Monthly State Let Construction Report For Bryan District As Of Jan 16, 2020 Page 1 Of 3

Last Update: Friday, January 17, 2020
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTSON ETC
HighwaySH 6 ETC
From0.6 MILES NORTH OF FM 979
To0.35 MILES SOUTH OF FM 1644 WEST
CSJ0049-06-078
Proj IDNH 2018(395)
Work TypeASPHALT RUBBER SEAL
 
31.2892287795.202680472.2999.9
Work Order02-26-18
Work Began05-07-18
Work Completed
Time Computed05-07-18
Contract Working Days53
Addl Days Granted3
Working Days Charged42
Percent Time Used75
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-078
INTERSTATE BARRICADES & MARKINGS, INC. (10.45)
Contract #01183227
Totals2287795.200.002680472.2999.9

CountyROBERTSON
HighwaySH 6
FromFALLS COUNTY LINE
ToFM 1644 WEST
CSJ0049-06-079
Proj IDNH 2019(977)
Work TypeOVERLAY
 
14.6027687390.672359031.5730.6
Work Order05-14-19
Work Began11-25-19
Work Completed
Time Computed08-12-19
Contract Working Days93
Addl Days Granted0
Working Days Charged38
Percent Time Used40
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-06-079
AREA WIDE PROTECTIVE, INC. (0.18)
CEN TEX HYDROSEED, INC. (0.18)
FORTSON CONTRACTING, INC. (2.81)
SCR CIVIL CONSTRUCTION, LLC (0.45)
STRIPE-A-ZONE, INC. (0.48)
TRP CONSTRUCTION GROUP, LLC (3.23)
Contract #04193241
Totals7687390.672085497.222359031.5730.6

CountyROBERTSON
HighwayUS 190
From0.27 MI NORTH OF CR 226 (ABBOTT RD)
To0.45 MILES S OF CR806 (SADBERRY RD)
CSJ0049-08-065
Proj IDNH 2018(615)
Work TypeRIGHT TURN DECEL / ACCEL LANES
 
12.3277241078.322665822.7336.8
CountyROBERTSON
HighwayUS 190
From0.45 MI S OF CR 806 (SADBERRY RD)
ToOSR (COUNTY LINE)
CSJ0049-08-067
Proj IDC 49-8-67
Work TypeMILLING AND HMA OVERLAY
 
2.4651046311.600.000.0
Work Order07-31-18
Work Began10-22-18
Work Completed
Time Computed08-30-18
Contract Working Days298
Addl Days Granted50
Working Days Charged135
Percent Time Used38
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0049-08-065
AREA WIDE PROTECTIVE, INC. (0.33)
CHEROKEE SERVICES (0.36)
COMEN ENTERPRISE LLC (1.41)
D. I. J. CONSTRUCTION, INC. (2.58)
J. H. ODEN CONTRACTING COMPANY (0.22)
STRIPE-A-ZONE, INC. (0.32)
NIXON ENGINEERING (0.00)
Contract #06183239
Totals8287389.92127859.752665822.7332.1

CountyBRAZOS ETC
HighwaySH 6 ETC
FromSH 6 WFR @ OSR
ToFM 2818
CSJ0049-09-078
Proj IDNH 2019(100)
Work TypeSEAL COAT
 
254.98410186765.8510729101.9599.9
Work Order11-15-18
Work Began07-08-19
Work Completed
Time Computed05-20-19
Contract Working Days128
Addl Days Granted0
Working Days Charged111
Percent Time Used86
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-078
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
STRIPE-A-ZONE, INC. (25.98)
BRYDL CONTRACTING, INC. (0.67)
Contract #10183013
Totals10186765.85610281.4410729101.9599.9

CountyBRAZOS
HighwayUS 190
FromAT FM 2818
To.
CSJ0049-09-079
Proj IDSTP 1802(486)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200388060.00519077.6599.9
Work Order09-19-18
Work Began01-21-19
Work Completed
Time Computed12-18-18
Contract Working Days52
Addl Days Granted26
Working Days Charged76
Percent Time Used97
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-09-079
AREA WIDE PROTECTIVE, INC. (1.56)
Contract #08183241
Totals388060.000.00519077.6599.9

CountyBRAZOS
HighwaySH 6
FromSH 21
ToFM 158
CSJ0049-12-096
Proj IDNH 1502(234)
Work TypeUPGRADE FREEWAY RAMPS
 
2.4597542870.377846124.6699.9
CountyZERO COUNTIES
Highway
From
To
CSJ0049-12-111
Proj ID
Work Type
 
0.00726261.700.0
Work Order08-20-15
Work Began02-29-16
Work Completed
Time Computed02-17-16
Contract Working Days308
Addl Days Granted135
Working Days Charged440
Percent Time Used99
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-096
ALLSTATE SIGNAL & CONSTRUCTION, LLC (4.25)
A BROTHERS MILLING, LLC (1.71)
CEN TEX HYDROSEED, INC. (4.03)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.58)
WILLOW CITY SIGN & RAIL, INC. (4.34)
COWBELL TRAFFIC SERVICES, INC. (0.16)
BEAR CREEK CONSTRUCTION, LLC (0.37)
AREA WIDE PROTECTIVE, INC. (0.53)
AARON CONCRETE CONTRACTORS, L.P. (0.61)
WEST TEXAS ROCK RESOURCES, LLC (0.03)
Contract #06153011
Totals7542870.370.008572386.3699.9

CountyBRAZOS ETC
HighwaySH 6 ETC
FromAT DRAW ON EFR AND WFR
To.
CSJ0049-12-105
Proj IDBR 2020(085)
Work TypeBRIDGE MAINTENANCE
 
1.4911471134.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days152
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-105
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10193020
Totals1471134.300.000.000.0

CountyBRAZOS
HighwaySH 6
FromOLD RELIANCE ROAD
ToFM 158 (BOONVILLE ROAD)
CSJ0049-12-115
Proj IDSTP 2019(461)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.4001105702.15147672.0013.3
Work Order10-09-19
Work Began12-06-19
Work Completed
Time Computed11-08-19
Contract Working Days126
Addl Days Granted0
Working Days Charged11
Percent Time Used8
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0049-12-115
CEN TEX HYDROSEED, INC. (3.37)
GLENN FUQUA, INC. (5.38)
AREA WIDE PROTECTIVE, INC. (1.12)
STEEL EFFECTS (0.00)
LONE STAR PRODUCTS (WICHITA FALLS) (0.00)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.83)
Contract #08193032
Totals1105702.15147672.00147672.0013.3

CountyROBERTSON
HighwayFM 46
FromFALLS CO LINE
ToSH 14
CSJ0049-14-011
Proj IDSTP 1702(019)HESG
Work TypePROFILE EDGELINE & CENTERLINE MARKS
 
31.278318695.300.000.0
CountyROBERTSON
HighwayFM 46
FromTHE FALLS COUNTY LINE
ToSH 14
CSJ0049-14-012
Proj IDSTP 2019(497)
Work TypeGRDG,WDN,STRCS,BASE,SURF,SGNS,MRKGS
 
1.3701404401.281095169.8177.9
Work Order03-18-19
Work Began06-27-19
Work Completed
Time Computed06-16-19
Contract Working Days93
Addl Days Granted0
Working Days Charged91
Percent Time Used97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0049-14-011
AREA WIDE PROTECTIVE, INC. (1.17)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.26)
BEAR CREEK CONSTRUCTION, LLC (22.30)
BROCK CONSTRUCTION, LLC (1.35)
CEN TEX HYDROSEED, INC. (2.34)
STRIPE-A-ZONE, INC. (17.79)
COMEN ENTERPRISE LLC (2.71)
LS HIGHWAY PRODUCTS, INC. (0.00)
Contract #02193019
Totals1723096.5899449.541095169.8163.5

CountyBRAZOS
HighwayBS 6-R ETC
FromON BS 6-R
ToAT THE INTERSECTION WITH 29TH ST
CSJ0050-01-079
Proj IDSTP 2017(914)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
2.6411474037.571579764.6799.9
Work Order06-26-17
Work Began11-27-17
Work Completed
Time Computed09-22-17
Contract Working Days190
Addl Days Granted28
Working Days Charged199
Percent Time Used91
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-01-079
STRIPE LINES, INC. (4.71)
TRAF-TEX, INC. (48.61)
AREA WIDE PROTECTIVE, INC. (0.68)
Contract #04173004
Totals1474037.570.001579764.6799.9

CountyBRAZOS ETC
HighwaySH 6 ETC
FromSH 6 EFR @ SH 40
To.5 MI N OF GRIMES COUNTY LINE
CSJ0050-02-111
Proj IDNH 2020(081)
Work TypeSEAL COAT
 
38.2314675136.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-20-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0050-02-111
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10193014
Totals4675136.430.000.000.0

CountyGRIMES
HighwaySH 6
FromBRAZOS COUNTY LINE
ToWALLER COUNTY LINE
CSJ0050-03-100
Proj IDC 50-3-100
Work TypeOVERLAY
 
14.3835798125.913553786.7261.2
Work Order08-17-18
Work Began08-12-19
Work Completed
Time Computed11-15-18
Contract Working Days72
Addl Days Granted10
Working Days Charged79
Percent Time Used96
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0050-03-100
AREA WIDE PROTECTIVE, INC. (0.12)
BATTERSON,LLP (3.03)
CPAVE, INC. (3.60)
DUSTROL, INC. (4.21)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
Contract #07183040
Totals5798125.918804.553553786.7261.2

CountyFREESTONE ETC
HighwayBU 84-R ETC
FromUS 84
ToSH 179
CSJ0057-02-037
Proj IDSTP 2018(232)
Work TypeSEAL COAT
 
385.07412525077.0015668053.0299.9
Work Order12-04-17
Work Began05-14-18
Work Completed
Time Computed05-01-18
Contract Working Days75
Addl Days Granted141
Working Days Charged152
Percent Time Used70
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-02-037
D. I. J. CONSTRUCTION, INC. (17.61)
BRYDL CONTRACTING, INC. (0.81)
Contract #10173003
Totals12525077.000.0015668053.0299.9

CountyFREESTONE ETC
HighwayUS 84 ETC
FromBU 84-R
ToIH 45
CSJ0057-03-041
Proj IDSTP 2019(496)HES
Work TypePROFILE EDGELINE MARKINGS
 
179.5411651842.00615085.5237.2
Work Order03-25-19
Work Began09-16-19
Work Completed
Time Computed09-09-19
Contract Working Days62
Addl Days Granted0
Working Days Charged43
Percent Time Used69
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-041
AREA WIDE PROTECTIVE, INC. (0.10)
SURFACE PREPARATION TECHNOLOGIES, LLC (4.37)
BRYDL CONTRACTING, INC. (4.50)
BATTERSON,LLP (1.77)
Contract #02193221
Totals1651842.0084043.09615085.5237.2

CountyFREESTONE ETC
HighwayUS 84 ETC
FromIH 45
ToSH 75
CSJ0057-03-042
Proj IDC 57-3-42
Work TypeASPHALT RUBBER SEAL
 
187.92113798219.667630516.3755.4
Work Order03-25-19
Work Began09-04-19
Work Completed
Time Computed07-01-19
Contract Working Days82
Addl Days Granted0
Working Days Charged98
Percent Time Used119
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-042
INTERSTATE BARRICADES & MARKINGS, INC. (10.21)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.05)
BRYDL CONTRACTING, INC. (0.55)
Contract #01193003
Totals13798219.6622578.007630516.3755.4

CountyFREESTONE
HighwayUS 84
FromLOOP 225
To0.2 MILES EAST OF LOOP 225
CSJ0057-03-043
Proj IDSTP 1902(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.20036277.000.000.0
CountyFREESTONE
HighwayUS 84
From0.09 MILES WEST OF BARKER ROAD
ToLOOP 225
CSJ0057-07-015
Proj IDSTP 1902(028)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.110304713.000.000.0
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed10-15-19
Contract Working Days30
Addl Days Granted0
Working Days Charged1
Percent Time Used3
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0057-03-043
AREA WIDE PROTECTIVE, INC. (3.32)
Contract #06193247
Totals340990.000.000.000.0

CountyWALKER
HighwaySH 75
From13TH STREET
ToSYCAMORE AVE
CSJ0110-01-043
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
1.857221490.0023220.0010.4
CountyFREESTONE
HighwayUS 79
FromAT US 84
To.
CSJ0205-06-032
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
0.200106719.0046750.0043.8
CountyWALKER
HighwayUS 190
FromAT SH 19
To.
CSJ0213-01-045
Proj IDSTP 2019(892)HES
Work TypeSAFETY
 
0.200158079.0020030.0012.6
Work Order06-20-19
Work Began09-09-18
Work Completed
Time Computed09-09-19
Contract Working Days105
Addl Days Granted0
Working Days Charged38
Percent Time Used36
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0110-01-043
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.68)
BATTEN DRILLING, INC. (0.97)
Contract #05193253
Totals486288.0020100.0090000.0018.5

CountyWASHINGTON
HighwayUS 290
FromAT SHEPPARD CREEK (US 290 WB)
To.
CSJ0114-09-080
Proj IDBR 2020(481)
Work TypeBRIDGE MAINTENANCE
 
0.6722499110.520.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0114-09-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01203017
Totals2499110.520.000.000.0

CountyBRAZOS
HighwaySH 21
FromBURLESON COUNTY LINE
To1.35 MILES W OF FM 2818
CSJ0116-04-100
Proj IDNH 2018(317)
Work TypeOVERLAY
 
21.0425427954.288265891.7199.9
Work Order02-05-18
Work Began03-06-18
Work Completed
Time Computed03-06-18
Contract Working Days135
Addl Days Granted49
Working Days Charged182
Percent Time Used98
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0116-04-100
AREA WIDE PROTECTIVE, INC. (0.50)
WEST TEXAS RUMBLE STRIP (0.21)
WILLOW CITY SIGN & RAIL, INC. (3.42)
FLASHER LIMITED (4.99)
CHEROKEE SERVICES (1.53)
CEN TEX HYDROSEED, INC. (0.11)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (0.32)
MURRAY CONSTRUCTION (0.75)
Contract #12173213
Totals5427954.280.008265891.7199.9

CountyBRAZOS
HighwayUS 190
FromON US 190 (SH 21)
ToAT MARINO ROAD
CSJ0117-01-052
Proj IDSTP 1802(744)HES
Work TypeMODERNIZE INTERSECT TRAFFIC SIGNAL
 
0.003321352.99320201.3899.6
Work Order09-18-18
Work Began01-09-19
Work Completed
Time Computed12-17-18
Contract Working Days59
Addl Days Granted0
Working Days Charged56
Percent Time Used94
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0117-01-052
AREA WIDE PROTECTIVE, INC. (0.59)
717 CONSTRUCTION SERVICES (10.81)
INTERSTATE BARRICADES & MARKINGS, INC. (4.20)
Contract #08183056
Totals321352.990.00320201.3899.6

page 1 | page 2 | page 3