Monthly Local Let Maintenance Report For Bryan District As Of Sep 18, 2019 Page 1 Of 4

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayMR0688
FromAT BRENHAM STATE SCHOOL
ToAT BRENHAM STATE SCHOOL
CSJ6250-83-001
Proj IDRMC - 625083001
Work TypeSURFACE TREAT PARKING LOTS
 
0.00139379.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days4
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03131701
Totals39379.850.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6310-91-001
Proj IDRMC - 631091001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001194000.00391407.0099.9
Work Order04-10-17
Work Began02-01-17
Work Completed
Time Computed04-18-17
Contract Working Days730
Addl Days Granted730
Working Days Charged942
Percent Time Used64
Contractor(s)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12161711
Totals194000.0016450.00391407.0099.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6312-27-001
Proj IDRMC - 631227001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.5048593.8021.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-24-18
Work Began01-24-18
Work Completed
Time Computed01-24-18
Contract Working Days731
Addl Days Granted0
Working Days Charged554
Percent Time Used75
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171703
Totals227312.500.0048593.8021.3

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6312-28-001
Proj IDRMC - 631228001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.50113508.3449.9
Work Order01-24-18
Work Began01-24-18
Work Completed
Time Computed02-01-18
Contract Working Days731
Addl Days Granted0
Working Days Charged585
Percent Time Used80
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171702
Totals227312.500.00113508.3449.9

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6312-29-001
Proj IDRMC - 631229001
Work TypeINSTALL SHORTLINE AND SPECIALTY MARKINGS
 
0.001227312.50126272.9555.5
Work Order01-31-18
Work Began01-24-18
Work Completed
Time Computed02-08-18
Contract Working Days731
Addl Days Granted0
Working Days Charged572
Percent Time Used78
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09171701
Totals227312.50872.00126272.9555.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6314-90-001
Proj IDRMC - 631490001
Work TypeINSTALL/REMOVE RAISED PAVEMENT MARKERS
 
0.001249203.00146149.51100.0
Work Order10-30-17
Work Began10-19-17
Work Completed09-01-19
Time Computed11-07-17
Contract Working Days80
Addl Days Granted0
Working Days Charged31
Percent Time Used38
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05171704
Totals249203.000.00146149.51100.0

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6315-09-001
Proj IDRMC - 631509001
Work TypePICNIC AREA MAINTENANCE
 
0.00125570.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TWO SISTER'S CONST CO.
SUBCONTRACTOR(S) FOR CCSJ: 6315-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171703
Totals25570.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6319-89-001
Proj IDRMC - 631989001
Work TypeROADSIDE MOWING
 
225.457207044.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JMT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6319-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181709
Totals207044.000.000.000.0

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6319-90-001
Proj IDRMC - 631990001
Work TypeROADSIDE MOWING
 
302.900161717.8865044.3640.2
Work Order06-03-19
Work Began05-15-19
Work Completed
Time Computed06-10-19
Contract Working Days48
Addl Days Granted0
Working Days Charged15
Percent Time Used31
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6319-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181708
Totals161717.880.0065044.3640.2

CountyBURLESON
HighwayFM0060
FromVARIOUS
ToVARIOUS
CSJ6319-91-001
Proj IDRMC - 631991001
Work TypeROADSIDE MOWING
 
233.630128367.4059554.0046.3
Work Order05-24-19
Work Began05-16-19
Work Completed
Time Computed06-01-19
Contract Working Days41
Addl Days Granted0
Working Days Charged14
Percent Time Used34
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6319-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181707
Totals128367.400.0059554.0046.3

CountyMILAM
HighwayFM0486
FromVARIOUS
ToVARIOUS
CSJ6319-92-001
Proj IDRMC - 631992001
Work TypeROADSIDE MOWING
 
333.935196537.8379115.1440.2
Work Order05-29-19
Work Began05-14-19
Work Completed
Time Computed06-06-19
Contract Working Days54
Addl Days Granted0
Working Days Charged19
Percent Time Used35
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6319-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181706
Totals196537.830.0079115.1440.2

CountyWALKER
HighwayFM1374
FromVARIOUS
ToVARIOUS
CSJ6319-95-001
Proj IDRMC - 631995001
Work TypeROADSIDE MOWING
 
263.500134832.5760868.3945.1
Work Order06-03-19
Work Began05-21-19
Work Completed
Time Computed06-11-19
Contract Working Days43
Addl Days Granted0
Working Days Charged14
Percent Time Used32
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6319-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181703
Totals134832.570.0060868.3945.1

CountyMADISON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6319-96-001
Proj IDRMC - 631996001
Work TypeROADSIDE MOWING
 
220.400107253.4847853.6444.6
Work Order06-03-19
Work Began05-21-19
Work Completed
Time Computed06-11-19
Contract Working Days35
Addl Days Granted0
Working Days Charged13
Percent Time Used37
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6319-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181702
Totals107253.480.0047853.6444.6

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6319-97-001
Proj IDRMC - 631997001
Work TypeROADSIDE MOWING
 
278.600173148.0876504.0444.1
Work Order05-23-19
Work Began05-15-19
Work Completed
Time Computed06-03-19
Contract Working Days44
Addl Days Granted0
Working Days Charged8
Percent Time Used18
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6319-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181701
Totals173148.080.0076504.0444.1

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6330-03-001
Proj IDRMC - 633003001
Work TypeSIGN MAINTENANCE
 
0.010298500.00188429.8363.1
Work Order10-01-18
Work Began09-20-18
Work Completed
Time Computed10-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged324
Percent Time Used88
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 6330-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07181702
Totals298500.004053.87188429.8363.1

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6332-80-001
Proj IDRMC - 633280001
Work TypePICNIC AREA MAINTENANCE
 
0.00131250.0032979.6099.9
Work Order08-07-18
Work Began08-07-18
Work Completed
Time Computed08-07-18
Contract Working Days365
Addl Days Granted61
Working Days Charged390
Percent Time Used91
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6332-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07181701
Totals31250.002755.2032979.6099.9

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6334-46-001
Proj IDSUP - 633446001
Work TypeBUILDING JANITORIAL
 
0.00116285.165885.0036.1
Work Order08-02-18
Work Began08-01-18
Work Completed
Time Computed08-02-18
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181702
Totals16285.16470.805885.0036.1

CountyMADISON
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6334-47-001
Proj IDSUP - 633447001
Work TypeMADISON JANITORIAL
 
0.01012007.826053.9550.4
Work Order08-06-18
Work Began08-01-18
Work Completed
Time Computed08-06-18
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6334-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181703
Totals12007.82500.356053.9550.4

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6335-77-001
Proj IDSUP - 633577001
Work TypeLITTER PICKUP & DISPOSAL
 
0.0011427445.161056140.3673.9
Work Order09-19-18
Work Began09-01-18
Work Completed
Time Computed09-30-18
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6335-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07181704
Totals1427445.1640575.051056140.3673.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6335-85-001
Proj IDSUP - 633585001
Work TypeYARD MAINTENANCE
 
0.01053604.8615403.8028.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-18
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged365
Percent Time Used50
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6335-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07181711
Totals53604.860.0015403.8028.7

page 1 | page 2 | page 3 | page 4