Monthly Local Let Maintenance Report For Bryan District As Of Mar 13, 2024 Page 3 Of 5

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6431-56-001
Proj IDRMC - 643156001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010199972.1855139.5927.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-15-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged261
Percent Time Used71
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6431-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01231709
Totals199972.187631.0255139.5927.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6432-48-001
Proj IDMMC - 643248001
Work TypeCUTBACK
 
0.010148920.00281762.1999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged250
Percent Time Used69
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231702
Totals148920.0098325.55281762.1999.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6432-50-001
Proj IDMMC - 643250001
Work TypeCUTBACK
 
0.010199560.00168044.1584.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-25-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged250
Percent Time Used69
Contractor(s)
MARTIN RESOURCE MANAGEMENT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6432-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05231703
Totals199560.0066341.04168044.1584.2

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6433-30-001
Proj IDMMC - 643330001
Work TypeWINTER WEATHER MATERIAL
 
0.010279961.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-27-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged156
Percent Time Used42
Contractor(s)
UNITED SALT CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6433-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231703
Totals279961.920.000.000.0

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6434-26-001
Proj IDSUP - 643426001
Work TypeJANITORIAL MAINTENANCE
 
0.01041668.0021600.2451.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged394
Percent Time Used53
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-26-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01231730
Totals41668.001532.4821600.2451.8

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6434-30-001
Proj IDSUP - 643430001
Work TypeJANITORIAL MAINTENANCE
 
0.01024699.2413015.0852.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged394
Percent Time Used53
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6434-30-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #01231731
Totals24699.24887.2813015.0852.6

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6436-60-001
Proj IDSUP - 643660001
Work TypeJANITORIAL MAINTENANCE
 
0.01025943.447040.0027.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged274
Percent Time Used37
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6436-60-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #02231730
Totals25943.440.007040.0027.1

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6438-25-001
Proj IDSUP - 643825001
Work TypeJANITORIAL MAINTENANCE
 
0.01049278.1618592.6537.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-01-23
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6438-25-001
WORLD TECHNICAL SERVICES, INC. (0.00)
Contract #03231730
Totals49278.161215.5518592.6537.7

CountyMILAM
HighwayUS0077
FromVARIOUS
ToVARIOUS
CSJ6438-47-001
Proj IDBPM - 643847001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010116900.00120017.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-15-23
Work Completed
Time Computed00-00-00
Contract Working Days13
Addl Days Granted0
Working Days Charged9
Percent Time Used69
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231702
Totals116900.0015150.00120017.6099.9

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6438-53-001
Proj IDBPM - 643853001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010163431.0063300.0038.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted14
Working Days Charged4
Percent Time Used10
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231710
Totals163431.0063300.0063300.0038.7

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6441-60-001
Proj IDRMC - 644160001
Work TypeTREE REMOVAL
 
0.010187350.00148196.0079.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-23-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged252
Percent Time Used69
Contractor(s)
CEHAND SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6441-60-001
FLORES TREE SERVICE LLC (0.00)
Contract #05231711
Totals187350.0020418.00148196.0079.1

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6443-46-001
Proj IDRMC - 644346001
Work TypeCRACK SEAL
 
0.010129814.50125935.5399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged66
Percent Time Used111
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6443-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231705
Totals129814.50125935.53125935.5399.9

CountyBRAZOS
HighwayFM2818
FromVARIOUS
ToVARIOUS
CSJ6443-48-001
Proj IDRMC - 644348001
Work TypeCRACK SEAL
 
0.010199407.08190858.3795.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-01-23
Work Completed
Time Computed00-00-00
Contract Working Days59
Addl Days Granted0
Working Days Charged59
Percent Time Used100
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6443-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231706
Totals199407.08134856.41190858.3795.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6444-14-001
Proj IDMMC - 644414001
Work TypeFLOWABLE FILL
 
0.010246560.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231709
Totals246560.000.000.000.0

CountyFREESTONE
HighwayIH0045
FromVARIOUS
ToVA
CSJ6444-22-001
Proj IDMMC - 644422001
Work TypeFLOWABLE FILL
 
0.010224560.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6444-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231710
Totals224560.000.000.000.0

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6444-24-001
Proj IDMMC - 644424001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010259500.00620618.0299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-28-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged217
Percent Time Used60
Contractor(s)
MARTIN MARIETTA MATERIALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231711
Totals259500.00169079.15620618.0299.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6444-30-001
Proj IDMMC - 644430001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010136752.0057383.6841.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6444-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231703
Totals136752.0014346.3957383.6841.9

CountyMILAM
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6444-98-001
Proj IDRMC - 644498001
Work TypePICNIC AREA MAINTENANCE
 
0.01055759.0030554.0054.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged201
Percent Time Used55
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6444-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231708
Totals55759.004824.0030554.0054.7

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6447-20-001
Proj IDMMC - 644720001
Work TypeWINTER WEATHER MATERIAL
 
0.010203504.329948.964.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-27-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged156
Percent Time Used42
Contractor(s)
THE BARGAIN SOURCE
SUBCONTRACTOR(S) FOR CCSJ: 6447-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231704
Totals203504.320.009948.964.8

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6447-60-001
Proj IDMMC - 644760001
Work TypeWINTER WEATHER MATERIAL
 
0.010205688.328825.304.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-14-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged169
Percent Time Used46
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08231705
Totals205688.328825.308825.304.2

page 1 | page 2 | page 3 | page 4 | page 5