Monthly State Let Construction Report For Bryan District As Of Aug 15, 2022 Page 4 Of 4

Last Update: Monday, August 15, 2022
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwayFM 2821
FromAT ROSENWALL ROAD
To.
CSJ2850-01-018
Proj IDSTP 2021(351)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2117590.121374121.7966.8
Work Order03-12-21
Work Began06-10-21
Work Completed
Time Computed06-10-21
Contract Working Days79
Addl Days Granted0
Working Days Charged131
Percent Time Used165
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2850-01-018
CEN TEX HYDROSEED, INC. (4.01)
HIGHWAY 1 LLC (1.63)
J & M CONTRACTING, COMPANY (9.96)
WATERS CONSTRUCTION COMPANY, INC. (2.69)
WILLOW CITY SIGN & RAIL, INC. (1.49)
PINNACLE GRINDING AND GROOVING LLC (0.26)
CITYLYNX, INC. (5.10)
Contract #02213218
Totals2117590.125481.731374121.7966.8

page 1 | page 2 | page 3 | page 4