Monthly State Let Maintenance Report For Bryan District As Of Dec 07, 2021 Page 2 Of 2

Last Update: Wednesday, December 08, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwaySH0075
FromSH 30
ToIH 45 EFR
CSJ6379-62-001
Proj IDRMC - 637962001
Work TypeHOT MIX
 
0.0101051583.931149282.0199.9
Work Order09-15-21
Work Began09-15-21
Work Completed
Time Computed09-20-21
Contract Working Days20
Addl Days Granted0
Working Days Charged20
Percent Time Used100
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6379-62-001
HIGHWAY 1 LLC (0.00)
Contract #06214005
Totals1051583.9366930.021149282.0199.9

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6383-13-001
Proj IDRMC - 638313001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101685260.00127597.007.5
Work Order08-26-21
Work Began08-26-21
Work Completed
Time Computed08-26-21
Contract Working Days730
Addl Days Granted0
Working Days Charged85
Percent Time Used11
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214005
Totals1685260.0056576.00127597.007.5

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6383-14-001
Proj IDRMC - 638314001
Work TypeTRAFFIC CONTROL SERVICES
 
0.0101602255.00184729.0011.5
Work Order08-30-21
Work Began08-30-21
Work Completed
Time Computed09-07-21
Contract Working Days730
Addl Days Granted0
Working Days Charged85
Percent Time Used11
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214003
Totals1602255.0071244.50184729.0011.5

CountyMADISON
HighwayFM1452
FromAT IRON CREEK
ToAT IRON CREEK
CSJ6385-57-001
Proj IDRMC - 638557001
Work TypeBRIDGE REPAIR
 
0.010320869.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6385-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214008
Totals320869.850.000.000.0

CountyBURLESON
HighwayFM0050
FromAT FOUNTAIN SLOUGH
ToAT FOUNTAIN SLOUGH
CSJ6388-17-001
Proj IDRMC - 638817001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010404499.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FUQUA CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12214007
Totals404499.000.000.000.0

page 1 | page 2