Monthly Local Let Maintenance Report For Beaumont District As Of Sep 18, 2019 Page 1 Of 4

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayFM0770
FromVARIOUS
ToVARIOUS
CSJ6186-01-001
Proj IDEMC - 618601001
Work TypeDEBRIS REMOVAL - LIBERTY CO EAST
 
1.000265644.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-20-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082009
Totals265644.180.000.000.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6186-02-001
Proj IDEMC - 618602001
Work Typeemergency debris removal
 
1.000152111.829764.496.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-18-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged13
Percent Time Used61
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082010
Totals152111.820.009764.496.4

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6192-82-001
Proj IDRMC - 619282001
Work TypeMOWING OF RIGHT OF WAY- BEAUMONT MAINT
 
161.000170270.30166250.9097.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-09
Work Began06-08-09
Work Completed
Time Computed06-12-09
Contract Working Days200
Addl Days Granted0
Working Days Charged81
Percent Time Used40
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092005
Totals170270.300.00166250.9097.6

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6207-02-001
Proj IDSUP - 620702001
Work TypeGROUNDS MAINTENANCE - JASPER
 
1.0005127.962144.1241.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102011
Totals5127.960.002144.1241.8

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-13-001
Proj IDSUP - 620713001
Work TypeJANITORIAL MAINTENANCE - WOODVILLE
 
1.0004032.004032.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102008
Totals4032.000.004032.0099.9

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 190
CSJ6207-14-001
Proj IDSUP - 620714001
Work TypePICNIC MAINTENANCE - WOODVILLE
 
1.00013440.619773.4372.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days364
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102009
Totals13440.610.009773.4372.7

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-15-001
Proj IDSUP - 620715001
Work TypeGROUNDS MAINTENANCE - WOODVILLE
 
1.0002911.401674.3657.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102010
Totals2911.400.001674.3657.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-45-001
Proj IDSUP - 620945001
Work TypeJANITORIAL MAINTENANCE - ANAHUAC
 
1.0004071.304013.2898.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged254
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6209-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102018
Totals4071.300.004013.2898.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-46-001
Proj IDSUP - 620946001
Work TypeGROUNDS MAINTENANCE - ANAHUAC
 
1.0008123.006965.7985.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102015
Totals8123.000.006965.7985.7

CountyLIBERTY
HighwayUS0090
FromVARIOUS LOCATIONS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6232-67-001
Proj IDRMC - 623267001
Work TypeCLEAN AND RESHAPE DITCHES
 
1.000163024.0054792.5550.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-02-12
Work Began07-02-12
Work Completed
Time Computed04-02-12
Contract Working Days51
Addl Days Granted0
Working Days Charged352
Percent Time Used690
Contractor(s)
PARTNER MARIA SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6232-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122002
Totals163024.000.0054792.5550.4

CountyJEFFERSON
HighwayUS0069
FromUS 69 N
ToUS 69 N
CSJ6237-81-001
Proj IDSUP - 623781001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.0006779.286136.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-12
Work Began02-01-12
Work Completed02-10-13
Time Computed02-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY
SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12112007
Totals6779.280.006136.20100.0

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6239-62-001
Proj IDSUP - 623962001
Work TypeSABINE RIVER AUTH. WATER SEWER TESTING
 
1.0001116.601015.3090.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-12
Work Began02-01-12
Work Completed
Time Computed01-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged330
Percent Time Used90
Contractor(s)
SABINE RIVER AUTHORITY OF TEXAS
SUBCONTRACTOR(S) FOR CCSJ: 6239-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122005
Totals1116.600.001015.3090.9

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6246-49-001
Proj IDSUP - 624649001
Work TypeLIBERTY ~ LITTER
 
1.000239756.04236236.2098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08122006
Totals239756.040.00236236.2098.5

CountyCHAMBERS
HighwayFM0565
FromVARIOUS LOCATIONS IN CHAMBERS COUNTY
To.
CSJ6306-11-001
Proj IDRMC - 630611001
Work TypeFULL DEPTH FLEXIBLE PAVEMENT REPAIR
 
0.001192474.00860932.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-23-19
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted45
Working Days Charged29
Percent Time Used38
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6306-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01192002
Totals192474.00585137.00860932.5099.9

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50381769.3694.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged724
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.500.00381769.3694.6

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.00290070.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed02-15-19
Time Computed00-00-00
Contract Working Days150
Addl Days Granted30
Working Days Charged170
Percent Time Used94
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.000.00290070.00100.0

CountyCHAMBERS
HighwaySH0073
FromVARIOUS LOCATIONS IN CHAMBERS
ToAND LIBERTY COUNTIES
CSJ6311-75-001
Proj IDBPM - 631175001
Work TypeJOINT/CONCRETE REP/CLEAN&SEAL/RAIL UPGRA
 
1.000262770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172004
Totals262770.000.000.000.0

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6312-31-001
Proj IDRMC - 631231001
Work TypeBEAUMONT MAINTENANCE ROW MOWING
 
208.000338025.00323025.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed06-03-19
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged63
Percent Time Used40
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172003
Totals338025.000.00323025.00100.0

CountyJEFFERSON
HighwaySH0087
FromIH-10 AT FM364 AND
ToSH87 AT THE INTRACOASTAL CANAL BRIDGE
CSJ6321-09-001
Proj IDRMC - 632109001
Work TypeHAULING ROADWAY MATERIAL
 
0.001189150.002394.001.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6321-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172001
Totals189150.000.002394.001.2

CountyJEFFERSON
HighwaySH0087
FromVARIOUS LOCATIONS
ToALONG SH 87
CSJ6323-94-001
Proj IDEMC - 632394001
Work TypeEROSION REPAIR TO ROADWAY AND CANAL
 
3.10619225096.8011485558.4159.7
Work Order00-00-00
Work Began09-26-18
Work Completed
Time Computed09-26-18
Contract Working Days205
Addl Days Granted4
Working Days Charged189
Percent Time Used90
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-94-001
MASON CONSTRUCTION, LTD. (0.14)
NORMAN HIGHWAY CONSTRUCTORS, INC. (1.10)
CRABTREE BARRICADE SYSTEMS, INC. (0.04)
CAJUN BOY DIRT & EQUIPMENT, INC. (0.02)
Contract #10172004
Totals19225096.801671131.0511485558.4159.7

page 1 | page 2 | page 3 | page 4