Monthly Local Let Maintenance Report For Beaumont District As Of Nov 12, 2021 Page 1 Of 7

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayFM0770
FromVARIOUS
ToVARIOUS
CSJ6186-01-001
Proj IDEMC - 618601001
Work TypeDEBRIS REMOVAL - LIBERTY CO EAST
 
1.000265644.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-20-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082009
Totals265644.180.000.000.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6186-02-001
Proj IDEMC - 618602001
Work Typeemergency debris removal
 
1.000152111.829764.496.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-18-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged13
Percent Time Used61
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082010
Totals152111.820.009764.496.4

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6192-82-001
Proj IDRMC - 619282001
Work TypeMOWING OF RIGHT OF WAY- BEAUMONT MAINT
 
161.000170270.30166250.9097.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-09
Work Began06-08-09
Work Completed
Time Computed06-12-09
Contract Working Days200
Addl Days Granted0
Working Days Charged81
Percent Time Used40
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092005
Totals170270.300.00166250.9097.6

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6207-02-001
Proj IDSUP - 620702001
Work TypeGROUNDS MAINTENANCE - JASPER
 
1.0005127.962144.1241.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102011
Totals5127.960.002144.1241.8

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-13-001
Proj IDSUP - 620713001
Work TypeJANITORIAL MAINTENANCE - WOODVILLE
 
1.0004032.004032.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102008
Totals4032.000.004032.0099.9

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 190
CSJ6207-14-001
Proj IDSUP - 620714001
Work TypePICNIC MAINTENANCE - WOODVILLE
 
1.00013440.619773.4372.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days364
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102009
Totals13440.610.009773.4372.7

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-15-001
Proj IDSUP - 620715001
Work TypeGROUNDS MAINTENANCE - WOODVILLE
 
1.0002911.401674.3657.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102010
Totals2911.400.001674.3657.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-45-001
Proj IDSUP - 620945001
Work TypeJANITORIAL MAINTENANCE - ANAHUAC
 
1.0004071.304013.2898.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged254
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6209-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102018
Totals4071.300.004013.2898.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-46-001
Proj IDSUP - 620946001
Work TypeGROUNDS MAINTENANCE - ANAHUAC
 
1.0008123.006965.7985.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102015
Totals8123.000.006965.7985.7

CountyLIBERTY
HighwayUS0090
FromVARIOUS LOCATIONS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6232-67-001
Proj IDRMC - 623267001
Work TypeCLEAN AND RESHAPE DITCHES
 
1.000163024.0054792.5550.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-02-12
Work Began07-02-12
Work Completed
Time Computed04-02-12
Contract Working Days51
Addl Days Granted0
Working Days Charged352
Percent Time Used690
Contractor(s)
PARTNER MARIA SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6232-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122002
Totals163024.000.0054792.5550.4

CountyJEFFERSON
HighwayUS0069
FromUS 69 N
ToUS 69 N
CSJ6237-81-001
Proj IDSUP - 623781001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.0006779.286136.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-12
Work Began02-01-12
Work Completed02-10-13
Time Computed02-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY
SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12112007
Totals6779.280.006136.20100.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6246-49-001
Proj IDSUP - 624649001
Work TypeLIBERTY ~ LITTER
 
1.000239756.04236236.2098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08122006
Totals239756.040.00236236.2098.5

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50381769.3694.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged724
Percent Time Used99
Contractor(s)
WORKQUEST
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.500.00381769.3694.6

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6336-15-001
Proj IDSUP - 633615001
Work TypeNEWTON LITTER
 
1.00065477.260.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-18
Work Began09-01-18
Work Completed09-01-19
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged211
Percent Time Used57
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6336-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09182005
Totals65477.260.000.00100.0

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6357-43-001
Proj IDSUP - 635743001
Work TypeNEWTON JANITORIAL
 
1.0008781.3611708.48100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-20
Work Completed02-01-21
Time Computed00-00-00
Contract Working Days365
Addl Days Granted10
Working Days Charged365
Percent Time Used97
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6357-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01202003
Totals8781.36731.7811708.48100.0

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6357-45-001
Proj IDSUP - 635745001
Work TypeWOODVILLE JANITORIAL
 
1.0009968.7613156.69100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-20
Work Began02-01-20
Work Completed10-27-21
Time Computed02-01-20
Contract Working Days365
Addl Days Granted10
Working Days Charged334
Percent Time Used89
Contractor(s)
WORKQUEST
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6357-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01202004
Totals9968.760.0013156.69100.0

CountyHARDIN
HighwayFM3513
FromVARIOUS LOCATIONS IN HARDIN AND
ToORANGE COUNTIES
CSJ6361-46-001
Proj IDRMC - 636146001
Work TypeMILL & OVERLAY
 
0.201223049.692347868.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-21
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted30
Working Days Charged40
Percent Time Used72
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6361-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09202002
Totals223049.6910218.552347868.6099.9

CountyORANGE
HighwayIH0010
FromVARIOUS LOCATIONS IN ORANGE,
ToHARDIN & JEFFERSON COUNTIES
CSJ6364-35-001
Proj IDBPM - 636435001
Work TypeRIPRAP/SCOUR/MISC BRIDGE REPAIR
 
0.001110744.00225546.1299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-16-21
Work Completed
Time Computed00-00-00
Contract Working Days37
Addl Days Granted0
Working Days Charged19
Percent Time Used51
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6364-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11202001
Totals110744.000.00225546.1299.9

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6365-45-001
Proj IDSUP - 636545001
Work TypeLARGE DEBRIS US 69 & SH 73
 
1.000505109.28347601.8068.8
Work Order06-01-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days365
Addl Days Granted365
Working Days Charged517
Percent Time Used70
Contractor(s)
WORKQUEST
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6365-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05202003
Totals505109.2819427.28347601.8068.8

CountyORANGE
HighwayIH0010
FromIH 10
ToIH 10
CSJ6365-46-001
Proj IDSUP - 636546001
Work TypeLARGE DEBRIS IH 10
 
1.000703840.80486717.0669.1
Work Order06-01-20
Work Began06-01-20
Work Completed
Time Computed06-01-20
Contract Working Days365
Addl Days Granted365
Working Days Charged518
Percent Time Used70
Contractor(s)
WORKQUEST
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6365-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05202002
Totals703840.8027070.80486717.0669.1

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7