Monthly State Let Construction Report For Bryan District As Of Aug 23, 2019 Page 1 Of 3

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON ETC
HighwaySH 6 ETC
From0.6 MILES NORTH OF FM 979
To0.35 MILES SOUTH OF FM 1644 WEST
CSJ0049-06-078
Proj IDNH 2018(395)
Work TypeASPHALT RUBBER SEAL
 
31.2892287795.202680472.2999.9
Work Order02-26-18
Work Began05-07-18
Work Completed
Time Computed05-07-18
Contract Working Days53
Addl Days Granted3
Working Days Charged42
Percent Time Used75
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-078
INTERSTATE BARRICADES & MARKINGS, INC. (10.45)
Contract #01183227
Totals2287795.200.002680472.2999.9

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.670.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days93
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193241
Totals7687390.670.000.000.0

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.322309911.2831.9
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.600.000.0
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted50
Working Days Charged78
Percent Time Used22
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.92358343.342309911.2827.8

CountyBRAZOS ETC
HighwaySH 6 ETC
FromSH 6 WFR @ OSR
ToFM 2818
CSJ0049-09-078
Proj IDNH 2019(100)
Work TypeSEAL COAT
 
254.98410186765.856115990.4060.0
Work Order11-15-18
Work Began07-08-19
Work Completed
Time Computed05-20-19
Contract Working Days128
Addl Days Granted0
Working Days Charged41
Percent Time Used32
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-078
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
STRIPE-A-ZONE, INC. (25.98)
BRYDL CONTRACTING, INC. (0.67)
Contract #10183013
Totals10186765.854370620.266115990.4060.0

CountyBRAZOS
HighwayUS 190
FromAT FM 2818
To.
CSJ0049-09-079
Proj IDSTP 1802(486)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200388060.00342075.0088.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-18
Work Began01-21-19
Work Completed
Time Computed12-18-18
Contract Working Days52
Addl Days Granted0
Working Days Charged50
Percent Time Used96
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-079
AREA WIDE PROTECTIVE, INC. (1.56)
Contract #08183241
Totals388060.000.00342075.0088.1

CountyBRAZOS
HighwaySH 6
FromSH 21
ToFM 158
CSJ0049-12-096
Proj IDNH 1502(234)
Work TypeUPGRADE FREEWAY RAMPS
 
2.4597542870.377384376.2997.8
CountyZERO COUNTIES
Highway
From
To
CSJ0049-12-111
Proj ID
Work Type
 
0.00726261.700.0
Work Order08-20-15
Work Began02-29-16
Work Completed
Time Computed02-17-16
Contract Working Days308
Addl Days Granted135
Working Days Charged419
Percent Time Used94
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.25)
A BROTHERS MILLING, LLC (1.71)
CEN TEX HYDROSEED, INC. (4.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.58)
WILLOW CITY SIGN & RAIL, INC. (4.34)
COWBELL TRAFFIC SERVICES, INC. (0.16)
BEAR CREEK CONSTRUCTION, LLC (0.37)
AREA WIDE PROTECTIVE, INC. (0.53)
AARON CONCRETE CONTRACTORS, L.P. (0.61)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
Contract #06153011
Totals7542870.37224291.438110637.9999.9

CountyBRAZOS
HighwaySH 6
FromOLD RELIANCE ROAD
ToFM 158 (BOONVILLE ROAD)
CSJ0049-12-115
Proj IDSTP 2019(461)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.4001105702.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days126
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-115
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193032
Totals1105702.150.000.000.0

CountyROBERTSON
HighwayFM 46
FromFALLS CO LINE
ToSH 14
CSJ0049-14-011
Proj IDSTP 1702(019)HESG
Work TypePROFILE EDGELINE & CENTERLINE MARKS
 
31.278318695.300.000.0
CountyROBERTSON
HighwayFM 46
FromTHE FALLS COUNTY LINE
ToSH 14
CSJ0049-14-012
Proj IDSTP 2019(497)
Work TypeGRDG,WDN,STRCS,BASE,SURF,SGNS,MRKGS
 
1.3701404401.28297675.2521.1
Work Order03-18-19
Work Began06-27-19
Work Completed
Time Computed06-16-19
Contract Working Days93
Addl Days Granted0
Working Days Charged21
Percent Time Used22
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-011
AREA WIDE PROTECTIVE, INC. (1.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.26)
BEAR CREEK CONSTRUCTION, LLC (22.30)
BROCK CONSTRUCTION, LLC (1.35)
CEN TEX HYDROSEED, INC. (2.34)
STRIPE-A-ZONE, INC. (17.79)
COMEN ENTERPRISE LLC (2.71)
Contract #02193019
Totals1723096.58297675.25297675.2517.2

CountyBRAZOS
HighwayBS 6-R ETC
FromON BS 6-R
ToAT THE INTERSECTION WITH 29TH ST
CSJ0050-01-079
Proj IDSTP 2017(914)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
2.6411474037.571560044.6799.9
Work Order06-26-17
Work Began11-27-17
Work Completed
Time Computed09-22-17
Contract Working Days190
Addl Days Granted28
Working Days Charged199
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-079
STRIPE LINES, INC. (4.71)
TRAF-TEX, INC. (48.61)
AREA WIDE PROTECTIVE, INC. (0.68)
Contract #04173004
Totals1474037.5718656.301560044.6799.9

CountyBRAZOS
HighwayBS 6-R
FromFM 2818
To0.7 MILES SOUTH OF FM 2818
CSJ0050-01-080
Proj IDSTP 1802(407)HES
Work TypeINSTALL RAISED MEDIAN
 
1.5301137292.261226407.8399.9
Work Order08-17-18
Work Began10-19-18
Work Completed
Time Computed10-16-18
Contract Working Days79
Addl Days Granted7
Working Days Charged62
Percent Time Used72
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-080
AREA WIDE PROTECTIVE, INC. (0.90)
CEN TEX HYDROSEED, INC. (1.26)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (18.96)
SPEEDY PAVING (2.86)
STRIPE LINES, INC. (3.11)
HOUSLEY COMMUNICATIONS, INC. (1.60)
PROPERTY CARETAKERS CORPORATION (0.49)
Contract #07183216
Totals1137292.2611034.551226407.8399.9

CountyBRAZOS
HighwayBS 6-R
From0.05 MILES NORTH OF FM 2347
To0.05 MILES SOUTH OF FM 2818
CSJ0050-01-086
Proj IDNH 2019(681)
Work TypeCONCRETE PAVEMENT REPAIR
 
3.2235989654.525937649.4594.9
Work Order04-25-19
Work Began05-28-19
Work Completed
Time Computed05-25-19
Contract Working Days80
Addl Days Granted0
Working Days Charged48
Percent Time Used60
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-086
AGGREGATE TECHNOLOGIES, INC. (3.54)
ANGEL BROTHERS ENTERPRISES, LTD. (6.64)
STRIPE LINES, INC. (2.92)
TEXAS CUTTING & CORING GP, INC. (0.26)
Contract #03193240
Totals5989654.522557777.755937649.4594.9

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.910.000.0
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted0
Working Days Charged26
Percent Time Used36
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.910.000.000.0

CountyFREESTONE ETC
HighwayBU 84-R ETC
FromUS 84
ToSH 179
CSJ0057-02-037
Proj IDSTP 2018(232)
Work TypeSEAL COAT
 
385.07412525077.0015668053.0299.9
Work Order12-04-17
Work Began05-14-18
Work Completed
Time Computed05-01-18
Contract Working Days75
Addl Days Granted141
Working Days Charged152
Percent Time Used70
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-02-037
D. I. J. CONSTRUCTION, INC. (17.61)
BRYDL CONTRACTING, INC. (0.81)
Contract #10173003
Totals12525077.000.0015668053.0299.9

CountyFREESTONE ETC
HighwayUS 84 ETC
FromBU 84-R
ToIH 45
CSJ0057-03-041
Proj IDSTP 2019(496)HES
Work TypePROFILE EDGELINE MARKINGS
 
179.5411651842.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days62
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-041
AREA WIDE PROTECTIVE, INC. (0.10)
SURFACE PREPARATION TECHNOLOGIES, LLC (4.37)
BRYDL CONTRACTING, INC. (4.50)
Contract #02193221
Totals1651842.000.000.000.0

CountyFREESTONE ETC
HighwayUS 84 ETC
FromIH 45
ToSH 75
CSJ0057-03-042
Proj IDC 57-3-42
Work TypeASPHALT RUBBER SEAL
 
187.92113798219.66228291.861.6
Work Order03-25-19
Work Began00-00-00
Work Completed
Time Computed07-01-19
Contract Working Days82
Addl Days Granted0
Working Days Charged20
Percent Time Used24
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-042
INTERSTATE BARRICADES & MARKINGS, INC. (10.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.05)
Contract #01193003
Totals13798219.66228291.86228291.861.6

CountyFREESTONE
HighwayUS 84
FromLOOP 225
To0.2 MILES EAST OF LOOP 225
CSJ0057-03-043
Proj IDSTP 1902(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20036277.000.000.0
CountyFREESTONE
HighwayUS 84
From0.09 MILES WEST OF BARKER ROAD
ToLOOP 225
CSJ0057-07-015
Proj IDSTP 1902(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.110304713.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193247
Totals340990.000.000.000.0

CountyWALKER
HighwaySH 75
From13TH STREET
ToSYCAMORE AVE
CSJ0110-01-043
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
1.857221490.000.000.0
CountyFREESTONE
HighwayUS 79
FromAT US 84
To.
CSJ0205-06-032
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
0.200106719.000.000.0
CountyWALKER
HighwayUS 190
FromAT SH 19
To.
CSJ0213-01-045
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
0.200158079.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193253
Totals486288.000.000.000.0

CountyBRAZOS
HighwaySH 21
FromBURLESON COUNTY LINE
To1.35 MILES W OF FM 2818
CSJ0116-04-100
Proj IDNH 2018(317)
Work TypeOVERLAY
 
21.0425427954.288198321.4399.9
Work Order02-05-18
Work Began03-06-18
Work Completed
Time Computed03-06-18
Contract Working Days135
Addl Days Granted49
Working Days Charged181
Percent Time Used98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-100
AREA WIDE PROTECTIVE, INC. (0.50)
WEST TEXAS RUMBLE STRIP (0.21)
WILLOW CITY SIGN & RAIL, INC. (3.42)
FLASHER LIMITED (4.99)
CHEROKEE SERVICES (1.53)
CEN TEX HYDROSEED, INC. (0.11)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.32)
MURRAY CONSTRUCTION (0.75)
Contract #12173213
Totals5427954.280.008198321.4399.9

CountyBRAZOS
HighwayUS 190
FromON US 190 (SH 21)
ToAT MARINO ROAD
CSJ0117-01-052
Proj IDSTP 1802(744)HES
Work TypeMODERNIZE INTERSECT TRAFFIC SIGNAL
 
0.003321352.99201357.5062.6
Work Order09-18-18
Work Began01-09-19
Work Completed
Time Computed12-17-18
Contract Working Days59
Addl Days Granted0
Working Days Charged29
Percent Time Used49
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-01-052
AREA WIDE PROTECTIVE, INC. (0.59)
717 CONSTRUCTION SERVICES (10.81)
Contract #08183056
Totals321352.9912042.71201357.5062.6

CountyMADISON
HighwaySH 75
FromVISER ST. E.
ToDALE ST.
CSJ0166-07-062
Proj IDSTP 2019(878)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.456432428.5536100.008.3
CountyMADISON
HighwaySH 75
FromAT COLLARD ST
To.
CSJ0166-07-063
Proj IDSTP 2019(878)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200287972.5921000.007.2
CountyMADISON
HighwayIH 45
FromAT SH 75
To.
CSJ0675-05-087
Proj IDSTP 2019(878)HES
Work TypeSAFETY
 
0.200363857.60276645.0676.0
Work Order06-20-19
Work Began07-28-19
Work Completed
Time Computed07-28-19
Contract Working Days90
Addl Days Granted0
Working Days Charged3
Percent Time Used3
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0166-07-062
THIRD COAST SERVICES LLC (20.06)
WILLOW CITY SIGN & RAIL, INC. (4.30)
INTERSTATE BARRICADES & MARKINGS, INC. (2.79)
AREA WIDE PROTECTIVE, INC. (0.82)
WEST TEXAS ROCK RESOURCES, LLC (0.73)
Contract #05193051
Totals1084258.74333745.06333745.0630.7

page 1 | page 2 | page 3