Monthly Local Let Maintenance Report For Beaumont District As Of Oct 16, 2017 Page 2 Of 5

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6303-25-001
Proj IDSUP - 630325001
Work TypeNEWTON GROUNDS
 
1.00010422.148011.84100.0
Work Order10-01-16
Work Began00-00-00
Work Completed10-01-17
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162004
Totals10422.14964.128011.84100.0

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6303-26-001
Proj IDSUP - 630326001
Work TypeWOODVILLE GROUNDS
 
1.00010122.356820.15100.0
Work Order10-01-16
Work Began10-01-16
Work Completed10-01-17
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162003
Totals10122.35865.106820.15100.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToSH 73
CSJ6303-89-001
Proj IDSUP - 630389001
Work TypeLARGE DEBRIS - US 69 & SH 73
 
1.000460447.52296634.4664.4
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged487
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162003
Totals460447.5213282.13296634.4664.4

CountyJEFFERSON
HighwayIH0010
FromIH 10
ToIH 10
CSJ6303-90-001
Proj IDSUP - 630390001
Work TypeLARGE DEBRIS - IH 10
 
1.000641607.20408915.7263.7
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged487
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162004
Totals641607.2022427.22408915.7263.7

CountyLIBERTY
HighwayUS0059
FromUS 59
ToUS 59
CSJ6303-91-001
Proj IDSUP - 630391001
Work TypeLARGE DEBRIS - LIBERTY
 
1.00075483.2039919.0052.8
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged487
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162005
Totals75483.202177.4039919.0052.8

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6303-95-001
Proj IDSUP - 630395001
Work TypeORANGE JANITORIAL
 
1.0006889.896078.0088.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162007
Totals6889.890.006078.0088.2

CountyJASPER
HighwayUS0096
FromVARIOUS LOCATIONS IN JASPER
ToAND NEWTON COUNTIES
CSJ6305-53-001
Proj IDBPM - 630553001
Work TypeRIPRAP/SPALL & JOINT REPAIR
 
1.000200176.00185721.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-13-17
Work Completed08-14-17
Time Computed00-00-00
Contract Working Days22
Addl Days Granted3
Working Days Charged39
Percent Time Used156
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162001
Totals200176.000.00185721.00100.0

CountyHARDIN
HighwayUS0096
FromHARDIN COUNTY
ToHARDIN COUNTY
CSJ6306-44-001
Proj IDBPM - 630644001
Work TypeRIPRAP AND SCOUR REPAIRS
 
0.001244250.00225565.3392.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-17
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged42
Percent Time Used79
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172001
Totals244250.000.00225565.3392.3

CountyCHAMBERS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6306-50-001
Proj IDSUP - 630650001
Work TypeANAHUAC LITTER
 
1.000186599.18138002.19100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162007
Totals186599.180.00138002.19100.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6306-53-001
Proj IDSUP - 630653001
Work TypeLIBERTY LITTER
 
1.000263499.74243348.89100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162003
Totals263499.740.00243348.89100.0

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6306-55-001
Proj IDSUP - 630655001
Work TypeORANGE LITTER
 
1.00087470.3464960.55100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162004
Totals87470.340.0064960.55100.0

CountyLIBERTY
HighwayUS0059
FromUS 59 IN LIBERTY COUNTY
ToUS 59 IN LIBERTY COUNTY
CSJ6307-58-001
Proj IDRMC - 630758001
Work TypeOVERLAY OF EXISTING ROADWAYS
 
1.000192805.00386584.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-30-17
Work Completed07-10-17
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged23
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6307-58-001
REPUBLIC TRAFFIC SAFETY, INC. (3678.34)
Contract #12162001
Totals192805.000.00386584.88100.0

CountyJASPER
HighwayUS0096
FromVARIOUS ROADWAYS IN JASPER, TYLER
ToAND NEWTON CO.
CSJ6307-89-001
Proj IDRMC - 630789001
Work TypeUS 96 ETC., CRACK SEAL
 
90.01658000.7357411.41100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-09-17
Work Completed03-13-17
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged5
Percent Time Used33
Contractor(s)
AW&E CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162001
Totals58000.730.0057411.41100.0

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50199052.4349.3
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged359
Percent Time Used49
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.5014650.53199052.4349.3

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.00144396.8092.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged47
Percent Time Used31
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.000.00144396.8092.6

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-16-001
Proj IDSUP - 631116001
Work TypeDMV GROUNDS
 
1.0005217.003553.0068.1
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162002
Totals5217.00438.003553.0068.1

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6311-17-001
Proj IDSUP - 631117001
Work TypeORANGE GROUNDS MAINTENANCE
 
1.0008910.005940.0066.6
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162003
Totals8910.00990.005940.0066.6

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-18-001
Proj IDSUP - 631118001
Work TypeDISTRICT GROUNDS MAINTENANCE
 
1.00040571.0032519.0080.1
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162004
Totals40571.003899.0032519.0080.1

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6311-19-001
Proj IDSUP - 631119001
Work TypeWOODVILLE PICNIC MAINTENANCE
 
1.00038898.7033343.9085.7
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162005
Totals38898.703834.8033343.9085.7

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-20-001
Proj IDSUP - 631120001
Work TypeNEWTON PICNIC MAINTENANCE
 
1.00019211.9615522.4080.7
Work Order11-01-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162006
Totals19211.961910.2815522.4080.7