9.63)
Contract #10193218
Totals1018096.50194159.80256987.3025.2

CountyORANGE ETC
HighwayIH 10 ETC
FromJEFFERSON COUNTY LINE, EAST
To5.201 MI E OF JEFFERSON COUNTY LINE
CSJ0028-09-116
Proj IDIM 0108(181)
Work TypeSAFETY LIGHTING
 
18.56215083451.809123075.0660.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-09-18
Work Began03-18-19
Work Completed
Time Computed00-00-00
Contract Working Days300
Addl Days Granted0
Working Days Charged144
Percent Time Used48
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0028-09-116
SOUTH TEXAS ILLUMINATION, LLC (41.49)
AMERICAN REMEDIATION OPTIONS, INC. (1.79)
Contract #07183048
Totals15083451.80385362.849123075.0660.4

CountyORANGE
HighwayIH 10
FromAT LITTLE CYPRESS BAYOU
To(STR 002814069)AND(STR 002814068)
CSJ0028-14-100
Proj IDBR 2013(443)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1895064499.672366175.7646.7
CountyORANGE
HighwayIH 10
FromW OF ADAMS BAYOU, EAST
ToW OF SABINE RIVER BRIDGE
CSJ0028-14-108
Proj IDIM 0108(184)
Work TypeGR, STR, BS, PVMT, SIGN
 
3.66947282929.2532717178.0669.1
CountyORANGE
HighwayIH 10
FromAT SH 87 AND T&NO RR
To(STR 002814108 & 109)
CSJ0028-14-109
Proj IDBR 2013(226)
Work TypeGR, BS, PVMT & STR
 
0.32216093789.7820528611.9499.9
Work Order03-18-14
Work Began05-30-14
Work Completed
Time Computed04-03-14
Contract Working Days679
Addl Days Granted360
Working Days Charged872
Percent Time Used83
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0028-14-100
A-1 EROSION CONTROL, LLC (0.16)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.08)
AMERICAN REMEDIATION OPTIONS, INC. (0.16)
BORTUNCO (0.66)
DAVIS TREE EXPERTS (0.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.23)
MESA ROD BUSTERS, INC. (7.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.45)
SCOTT DERR PAINTING CO, LLC (0.05)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.80)
TRAF-TEX, INC. (0.97)
ROADWAY CONSTRUCTION, LLC (0.31)
C PAVE, INC. (0.01)
NORMAN HIGHWAY CONSTRUCTORS, INC. (0.46)
CRABTREE BARRICADE SYSTEMS, INC. (0.03)
JANCO (0.98)
ASHTON SAWING AND DRILLING LLC (0.05)
RAY"S THREADING AND FAB SHOP (0.71)
GULF COAST GROUTING, INC. (0.18)
Contract #02143032
Totals68441218.701120241.6555611965.7681.2

CountyJASPER ETC
HighwayUS 96 ETC
FromAT GOODE BRANCH
To(STR 201220006504012)
CSJ0065-04-079
Proj IDBR 2019(946)
Work TypeBRIDGE MAINTENANCE
 
1.5041098472.8991475.498.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-19
Work Began01-14-20
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged9
Percent Time Used11
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0065-04-079
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.32)
INTERSTATE BARRIER SAWING LLC (0.74)
ODUM SERVICES, LLC (28.30)
LONESTAR TRAFFIC SAFETY, LLC (0.75)
Contract #05193248
Totals1098472.8991475.4991475.498.3

CountyHARDIN
HighwayUS 96
FromVILLAGE CREEK BRIDGE
ToUS 69
CSJ0065-05-145
Proj IDC 65-5-145
Work TypeMILL AND OVERLAY EXISTING ROADWAY
 
4.8964178757.295494179.1699.9
CountyJEFFERSON
HighwayIH 10
FromWALDEN ROAD
To0.23 MILES WEST OF US 90
CSJ0739-02-164
Proj IDC 739-2-164
Work TypeMILL AND OVERLAY EXISTING ROADWAY
 
2.3372593474.6053544.432.0
Work Order08-15-18
Work Began02-16-19
Work Completed
Time Computed02-16-19
Contract Working Days124
Addl Days Granted71
Working Days Charged140
Percent Time Used71
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0065-05-145
CRABTREE BARRICADE SYSTEMS, INC. (5.56)
CPAVE, INC. (3.35)
DUSTROL, INC. (9.47)
Contract #07183027
Totals6772231.896680.325547723.5981.9

CountyJEFFERSON
HighwayUS 69
FromTRAM ROAD, SOUTH
ToLNVA CANAL
CSJ0065-07-062
Proj IDNH 2019(818)
Work TypeWiden Freeway
 
2.27921735071.856738713.7131.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began07-16-19
Work Completed
Time Computed00-00-00
Contract Working Days412
Addl Days Granted0
Working Days Charged112
Percent Time Used27
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0065-07-062
CEN TEX HYDROSEED, INC. (0.31)
CRABTREE BARRICADE SYSTEMS, INC. (1.15)
AREA WIDE PROTECTIVE, INC. (0.22)
CREATIVE PAVING CONCEPTS, LLC (1.20)
INTECH CONTRACTING LLC (2.99)
THIRD COAST SERVICES LLC (3.87)
J & M CONTRACTING, COMPANY (5.63)
JOHN REED AND COMPANY, LLC (18.03)
MESA ROD BUSTERS, INC. (0.17)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.60)
MIK INDUSTRIAL, LLC (0.69)
TEXAS CUTTING & CORING GP, INC. (0.30)
Contract #04193009
Totals21735071.85994013.786738713.7131.0

CountyLIBERTY
HighwayUS 59
FromSOUTH END OF CLEVELAND BYPASS
ToMONTGOMERY COUNTY LINE
CSJ0177-03-096
Proj IDNH 2012(594)
Work TypeGR, STR, BS, PVMT, SIGN, STRIPE
 
4.475100888506.7418583605.5818.4
CountyMONTGOMERY
HighwayIH 69
FromFOSTORIA ROAD, NORTH
ToLIBERTY COUNTY LINE
CSJ0177-05-113
Proj IDNH 2019(022)
Work TypeCONSTRUCT DETENTION POND
 
0.0811256328.4596346.947.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began05-01-19
Work Completed
Time Computed00-00-00
Contract Working Days736
Addl Days Granted0
Working Days Charged190
Percent Time Used25
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0177-03-096
PRIMATE CONSTRUCTION, LP (0.25)
ATS DRILLING, INC. (4.05)
CREACOM, INC. (3.80)
J. H. ODEN CONTRACTING COMPANY (0.40)
DUSTROL, INC. (0.57)
WILLOW CITY SIGN & RAIL, INC. (0.66)
SCR CIVIL CONSTRUCTION, LLC (0.03)
BOWMAN ENGINEERING & CONSULTING, INC. (7.58)
PMI PAVEMENT MARKING, LLC (0.93)
SMITH & COMPANY (3.82)
EUBANK EXCAVATION, L.L.C. (0.22)
MCNORTON DEWATERING, INC. (0.05)
Contract #09183201
Totals102144835.191887047.5218679952.5218.2

CountyLIBERTY
HighwayUS 59
FromSL 573 (SOUTH)
ToSL 573 (NORTH)
CSJ0177-03-103
Proj IDNH 2020(591)
Work TypeOVERLAY
 
3.6212133678.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days128
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-03-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02203213
Totals2133678.320.000.000.0

CountyLIBERTY
HighwayUS 59
FromSAN JACINTO C/L, SOUTH
ToSL 573
CSJ0177-03-104
Proj IDNH 2019(621)
Work TypeMILL, ACP, PFC
 
2.4811514862.401446246.4195.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began08-05-19
Work Completed
Time Computed00-00-00
Contract Working Days57
Addl Days Granted0
Working Days Charged41
Percent Time Used71
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-03-104
CPAVE, INC. (3.61)
WEST TEXAS ROCK RESOURCES, LLC (0.30)
BATTERSON,LLP (3.36)
Contract #03193228
Totals1514862.404900.001446246.4195.4

CountyJASPER
HighwayUS 69
FromANGELINA C/L
ToTYLER C/L
CSJ0200-04-024
Proj IDNH 2019(629)
Work TypeGR, BA, ACP
 
1.4341481134.601663759.0699.9
CountyTYLER
HighwayUS 69
FromJASPER C/L
ToFM 256
CSJ0200-05-048
Proj IDNH 2019(629)
Work TypeGR, BA, ACP
 
8.5463795908.043848781.3399.9
CountyTYLER
HighwayUS 69
FromFM 256
ToUS 190
CSJ0200-06-055
Proj IDNH 2019(629)
Work TypeGR, BA, ACP
 
9.4033568074.633944211.4299.9
Work Order03-25-19
Work Began08-07-19
Work Completed
Time Computed06-25-19
Contract Working Days105
Addl Days Granted0
Working Days Charged105
Percent Time Used100
Contractor(s)
HERITAGE ASPHALT COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0200-04-024
APEX HIGHWAY SERVICES, LLC (0.32)
CRABTREE BARRICADE SYSTEMS, INC. (0.26)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.98)
PMI PAVEMENT MARKING, LLC (2.87)
TEXOP CONSTRUCTION (0.98)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY (57.03)
Contract #02193208
Totals8845117.270.009456751.8199.9

CountyTYLER
HighwayUS 69
From0.68 MI SOUTH OF US 190
ToIVANHOE DR.
CSJ0200-07-054
Proj IDNH 2019(676)
Work TypeGR, BS, MILL , ACP, STRIPE
 
6.5583070400.303128749.3199.9
Work Order03-18-19
Work Began07-09-19
Work Completed
Time Computed07-09-19
Contract Working Days64
Addl Days Granted3
Working Days Charged47
Percent Time Used70
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-07-054
CRABTREE BARRICADE SYSTEMS, INC. (2.54)
TEXOP CONSTRUCTION (9.32)
WEST TEXAS ROCK RESOURCES, LLC (0.34)
Contract #02193034
Totals3070400.300.003128749.3199.9

CountyHARDIN
HighwayUS 69
FromFM 421, SOUTH
ToUS 96
CSJ0200-10-067
Proj IDNH 1802(598)
Work TypeGR, BS, STR, PVMT, SIGN
 
1.6491853959.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-10-067
BAY CITY TRAFFIC (1.79)
AMERICAN REMEDIATION OPTIONS, INC. (5.51)
CRABTREE BARRICADE SYSTEMS, INC. (2.08)
Contract #01193215
Totals1853959.540.000.000.0

CountyJEFFERSON
HighwayUS 69
FromLNVA CANAL, SOUTH
ToIH 10
CSJ0200-11-095
Proj IDNH 1802(412)
Work TypeGR, BS, STR, PVMT
 
3.62431528539.207682730.4124.3
Work Order08-15-18
Work Began10-14-18
Work Completed
Time Computed10-14-18
Contract Working Days652
Addl Days Granted36
Working Days Charged198
Percent Time Used28
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-11-095
HOUSTON SAWING & DRILLING (0.01)
APEX HIGHWAY SERVICES LLC (0.02)
DUSTROL, INC. (1.12)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (3.56)
CPAVE, INC. (0.69)
AMERICAN REMEDIATION OPTIONS, INC. (1.79)
NORMAN HIGHWAY CONSTRUCTORS, INC. (9.42)
WEBBER BARRIER SERVICES, LLC. (5.67)
W. W. FOUNDATION DRILLING, LTD. (1.61)
CRABTREE BARRICADE SYSTEMS, INC. (1.06)
(INACTIVE)MIRE TRUCKING & SERVICES (0.12)
HB FARMER FOUNDATION, LLC (1.61)
BREDA COMPANY, INC. (0.64)
Contract #07183004
Totals31528539.20162979.857682730.4124.3

CountyJEFFERSON
HighwayUS 69
From0.15 MI N OF SP 380, SOUTH
To0.20 MI S OF SH 347
CSJ0200-14-085
Proj IDBR 2018(658)
Work TypeREPAINT STRUCTURES WITH SPOT REPAIR
 
1.2118319407.207812192.3189.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-18
Work Began11-26-18
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged169
Percent Time Used90
Contractor(s)
CEKRA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-14-085
THE TRUESDELL CORPORATION (2.68)
(INACTIVE)OLDCASTLE MATERIALS TEXAS, INC. (29.40)
CRABTREE BARRICADE SYSTEMS, INC. (1.23)
DUSTROL, INC. (2.28)
Contract #06183248
Totals8319407.20100537.237812192.3189.9

CountyJEFFERSON
HighwayUS 69
From0.6 MI NORTH OF SPUR 93, SOUTH
ToSPUR 93 (NBFR)
CSJ0200-14-086
Proj IDSTP 2019(622)
Work TypeREMOVE CONC, GR, BS, CONC PAV
 
0.6002395589.661127381.7047.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began06-21-19
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted2
Working Days Charged93
Percent Time Used76
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-14-086
AMERICAN REMEDIATION OPTIONS, INC. (0.79)
CPAVE, INC. (0.47)
CRABTREE BARRICADE SYSTEMS, INC. (2.86)
DUSTROL, INC. (2.01)
NORMAN HIGHWAY CONSTRUCTORS, INC. (5.41)
BREDA COMPANY, INC. (1.50)
MID-COUNTY LAND CO., LTD. (2.57)
ANTIGO CONSTRUCTION, INC. (0.56)
Contract #03193223
Totals2395589.6692706.601127381.7047.0

CountyTYLER ETC
HighwayUS 190 ETC
FromPOLK COUNTY LINE, EAST
To0.14 MI W OF US 69
CSJ0213-06-044
Proj IDSTP 2020(020)
Work TypeSEAL COAT
 
205.41712309357.082446115.1419.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-09-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0213-06-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09193002
Totals12309357.08208700.682446115.1419.8

CountyNEWTON
HighwaySH 63
FromAT SABINE RIVER(BURRS FERRY)
To(STR_021404005)
CSJ0214-03-036
Proj IDBR 1802(764)
Work TypeRETROFIT BRIDGE BENTS
 
0.3562799157.503435589.2299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began11-14-18
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted25
Working Days Charged113
Percent Time Used93
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0214-03-036
AREA WIDE PROTECTIVE, INC. (0.15)
RUSSO CORPORATION (44.88)
BOWMAN ENGINEERING & CONSULTING, INC. (2.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (1.09)
Contract #08183058
Totals2799157.5037081.643435589.2299.9

CountyTYLER
HighwayUS 287
FromPOLK COUNTY LINE, EAST
ToN BEECH STREET
CSJ0341-04-070
Proj IDC 341-4-70
Work TypeACP, STRIPE
 
17.4575442445.865532195.8399.9
Work Order01-11-19
Work Began04-22-19
Work Completed
Time Computed04-22-19
Contract Working Days90
Addl Days Granted20
Working Days Charged104
Percent Time Used94
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0341-04-070
AMERICAN REMEDIATION OPTIONS, INC. (0.05)
AREA WIDE PROTECTIVE, INC. (0.09)
CHEROKEE SERVICES (0.50)
DUSTROL, INC. (8.85)
INTERSTATE BARRICADES & MARKINGS, INC. (0.18)
PAVEMENT MARKINGS INC. (1.94)
WEST TEXAS ROCK RESOURCES, LLC (0.38)
PMI PAVEMENT MARKING, LLC (1.94)
FREDONIA CONSTRUCTION SERVICES (0.01)
Contract #12183215
Totals5442445.860.005532195.8399.9

CountyCHAMBERS
HighwaySH 124
From4.O MI S OF FM 1941
ToINTRACOASTAL CANAL BRIDGE
CSJ0367-01-069
Proj IDNH 2019(803)
Work TypeGR,BS, STR, ACP, STFO
 
4.4251919055.952050092.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began07-22-19
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged59
Percent Time Used100
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0367-01-069
AMERICAN REMEDIATION OPTIONS, INC. (0.83)
CRABTREE BARRICADE SYSTEMS, INC. (8.81)
DUSTROL, INC. (0.50)
STRIPE-A-ZONE, INC. (0.92)
Contract #03193036
Totals1919055.95289327.902050092.0299.9