Monthly State Let Maintenance Report For Bryan District As Of Nov 12, 2021 Page 1 Of 2

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwayIH0045
FromMONTGOMERY/WALKER COUNTY LINE
ToFREESTONE/NAVARRO COUNTY LINE
CSJ6298-21-001
Proj IDRMC - 629821001
Work TypePERFORMANCE-BASED TOTAL MAINT. OF IH 45
 
112.2008996600.0018686516.4899.9
Work Order07-26-16
Work Began07-01-16
Work Completed
Time Computed07-26-16
Contract Working Days1,095
Addl Days Granted1,095
Working Days Charged1,949
Percent Time Used88
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164009
Totals8996600.00279992.7818686516.4899.9

CountyBRAZOS
HighwayBS0006R
FromVARIOUS
ToVARIOUS
CSJ6341-26-001
Proj IDRMC - 634126001
Work TypeHMA MILL AND INLAY
 
0.001546196.002889030.60100.0
Work Order08-19-19
Work Began08-22-19
Work Completed10-06-21
Time Computed09-03-19
Contract Working Days365
Addl Days Granted370
Working Days Charged771
Percent Time Used104
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6341-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194204
Totals546196.0010559.502889030.60100.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6341-27-001
Proj IDRMC - 634127001
Work TypeHMA MILL AND INLAY
 
0.0011137391.752226140.27100.0
Work Order08-29-19
Work Began08-29-19
Work Completed09-08-21
Time Computed09-09-19
Contract Working Days365
Addl Days Granted365
Working Days Charged734
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6341-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194206
Totals1137391.750.002226140.27100.0

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6346-24-001
Proj IDRMC - 634624001
Work TypeINSTALLATION OF DRIVEWAY PIPE
 
0.001715533.001501150.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-04-19
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted731
Working Days Charged789
Percent Time Used53
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6346-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194205
Totals715533.002826.171501150.6499.9

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6346-62-001
Proj IDRMC - 634662001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0011869290.001868860.00100.0
Work Order09-05-19
Work Began09-05-19
Work Completed10-05-21
Time Computed09-05-19
Contract Working Days731
Addl Days Granted30
Working Days Charged753
Percent Time Used98
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6346-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194207
Totals1869290.0039165.001868860.00100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6346-63-001
Proj IDRMC - 634663001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0011841225.002402022.50100.0
Work Order09-26-19
Work Began09-05-19
Work Completed10-05-21
Time Computed09-26-19
Contract Working Days731
Addl Days Granted30
Working Days Charged757
Percent Time Used99
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6346-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194206
Totals1841225.0042547.502402022.50100.0

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6348-24-001
Proj IDRMC - 634824001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0012322131.101739932.1474.9
Work Order06-23-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days731
Addl Days Granted0
Working Days Charged488
Percent Time Used66
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6348-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204002
Totals2322131.10101132.421739932.1474.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6352-14-001
Proj IDRMC - 635214001
Work TypeSPOT PAVEMENT MARKINGS
 
0.001707400.00468022.4866.1
Work Order08-18-20
Work Began08-18-20
Work Completed
Time Computed08-18-20
Contract Working Days730
Addl Days Granted0
Working Days Charged440
Percent Time Used60
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6352-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05204205
Totals707400.0024297.19468022.4866.1

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6364-04-001
Proj IDRMC - 636404001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001633895.00402359.0063.4
Work Order10-20-20
Work Began10-20-20
Work Completed
Time Computed10-20-20
Contract Working Days731
Addl Days Granted0
Working Days Charged377
Percent Time Used51
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6364-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204006
Totals633895.0020148.00402359.0063.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6364-17-001
Proj IDRMC - 636417001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001865110.00526699.5060.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-20
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged390
Percent Time Used53
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6364-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204007
Totals865110.0065318.00526699.5060.8

CountyFREESTONE
HighwayUS0084
FromVARIOUS
ToVARIOUS
CSJ6364-18-001
Proj IDRMC - 636418001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001730335.00176359.6824.1
Work Order12-08-20
Work Began12-08-20
Work Completed
Time Computed12-08-20
Contract Working Days730
Addl Days Granted0
Working Days Charged328
Percent Time Used44
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6364-18-001
JUNIOR CONSTRUCTION COMPANY, INC. (0.00)
Contract #09204205
Totals730335.006462.50176359.6824.1

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6364-19-001
Proj IDRMC - 636419001
Work TypeTHERMOPLASTIC PAVEMENT MARKING INSTALL
 
0.0011967810.002285960.6999.9
Work Order10-19-20
Work Began10-19-20
Work Completed
Time Computed10-19-20
Contract Working Days730
Addl Days Granted0
Working Days Charged378
Percent Time Used51
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6364-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204014
Totals1967810.00416214.002285960.6999.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6367-62-001
Proj IDRMC - 636762001
Work TypeREMOVE/INSTALL LARGE GUIDE SIGNS
 
0.001677125.00109812.2116.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-05-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged241
Percent Time Used66
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6367-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204204
Totals677125.000.00109812.2116.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6373-03-001
Proj IDRMC - 637303001
Work TypePAVEMENT MARKINGS
 
321086.00116328.5036.2
Work Order04-12-21
Work Began04-15-21
Work Completed
Time Computed04-14-21
Contract Working Days365
Addl Days Granted0
Working Days Charged200
Percent Time Used54
Contractor(s)
PMI PAVEMENT MARKING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6373-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214003
Totals321086.0033548.65116328.5036.2

CountyBRAZOS
HighwayBS0006R
FromVARIOUS
ToVARIOUS
CSJ6373-94-001
Proj IDRMC - 637394001
Work TypeMILL AND INLAY
 
0.010708467.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-09-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6373-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214004
Totals708467.000.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6373-95-001
Proj IDRMC - 637395001
Work TypeMILL AND INLAY
 
1225720.00295961.7324.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-25-21
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged60
Percent Time Used16
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6373-95-001
NIXON ENGINEERING (0.00)
Contract #06214007
Totals1225720.00295961.73295961.7324.1

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6373-96-001
Proj IDRMC - 637396001
Work TypeMILL AND INLAY
 
986327.00182189.2918.4
Work Order08-24-21
Work Began08-24-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6373-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04214005
Totals986327.00182189.29182189.2918.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6373-97-001
Proj IDRMC - 637397001
Work TypeSPOT BASE REPAIR
 
654817.5069326.9910.5
Work Order08-25-21
Work Began08-25-21
Work Completed
Time Computed08-25-21
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6373-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06214006
Totals654817.5069326.9969326.9910.5

CountyMADISON
HighwaySH0021
From~1.17 MI E OF IH 45 EFR
To~0.47 MI E OF HAPPY HAVEN RD
CSJ6375-25-001
Proj IDRMC - 637525001
Work TypeMILL AND INLAY PROJECT
 
4.3401673115.051625994.74100.0
Work Order04-28-21
Work Began04-28-21
Work Completed09-20-21
Time Computed04-28-21
Contract Working Days48
Addl Days Granted0
Working Days Charged48
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6375-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02214006
Totals1673115.0532109.801625994.74100.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6376-13-001
Proj IDRMC - 637613001
Work TypeSPOT BASE REPAIR
 
0.010638323.50234673.2536.7
Work Order08-24-21
Work Began08-24-21
Work Completed
Time Computed09-01-21
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6376-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214006
Totals638323.50234673.25234673.2536.7

page 1 | page 2