Monthly State Let Construction Report For Bryan District As Of Dec 07, 2021 Page 4 Of 4

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGRIMES ETC
HighwayFM 1774 ETC
FromAT CR 302
To.
CSJ1400-02-025
Proj IDSTP 2B20(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.9156403546.103434183.4253.6
Work Order12-11-20
Work Began03-11-21
Work Completed
Time Computed03-11-21
Contract Working Days190
Addl Days Granted0
Working Days Charged112
Percent Time Used58
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1400-02-025
CEN TEX HYDROSEED, INC. (2.06)
CITYLYNX, INC. (3.28)
PINNACLE GRINDING AND GROOVING LLC (0.14)
STATEWIDE MATERIALS TRANSPORT, LTD. (0.00)
TRAFFIC SIGNS & LINES, LLC (0.00)
WATERS CONSTRUCTION COMPANY, INC. (0.00)
Contract #11203233
Totals6403546.10788887.993434183.4253.6

CountyMILAM
HighwayFM 908
FromAT BRUSHY CREEK
To.
CSJ2087-01-021
Proj IDBR 2021(027)
Work TypeBRIDGE REPLACEMENT
 
0.1001185695.671208631.1599.9
Work Order11-19-20
Work Began01-15-21
Work Completed
Time Computed01-15-21
Contract Working Days79
Addl Days Granted5
Working Days Charged84
Percent Time Used100
Contractor(s)
SB CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 2087-01-021
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.26)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.49)
TEXAS MATERIALS GROUP, INC. (5.69)
VOGES DRILLING CO. (6.34)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.30)
JVH4 SERVICES, LLC (1.04)
TORO BRAVO CONSTRUCTION, LLC (1.93)
PRIMATE CONSTRUCTION, LP (0.38)
PMI PAVEMENT MARKING, LLC (0.87)
Contract #10203017
Totals1185695.670.001208631.1599.9

CountyBRAZOS
HighwayFM 2818
FromFM 60
ToFM 2154
CSJ2399-01-068
Proj IDSTP 2020(880)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.634844467.400.000.0
CountyBRAZOS
HighwayFM 2818
From0.5 MILES NORTH OF FM 60
ToFM 2154
CSJ2399-01-074
Proj IDNH 2020(879)
Work TypeWIDEN NON-FREEWAY
 
3.21541689887.078806056.8321.1
CountyBRAZOS
HighwayFM 2818
From0.5 MILES NORTH OF FM 60
ToFM 2154
CSJ2399-01-079
Proj IDNH 2B20(178)
Work TypeRIGHT OF WAY
 
3.2152720291.002083932.4876.6
Work Order10-21-20
Work Began02-01-21
Work Completed
Time Computed01-19-21
Contract Working Days597
Addl Days Granted0
Working Days Charged197
Percent Time Used32
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 2399-01-068
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.77)
AREA WIDE PROTECTIVE, INC. (0.13)
BROCK CONSTRUCTION, LLC (0.29)
CEN TEX HYDROSEED, INC. (0.46)
D & S CONTRACTING, INC. (5.59)
FLASHER EQUIPMENT COMPANY (0.79)
FLOVERA CONSTRUCTION SERVICES, LLC (3.21)
LARRY YOUNG PAVING, INC. (3.98)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.32)
PRIMATE CONSTRUCTION, LP (0.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.42)
WILLOW CITY SIGN & RAIL, INC. (0.87)
SCOTT DERR PAINTING CO, LLC (0.53)
GREEN TEAMS, INC. (1.75)
TORO BRAVO CONSTRUCTION, LLC (0.01)
JOHN WRIGHT CONSTRUCTION (0.36)
CUSTOM FABRICATORS & REPAIRS, INC. (0.16)
BATTEN DRILLING, INC. (0.00)
FARR FOUNDATION, INC. (0.11)
AGGREGATE TECHNOLOGIES, INC. (0.03)
HEATRO PIPELINE SERVICES, L.L.C. (0.01)
Contract #09203203
Totals45254645.471218002.7310889989.3124.0

CountyWASHINGTON
HighwayFM 577
FromAT OLD CHAPPELL HILL ROAD
To.
CSJ2447-01-032
Proj IDF 2022(010)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
576065.380.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-26-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2447-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213215
Totals576065.380.000.000.0

CountyWALKER
HighwayFM 2821
FromAT ROSENWALL ROAD
To.
CSJ2850-01-018
Proj IDSTP 2021(351)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2117590.121040258.3049.3
Work Order03-12-21
Work Began06-10-21
Work Completed
Time Computed06-10-21
Contract Working Days79
Addl Days Granted0
Working Days Charged84
Percent Time Used106
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2850-01-018
CEN TEX HYDROSEED, INC. (4.01)
HIGHWAY 1 LLC (1.63)
J & M CONTRACTING, COMPANY (9.96)
WATERS CONSTRUCTION COMPANY, INC. (2.69)
WILLOW CITY SIGN & RAIL, INC. (1.49)
PINNACLE GRINDING AND GROOVING LLC (0.26)
CITYLYNX, INC. (5.10)
Contract #02213218
Totals2117590.12307195.391040258.3049.3

CountyBRAZOS
HighwayFM 2347
FromBIZZELL ST
ToBS 6-R
CSJ3138-01-029
Proj IDSTP 2020(954)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.6511222395.101160289.2586.4
CountyBRAZOS
HighwayFM 2347
FromAT DEXTER/ THOCKMORTON
To.
CSJ3138-01-030
Proj IDSTP 2020(954)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200311631.10320767.1799.9
CountyBRAZOS
HighwayFM 2347
FromFM 2154
ToBIZZELL STREET
CSJ3138-01-032
Proj IDSTP 2020(955)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
883955.40885432.1199.9
Work Order08-20-20
Work Began01-07-21
Work Completed
Time Computed11-18-20
Contract Working Days107
Addl Days Granted0
Working Days Charged118
Percent Time Used110
Contractor(s)
LARRY YOUNG PAVING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3138-01-029
BRITTEN HYDROSEEDING (0.60)
CITYLYNX, INC. (10.52)
CENTRAL TEXAS ARBORISTS & CONSULTING, LLC (0.34)
TRAFFIC SIGNS & LINES, LLC (6.48)
D. I. J. CONSTRUCTION, INC. (0.07)
Contract #07203035
Totals2417981.601886.702366488.5393.5

page 1 | page 2 | page 3 | page 4