Monthly State Let Construction Report For Bryan District As Of May 10, 2022 Page 1 Of 3

Last Update: Monday, May 16, 2022
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.678712635.1199.9
Work Order05-14-19
Work Began11-25-19
Work Completed
Time Computed08-12-19
Contract Working Days93
Addl Days Granted5
Working Days Charged107
Percent Time Used109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
AREA WIDE PROTECTIVE, INC. (0.18)
CEN TEX HYDROSEED, INC. (0.18)
FORTSON CONTRACTING, INC. (2.81)
SCR CIVIL CONSTRUCTION, LLC (0.45)
STRIPE-A-ZONE, INC. (0.48)
TRP CONSTRUCTION GROUP, LLC (3.23)
POTTER TRUCKING (0.00)
VELASCO"S TRANSPORTS (0.00)
Contract #04193241
Totals7687390.670.008712635.1199.9

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.3210409730.4799.9
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.60749106.7471.5
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted50
Working Days Charged346
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.922300.0011158837.2199.9

CountyBRAZOS
HighwayBS 6-R
FromOLD HEARNE ROAD
To15TH STREET
CSJ0049-09-087
Proj IDC 49-9-87
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
4137992.910.000.0
Work Order01-20-22
Work Began00-00-00
Work Completed
Time Computed04-20-22
Contract Working Days151
Addl Days Granted0
Working Days Charged6
Percent Time Used3
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-087
BROCK CONSTRUCTION, LLC (0.24)
CEN TEX HYDROSEED, INC. (2.20)
CITYLYNX, INC. (24.49)
ELLIOTT CONSTRUCTION, LLC (8.01)
STRIPE LINES, INC. (2.58)
Contract #12213210
Totals4137992.910.000.000.0

CountyBRAZOS
HighwayBS 6-R
FromSH 6 N
ToSH 21
CSJ0049-09-088
Proj IDF 2022(058)
Work TypeSEAL COAT
 
847125.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-15-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days11
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-088
INTERSTATE BARRICADES & MARKINGS, INC. (7.49)
Contract #10213014
Totals847125.270.000.000.0

CountyBRAZOS
HighwayUS 190
FromSH OSR
ToFM 2818
CSJ0049-09-090
Proj IDSTP 2022(235)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
490974.560.000.0
CountyBRAZOS
HighwaySH 6
FromFM 159
ToGRIMES COUNTY LINE
CSJ0050-02-119
Proj IDSTP 2022(235)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001957152.340.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-15-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days111
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01223016
Totals1448126.900.000.000.0

CountyBRAZOS ETC
HighwaySH 6 ETC
FromAT DRAW ON EFR AND WFR
To.
CSJ0049-12-105
Proj IDBR 2020(085)
Work TypeBRIDGE MAINTENANCE
 
1.4911471134.301657293.0499.9
Work Order11-20-19
Work Began03-10-20
Work Completed
Time Computed02-18-20
Contract Working Days152
Addl Days Granted25
Working Days Charged150
Percent Time Used84
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-105
FLASHER EQUIPMENT COMPANY (1.36)
BLACKTOP INDUSTRIES LLC (18.12)
DUSTROL, INC. (0.46)
MOBILE ENTERPRISES, INC. (5.93)
STRIPE LINES, INC. (0.00)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.93)
WILLOW CITY SIGN & RAIL, INC. (1.13)
Contract #10193020
Totals1471134.300.001657293.0499.9

CountyBRAZOS
HighwaySH 6
FromOLD RELIANCE ROAD
ToFM 158 (BOONVILLE ROAD)
CSJ0049-12-115
Proj IDSTP 2019(461)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.4001105702.151180743.7399.9
Work Order10-09-19
Work Began12-06-19
Work Completed
Time Computed11-08-19
Contract Working Days126
Addl Days Granted15
Working Days Charged151
Percent Time Used107
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-115
CEN TEX HYDROSEED, INC. (3.37)
GLENN FUQUA, INC. (5.38)
AREA WIDE PROTECTIVE, INC. (1.12)
STEEL EFFECTS (0.00)
LONE STAR PRODUCTS (WICHITA FALLS) (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.83)
BRITTEN HYDROSEEDING (0.37)
Contract #08193032
Totals1105702.1593.281180743.7399.9

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-014
Proj IDF 2021(768)
Work TypeTRAFFIC CONTROL DEVICES
 
16.2762552415.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04223014
Totals2552415.920.000.000.0

CountyROBERTSON ETC
HighwaySH 14 ETC
FromFM 46
ToSH 6
CSJ0049-15-014
Proj IDF 2022(080)
Work TypeSEAL COAT
 
4.82714704110.352629982.9217.8
Work Order12-30-21
Work Began04-18-22
Work Completed
Time Computed04-18-22
Contract Working Days122
Addl Days Granted0
Working Days Charged10
Percent Time Used8
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213001
Totals14704110.35742420.212629982.9217.8

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromAT WALTON DRIVE/NEW MAIN DRIVE
To.WA
CSJ0050-01-087
Proj IDSTP 2021(024)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6001136623.60809343.1571.5
Work Order11-19-20
Work Began04-20-21
Work Completed
Time Computed02-17-21
Contract Working Days158
Addl Days Granted0
Working Days Charged164
Percent Time Used103
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-087
AREA WIDE PROTECTIVE, INC. (1.66)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.47)
LINEAR TRAFFIC MARKINGS LLC (0.48)
PALOMARES CONSTRUCTION, INC. (1.40)
A. L. HELMCAMP, INC. (8.13)
Contract #10203019
Totals1136623.6027770.68809343.1571.5

CountyGRIMES
HighwaySH 6
FromAT FM 2
To.
CSJ0050-03-096
Proj IDSTP 2021(770)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.40018052622.002711836.4815.0
Work Order09-16-21
Work Began11-01-21
Work Completed
Time Computed11-01-21
Contract Working Days579
Addl Days Granted0
Working Days Charged29
Percent Time Used5
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.47)
DIIBS SPECIALISTS, LLC (0.86)
JB PINNACLE GROUP, LLC (0.99)
PINNACLE GRINDING AND GROOVING LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
D. I. J. CONSTRUCTION, INC. (1.08)
LONESTAR TRAFFIC SAFETY, LLC (0.30)
TEXAS STERLING CONSTRUCTION CO. (3.19)
TORO BRAVO CONSTRUCTION, LLC (0.32)
Contract #08213005
Totals18052622.0085844.612711836.4815.0

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.916202557.0799.9
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted54
Working Days Charged115
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.9123625.006202557.0799.9

CountyGRIMES ETC
HighwaySH 6 ETC
FromAT FM 1227
To.
CSJ0050-03-107
Proj IDSTP 2B20(204)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.100990316.51925475.9293.4
Work Order10-21-20
Work Began04-13-21
Work Completed
Time Computed01-19-21
Contract Working Days171
Addl Days Granted0
Working Days Charged90
Percent Time Used52
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-107
LONESTAR TRAFFIC SAFETY, LLC (1.15)
PINNACLE GRINDING AND GROOVING LLC (0.32)
CEN TEX HYDROSEED, INC. (1.36)
STRIPE LINES, INC. (0.74)
BRAZOS PAVING, INC. (17.65)
Contract #09203024
Totals990316.5193.24925475.9293.4

CountyWALKER
HighwaySH 75
FromAT 2793
To.
CSJ0110-01-049
Proj IDF 2021(717)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200946421.73245782.7025.9
Work Order09-29-21
Work Began12-16-21
Work Completed
Time Computed12-16-21
Contract Working Days47
Addl Days Granted0
Working Days Charged28
Percent Time Used59
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049
STRIPE LINES, INC. (5.65)
CEN TEX HYDROSEED, INC. (2.93)
COLD CREEK CONSTRUCTION, LTD (3.92)
J & M CONTRACTING, COMPANY (4.05)
AREA WIDE PROTECTIVE, INC. (1.90)
Contract #07213042
Totals946421.730.00245782.7025.9

CountyWASHINGTON
HighwayBU 290F
FromBS 36-J
ToMARKET STREET
CSJ0114-09-077
Proj IDSTP 2B20(105)
Work TypeOVERLAY
 
2.6392697457.952411838.6389.4
Work Order11-19-20
Work Began02-08-21
Work Completed
Time Computed02-08-21
Contract Working Days108
Addl Days Granted27
Working Days Charged71
Percent Time Used52
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-077
CITYLYNX, INC. (3.60)
CEN TEX HYDROSEED, INC. (0.09)
A BROTHERS MILLING, LLC (5.83)
STRIPE LINES, INC. (3.43)
WILLOW CITY SIGN & RAIL, INC. (1.69)
Contract #08203030
Totals2697457.9570692.842411838.6389.4

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 390
To0.1 MI E OF FM 2679
CSJ0114-09-089
Proj IDF 2021(776)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.6001254827.8085569.006.8
Work Order09-21-21
Work Began00-00-00
Work Completed
Time Computed12-20-21
Contract Working Days199
Addl Days Granted0
Working Days Charged19
Percent Time Used9
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213250
Totals1254827.800.0085569.006.8

CountyBURLESON
HighwaySH 21
FromAT FM 2000
To.
CSJ0116-03-066
Proj IDF 2022(488)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2941282.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days133
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0116-03-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05223225
Totals2941282.430.000.000.0

CountyBRAZOS
HighwaySH 21
FromAT SIMS AVE.
To.
CSJ0116-04-104
Proj IDSTP 2020(787)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200263629.50274426.1299.9
Work Order07-20-20
Work Began12-11-20
Work Completed
Time Computed10-19-20
Contract Working Days68
Addl Days Granted5
Working Days Charged71
Percent Time Used97
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-104
AREA WIDE PROTECTIVE, INC. (1.50)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.57)
LINEAR TRAFFIC MARKINGS LLC (3.99)
PALOMARES CONSTRUCTION, INC. (6.67)
Contract #05203231
Totals263629.500.00274426.1299.9

CountyFREESTONE
HighwaySH 75
FromCR 490
ToLEON CO. LINE
CSJ0166-03-033
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2277381.402737771.8899.9
CountyGRIMES
HighwaySH 90
From0.50 MILES N. OF FM 149
To0.15 MILES S OF CR 444
CSJ0315-03-062
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.109807796.26879199.0599.9
CountyBRAZOS
HighwayFM 1687
FromFM 50
ToSH 21
CSJ1560-01-038
Proj IDSTP 2020(951)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.7331006627.54964271.3295.7
Work Order08-20-20
Work Began01-04-21
Work Completed
Time Computed11-18-20
Contract Working Days259
Addl Days Granted0
Working Days Charged246
Percent Time Used94
Contractor(s)
BEAR CREEK CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0166-03-033
MOBILE ENTERPRISES, INC. (2.18)
D. I. J. CONSTRUCTION, INC. (0.00)
DALLAS LITE AND BARRICADE, INC. (0.00)
DOUBLE OAK EROSION, INC. (0.00)
FORTSON CONTRACTING, INC. (0.00)
J & M CONTRACTING, COMPANY (0.00)
Contract #07203016
Totals4091805.20222736.554581242.2599.9

CountyMILAM
HighwayFM 845
FromUS 190
ToSOUTH KARNES AVENUE
CSJ0185-06-010
Proj IDC 185-6-10
Work TypeREHABILITATION OF EXISTING ROAD
 
1.9313591284.130.000.0
CountyMILAM
HighwayFM 845
FromSOUTH KARNES AVENUE
ToFM 1600
CSJ0185-06-012
Proj IDF 2022(253)
Work TypeOVERLAY
 
391142.140.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days165
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAZOS PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0185-06-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01223208
Totals3982426.270.000.000.0

page 1 | page 2 | page 3