Monthly State Let Construction Report For Bryan District As Of Nov 12, 2021 Page 1 Of 4

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.678496868.0899.9
Work Order05-14-19
Work Began11-25-19
Work Completed
Time Computed08-12-19
Contract Working Days93
Addl Days Granted5
Working Days Charged107
Percent Time Used109
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
AREA WIDE PROTECTIVE, INC. (0.18)
CEN TEX HYDROSEED, INC. (0.18)
FORTSON CONTRACTING, INC. (2.81)
SCR CIVIL CONSTRUCTION, LLC (0.45)
STRIPE-A-ZONE, INC. (0.48)
TRP CONSTRUCTION GROUP, LLC (3.23)
POTTER TRUCKING (0.00)
VELASCO"S TRANSPORTS (0.00)
Contract #04193241
Totals7687390.670.008496868.0899.9

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.3210259126.7299.9
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.60739225.3470.6
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted50
Working Days Charged346
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.926059.2610998352.0699.9

CountyBRAZOS
HighwayBS 6-R
FromSH 6 N
ToSH 21
CSJ0049-09-088
Proj IDF 2022(058)
Work TypeSEAL COAT
 
847125.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days11
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213014
Totals847125.270.000.000.0

CountyBRAZOS ETC
HighwaySH 6 ETC
FromAT DRAW ON EFR AND WFR
To.
CSJ0049-12-105
Proj IDBR 2020(085)
Work TypeBRIDGE MAINTENANCE
 
1.4911471134.301606058.1499.9
Work Order11-20-19
Work Began03-10-20
Work Completed
Time Computed02-18-20
Contract Working Days152
Addl Days Granted25
Working Days Charged135
Percent Time Used76
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-105
FLASHER EQUIPMENT COMPANY (1.36)
BLACKTOP INDUSTRIES LLC (18.12)
DUSTROL, INC. (0.46)
MOBILE ENTERPRISES, INC. (5.93)
STRIPE LINES, INC. (0.00)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.93)
WILLOW CITY SIGN & RAIL, INC. (1.13)
Contract #10193020
Totals1471134.30187384.351606058.1499.9

CountyBRAZOS
HighwaySH 6
FromOLD RELIANCE ROAD
ToFM 158 (BOONVILLE ROAD)
CSJ0049-12-115
Proj IDSTP 2019(461)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.4001105702.151144606.1399.9
Work Order10-09-19
Work Began12-06-19
Work Completed
Time Computed11-08-19
Contract Working Days126
Addl Days Granted0
Working Days Charged144
Percent Time Used114
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-115
CEN TEX HYDROSEED, INC. (3.37)
GLENN FUQUA, INC. (5.38)
AREA WIDE PROTECTIVE, INC. (1.12)
STEEL EFFECTS (0.00)
LONE STAR PRODUCTS (WICHITA FALLS) (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.83)
BRITTEN HYDROSEEDING (0.37)
Contract #08193032
Totals1105702.150.001144606.1399.9

CountyROBERTSON
HighwayFM 46
FromFALLS CO LINE
ToSH 14
CSJ0049-14-011
Proj IDSTP 1702(019)HESG
Work TypePROFILE EDGELINE & CENTERLINE MARKS
 
31.278318695.30248947.0078.1
CountyROBERTSON
HighwayFM 46
FromTHE FALLS COUNTY LINE
ToSH 14
CSJ0049-14-012
Proj IDSTP 2019(497)
Work TypeGRDG,WDN,STRCS,BASE,SURF,SGNS,MRKGS
 
1.3701404401.281476318.0999.9
CountyZERO COUNTIES
Highway
From
To
CSJ0205-02-066
Proj ID
Work Type
 
0.00570411.340.0
Work Order03-18-19
Work Began06-27-19
Work Completed
Time Computed06-16-19
Contract Working Days93
Addl Days Granted0
Working Days Charged91
Percent Time Used97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-011
AREA WIDE PROTECTIVE, INC. (1.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.26)
BEAR CREEK CONSTRUCTION, LLC (22.30)
BROCK CONSTRUCTION, LLC (1.35)
CEN TEX HYDROSEED, INC. (2.34)
STRIPE-A-ZONE, INC. (17.79)
COMEN ENTERPRISE LLC (2.71)
LS HIGHWAY PRODUCTS, INC. (0.00)
D. I. J. CONSTRUCTION, INC. (0.00)
Contract #02193019
Totals1723096.580.002295676.4399.9

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-013
Proj IDSTP 2021(066)
Work TypeSEAL COAT
 
16.2769071397.849046939.9899.7
Work Order03-18-21
Work Began04-26-21
Work Completed
Time Computed05-01-21
Contract Working Days112
Addl Days Granted0
Working Days Charged92
Percent Time Used82
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-013
BRYDL CONTRACTING, INC. (0.98)
INTERSTATE BARRICADES & MARKINGS, INC. (1.82)
Contract #10203006
Totals9071397.8453050.009046939.9899.7

CountyROBERTSON ETC
HighwayFM 46 ETC
FromFALLS COUNTY LINE
ToSH 14
CSJ0049-14-014
Proj IDF 2021(768)
Work TypeTRAFFIC CONTROL DEVICES
 
16.2761534451.130.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213244
Totals1534451.130.000.000.0

CountyROBERTSON ETC
HighwaySH 14 ETC
FromFM 46
ToSH 6
CSJ0049-15-014
Proj IDF 2022(080)
Work TypeSEAL COAT
 
4.82714704110.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days122
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-15-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213001
Totals14704110.350.000.000.0

CountyBRAZOS ETC
HighwayBS 6-R ETC
FromAT WALTON DRIVE/NEW MAIN DRIVE
To.WA
CSJ0050-01-087
Proj IDSTP 2021(024)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6001136623.60678564.3059.7
Work Order11-19-20
Work Began04-20-21
Work Completed
Time Computed02-17-21
Contract Working Days158
Addl Days Granted0
Working Days Charged126
Percent Time Used79
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-087
AREA WIDE PROTECTIVE, INC. (1.66)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (3.47)
LINEAR TRAFFIC MARKINGS LLC (0.48)
PALOMARES CONSTRUCTION, INC. (1.40)
A. L. HELMCAMP, INC. (8.13)
Contract #10203019
Totals1136623.60208702.15678564.3059.7

CountyBRAZOS ETC
HighwaySH 6 ETC
FromSH 6EFR @ SH 40
To.5 MI N OF GRIMES COUNTY LINE
CSJ0050-02-113
Proj IDNH 2021(060)
Work TypeTRAFFIC CONTROL DEVICES
 
222.3482655543.382683765.6099.9
Work Order02-03-21
Work Began03-22-21
Work Completed
Time Computed03-05-21
Contract Working Days64
Addl Days Granted0
Working Days Charged62
Percent Time Used96
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-02-113
BRYDL CONTRACTING, INC. (1.24)
Contract #09203033
Totals2655543.380.002683765.6099.9

CountyGRIMES
HighwaySH 6
FromAT FM 2
To.
CSJ0050-03-096
Proj IDSTP 2021(770)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.40018052622.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began11-01-21
Work Completed
Time Computed00-00-00
Contract Working Days579
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (1.47)
DIIBS SPECIALISTS, LLC (0.86)
JB PINNACLE GROUP, LLC (0.99)
PINNACLE GRINDING AND GROOVING LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.23)
D. I. J. CONSTRUCTION, INC. (1.08)
LONESTAR TRAFFIC SAFETY, LLC (0.30)
TEXAS STERLING CONSTRUCTION CO. (3.19)
TORO BRAVO CONSTRUCTION, LLC (0.32)
Contract #08213005
Totals18052622.000.000.000.0

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.916031857.4699.9
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted22
Working Days Charged115
Percent Time Used122
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.910.006031857.4699.9

CountyGRIMES ETC
HighwaySH 6 ETC
FromAT FM 1227
To.
CSJ0050-03-107
Proj IDSTP 2B20(204)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.100990316.51852528.0686.0
Work Order10-21-20
Work Began04-13-21
Work Completed
Time Computed01-19-21
Contract Working Days171
Addl Days Granted0
Working Days Charged87
Percent Time Used50
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-107
LONESTAR TRAFFIC SAFETY, LLC (1.15)
PINNACLE GRINDING AND GROOVING LLC (0.32)
CEN TEX HYDROSEED, INC. (1.36)
STRIPE LINES, INC. (0.74)
BRAZOS PAVING, INC. (17.65)
Contract #09203024
Totals990316.5113730.40852528.0686.0

CountyFREESTONE ETC
HighwayUS 84 ETC
FromIH 45
ToSH 75
CSJ0057-03-042
Proj IDC 57-3-42
Work TypeASPHALT RUBBER SEAL
 
187.92113798219.6613998074.8399.9
Work Order03-25-19
Work Began09-04-19
Work Completed
Time Computed07-01-19
Contract Working Days82
Addl Days Granted0
Working Days Charged82
Percent Time Used100
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-042
INTERSTATE BARRICADES & MARKINGS, INC. (10.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.05)
BRYDL CONTRACTING, INC. (0.55)
Contract #01193003
Totals13798219.661099.0013998074.8399.9

CountyWALKER
HighwaySH 75
FromAT 2793
To.
CSJ0110-01-049
Proj IDF 2021(717)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200946421.730.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-29-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days47
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-049
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07213042
Totals946421.730.000.000.0

CountyWASHINGTON
HighwayBU 290F
FromBS 36-J
ToMARKET STREET
CSJ0114-09-077
Proj IDSTP 2B20(105)
Work TypeOVERLAY
 
2.6392697457.95603805.8022.3
Work Order11-19-20
Work Began02-08-21
Work Completed
Time Computed02-08-21
Contract Working Days108
Addl Days Granted15
Working Days Charged17
Percent Time Used13
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-077
CITYLYNX, INC. (3.60)
CEN TEX HYDROSEED, INC. (0.09)
A BROTHERS MILLING, LLC (5.83)
STRIPE LINES, INC. (3.43)
WILLOW CITY SIGN & RAIL, INC. (1.69)
Contract #08203030
Totals2697457.95243429.30603805.8022.3

CountyWASHINGTON ETC
HighwayUS 290 ETC
FromAT SS 125
To.
CSJ0114-09-078
Proj IDSTP 2020(798)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.800584899.11586801.7799.9
Work Order07-07-20
Work Began08-10-20
Work Completed
Time Computed08-06-20
Contract Working Days188
Addl Days Granted0
Working Days Charged162
Percent Time Used86
Contractor(s)
ALLSTATE SIGNAL & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-078
STRIPE LINES, INC. (3.31)
Contract #05203229
Totals584899.110.00586801.7799.9

CountyWASHINGTON ETC
HighwayUS 290 ETC
From0.1 MI W OF FM 390
To0.1 MI E OF FM 2679
CSJ0114-09-089
Proj IDF 2021(776)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.6001254827.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-21-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days199
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CITYLYNX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213250
Totals1254827.800.000.000.0

CountyBRAZOS
HighwaySH 21
FromAT SIMS AVE.
To.
CSJ0116-04-104
Proj IDSTP 2020(787)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200263629.50269922.7899.9
Work Order07-20-20
Work Began12-11-20
Work Completed
Time Computed10-19-20
Contract Working Days68
Addl Days Granted5
Working Days Charged71
Percent Time Used97
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-104
AREA WIDE PROTECTIVE, INC. (1.50)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (2.57)
LINEAR TRAFFIC MARKINGS LLC (3.99)
PALOMARES CONSTRUCTION, INC. (6.67)
Contract #05203231
Totals263629.500.00269922.7899.9

page 1 | page 2 | page 3 | page 4