Monthly State Let Construction Report For Brownwood District As Of Nov 12, 2021 Page 1 Of 2

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND ETC
HighwayIH 20 ETC
From1.2 MI W OF SH 6
ToFM 570
CSJ0007-03-094
Proj IDF 2022(233)
Work TypeSEAL COAT
 
315.77814844220.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days105
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213003
Totals14844220.020.000.000.0

CountyEASTLAND
HighwayIH 20
FromCALLAHAN C/L
To.3 MI E OF FM 570
CSJ0007-03-097
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
19.8883143781.391500722.3547.7
CountyEASTLAND
HighwayIH 20
From.3 MI E OF FM 570
To.41 MI W OF FM 2461
CSJ0007-04-133
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
992192.75331172.6133.3
CountyEASTLAND
HighwayIH 20
From0.41 MI W OF FM 2461
ToLP 254 (E INTERSECTION)
CSJ0007-06-265
Proj IDSTP 2021(326)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.307856755.58368289.4642.9
Work Order03-18-21
Work Began06-14-21
Work Completed
Time Computed04-17-21
Contract Working Days338
Addl Days Granted0
Working Days Charged87
Percent Time Used25
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-097
AVANZA CONSTRUCTION & EARTHWORKS, LLC (2.40)
CROWDER CONSTRUCTION CO., INC. (EASTLAND) (1.20)
TNT CRANE & RIGGING, INC. (2.40)
Contract #02213210
Totals4992729.72203957.522200184.4244.0

CountyEASTLAND
HighwayIH 20
FromAPPROX 3.5 MILES EAST OF LP 254
To0.5 MI E OF SH 16
CSJ0007-06-084
Proj IDSTP 2017(368)HES
Work TypeREALIGN EXISTING ROADWAY
 
3.49675522594.1279375529.3599.9
Work Order04-24-17
Work Began07-24-17
Work Completed
Time Computed07-23-17
Contract Working Days914
Addl Days Granted266
Working Days Charged1,221
Percent Time Used103
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-084
DUSTROL, INC. (0.39)
RYAN CONSTRUCTION, INC. (1.89)
VENUS CONSTRUCTION (5.70)
F & W ELECTRICAL CONTRACTORS, INC. (1.42)
HOUSTON SAWING & DRILLING (0.00)
PREMIER PAVING, LTD. (9.21)
FLASHER EQUIPMENT COMPANY (0.33)
DRILL TECH DRILLING & SHORING, INC. (3.52)
SBM FARMS (3.05)
SCOTT DERR PAINTING CO, LLC (0.01)
CDM HOLDINGS, LLC (0.21)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.76)
DIAMOND SURFACE, INC. (0.02)
ODUM SERVICES, L.P. (0.08)
MARIO SINACOLA & SONS EXCAVATING, INC. (2.70)
WOOD WATERING SERVICES, LLC (0.00)
NOBLES ROAD CONSTRUCTION, INC. (10.65)
HERDEZ TRUCKING, INC. (0.81)
HAYWARD BAKER, INC. (0.10)
AR DANIEL CONSTRUCTION SERVICES, INC. (0.09)
PRECISION DRILLING CO. (0.03)
COWBOY AND SONS LP DBA COWBOY TRUCKING (0.57)
BREDA COMPANY, INC. (0.79)
ANCORTEX, INC. (0.17)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.18)
BADGER DAYLIGHTING CORP. (0.01)
BOWMAN ENGINEERING & CONSULTING, INC. (0.01)
Contract #03173201
Totals75522594.12755543.0979375529.3599.9

CountyMCCULLOCH
HighwayUS 87
FromBRADY CREEK BRIDGE
To.4 MILES WEST OF US 283
CSJ0070-06-041
Proj IDNH 2B20(071)
Work TypeREHABILITATION OF EXISTING ROAD
 
3.5476955456.065293017.8976.0
CountyMCCULLOCH
HighwayUS 87
FromAT JACQUELINE RUFFIN ROAD
To.
CSJ0070-06-052
Proj IDNH 2B20(071)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
100625.000.000.0
Work Order01-14-21
Work Began03-15-21
Work Completed
Time Computed03-15-21
Contract Working Days298
Addl Days Granted0
Working Days Charged133
Percent Time Used44
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-06-041
JR WEST TEXAS CONCRETE LLC (10.63)
L&H ELECTRICAL, LLC (3.87)
D. I. J. CONSTRUCTION, INC. (2.97)
DALLAS LITE AND BARRICADE, INC. (0.60)
TIGHT LINE CONSTRUCTION, LLC (0.51)
MPB, INC. (0.67)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.03)
WEST TEXAS ROCK RESOURCES, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.08)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.33)
CHEROKEE SERVICES (0.67)
Contract #12203209
Totals7056081.06442064.045293017.8975.0

CountyCOMANCHE ETC
HighwayUS 67 ETC
From0.5 MILES WEST OF INDIAN CREEK
ToBROWN C/L
CSJ0079-02-052
Proj IDNH 2B20(309)
Work TypeSEAL COAT
 
329.77611314209.2110847901.8795.8
Work Order03-01-21
Work Began04-06-21
Work Completed
Time Computed04-06-21
Contract Working Days68
Addl Days Granted38
Working Days Charged104
Percent Time Used98
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0079-02-052
CENTERLINE TECHNOLOGIES, LLC (7.62)
BARRICADES PLUS, LLC (1.44)
K. L. DURHAM CONSTRUCTION, L.L.C. (2.25)
D. I. J. CONSTRUCTION, INC. (1.84)
RED SIXTEEN CONSTRUCTION, INC (1.14)
LINEAR TRAFFIC MARKINGS LLC (0.00)
Contract #11203007
Totals11314209.21115153.4010847901.8795.8

CountyCOMANCHE
HighwayUS 67
FromUS 67
ToAT FM 3381
CSJ0079-03-051
Proj IDF 2021(766)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
850894.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0079-03-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213255
Totals850894.760.000.000.0

CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-142
Proj IDSTP 2018(829)
Work TypeRECONSTRUCT URBAN ROADWAY
 
1.47611116710.558551866.4676.9
CountyEASTLAND
HighwayUS 183
FromRISING STAR NCL
ToNEAR SH 36
CSJ0127-02-146
Proj IDSTP 2018(212)
Work TypeACQUISITION AND UTILITY ADJUSTMENTS
 
0.8093038242.002932114.4796.5
CountyEASTLAND
HighwayUS 183
FromNEAR SH 36
ToNEAR RISING STAR SCL
CSJ0127-02-147
Proj IDSTP 2018(211)
Work TypeUTILITY ADJUSTMENTS
 
0.6672732059.003993147.6999.9
Work Order06-11-18
Work Began08-17-18
Work Completed
Time Computed08-10-18
Contract Working Days790
Addl Days Granted103
Working Days Charged779
Percent Time Used87
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-142
F & W ELECTRICAL CONTRACTORS, INC._(SAN ANTONIO) (1.37)
TTG UTILITIES, LP (23.02)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
W.S. CONSTRUCTION COMPANY (24.13)
FLASHER EQUIPMENT COMPANY (0.97)
NIXON ENGINEERING (0.00)
DALLAS LITE AND BARRICADE, INC. (0.01)
Contract #05183221
Totals16887011.55301301.8315477128.6291.6

CountyEASTLAND
HighwayUS 183
FromCR 173
To5 MI. N OF RISING STAR NCL
CSJ0127-02-148
Proj IDF 2021(747)
Work TypeOVERLAY
 
5.4321372072.3074949.165.4
Work Order08-18-21
Work Began10-25-21
Work Completed
Time Computed09-17-21
Contract Working Days39
Addl Days Granted0
Working Days Charged1
Percent Time Used2
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-148
STRIPE-A-ZONE, LLC (3.63)
TEXAS TRAFFIC AND BARRICADE, LLC (0.51)
Contract #07213036
Totals1372072.3074949.1674949.165.4

CountyBROWN
HighwayUS 377
From0.037 MI S OF CR 199
ToMCCULLOCH C/L
CSJ0128-01-113
Proj IDF 2021(449)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
15.53999853.22101367.1499.9
CountyBROWN
HighwayUS 377
FromFM 45
ToMCCULLOCH C/L
CSJ0128-01-116
Proj IDF 2021(450)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
16.337891457.8080000.008.9
Work Order08-18-21
Work Began09-21-21
Work Completed
Time Computed09-17-21
Contract Working Days132
Addl Days Granted0
Working Days Charged12
Percent Time Used9
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-113
PINNACLE GRINDING AND GROOVING LLC (1.84)
SAFETY COP, LLC (2.21)
STRIPE-A-ZONE, INC. (6.51)
Contract #07213218
Totals991311.02173361.74181367.1418.2

CountyEASTLAND
HighwaySH 36
From0.003 MI. W. OF E MILLS ST
ToCOMANCHE C/L
CSJ0182-01-017
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.924290281.85536337.5099.9
CountyCOMANCHE
HighwaySH 36
FromEASTLAND C/L
To0.322 MI. NW OF BARNES AVE
CSJ0182-02-043
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
20.421818111.090.000.0
CountyCOMANCHE
HighwaySH 36
FromUS 67
ToHAMILTON C/L
CSJ0183-01-044
Proj IDF 2021(451)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
22.272989791.080.000.0
Work Order05-14-21
Work Began00-00-00
Work Completed
Time Computed06-13-21
Contract Working Days176
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0182-01-017
SAFETY COP, LLC (5.70)
Contract #04213221
Totals2098184.020.00536337.5025.5

CountyCOMANCHE
HighwaySH 36
FromEASTLAND C/L
ToFM 1477
CSJ0182-02-046
Proj IDF 2021(566)
Work TypeOVERLAY
 
10.0002320588.822393380.8499.9
Work Order06-10-21
Work Began08-23-21
Work Completed
Time Computed07-11-21
Contract Working Days34
Addl Days Granted0
Working Days Charged34
Percent Time Used100
Contractor(s)
NORTHEASTERN PAVERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0182-02-046
CONTRACTORS SERVICE COMPANY (0.20)
FLAT LINE, INC. (2.62)
PINNACLE GRINDING AND GROOVING LLC (0.75)
WEST TEXAS ROCK RESOURCES, LLC (1.21)
Contract #05213020
Totals2320588.8228307.202393380.8499.9

CountyCOMANCHE
HighwaySH 36
FromAT US 67
To.
CSJ0183-01-049
Proj IDF 2021(452)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
68732.930.000.0
CountyEASTLAND
HighwaySH 16
FromAT FM 8
To.
CSJ0288-03-033
Proj IDF 2021(452)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
130520.810.000.0
Work Order05-27-21
Work Began00-00-00
Work Completed
Time Computed08-25-21
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SEFBO PIPELINE BRIDGE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-049
SERVICES UNLIMITED (10.61)
WG ENGINEERING & CONSTRUCTION, LLC (43.07)
Contract #04213028
Totals199253.740.000.000.0

CountyCOMANCHE
HighwaySH 36
From0.3 MILES NORTH OF FM 1702
To0.34 MILES SOUTH OF FM 1702
CSJ0183-01-053
Proj IDF 2021(767)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.650999893.620.000.0
CountyCOMANCHE
HighwaySH 36
From1.87 MI N OF FM 1702
To.4 MI S OF FM 1702
CSJ0183-01-055
Proj IDF 2021(767)
Work TypeOVERLAY
 
2.140557701.880.000.0
Work Order09-16-21
Work Began00-00-00
Work Completed
Time Computed10-16-21
Contract Working Days114
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213047
Totals1557595.500.000.000.0

CountyLAMPASAS
HighwayUS 190
FromAT FM 2313
To.
CSJ0231-01-057
Proj IDC 231-1-57
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.043387266.750.000.0
Work Order09-29-21
Work Began00-00-00
Work Completed
Time Computed10-29-21
Contract Working Days51
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0231-01-057
BARRON ENVIRONMENTAL, L.P. (0.35)
DALLAS LITE AND BARRICADE, INC. (2.12)
L&H ELECTRICAL, LLC (27.59)
D. I. J. CONSTRUCTION, INC. (3.81)
Contract #05213232
Totals387266.750.000.000.0

CountyEASTLAND
HighwaySH 6
FromSL 389
To0.18 MI. N. OF CRESSENT ST
CSJ0257-04-029
Proj IDF 2022(007)
Work TypeSUPER-2 HIGHWAY
 
8.94710587368.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09213204
Totals10587368.260.000.000.0

CountyCOMANCHE
HighwaySH 6
FromSH 16 NORTH
ToEAST CITY LIMIT OF DELEON
CSJ0257-05-045
Proj IDC 257-5-45
Work TypeWIDEN NON-FREEWAY
 
1.9319728370.403135617.4132.2
CountyCOMANCHE
HighwaySH 6
FromSH 16 NORTH
ToEAST CITY LIMIT OF DELEON
CSJ0257-05-048
Proj IDROW 257-5-48
Work TypeRIGHT OF WAY
 
1.931558860.00647710.0099.9
Work Order07-20-20
Work Began10-05-20
Work Completed
Time Computed09-18-20
Contract Working Days688
Addl Days Granted1
Working Days Charged247
Percent Time Used35
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-045
SOUTHERN CROSS CONTRACTORS, LLC (0.64)
F & W ELECTRICAL CONTRACTORS, INC. (7.41)
FLASHER EQUIPMENT COMPANY (1.25)
B & L CONSTRUCTION COMPANY (2.33)
SITE BARRICADES (0.00)
BUYERS BARRICADES, INC. (0.04)
B & L MANHOLE SERVICE (0.01)
BCAC UNDERGROUND LLC (0.00)
TEXAS ALTERNATIVE GRASSER INCORPORATED (0.03)
Contract #05203204
Totals10287230.40131297.523783327.4136.7

CountyCOMANCHE ETC
HighwaySH 6
FromEASTLAND COUNTY LINE
ToSH 16
CSJ0257-05-046
Proj IDNH 2020(457)
Work TypeSUPER-2 HIGHWAY
 
18.16413793112.534461991.3932.3
Work Order06-09-20
Work Began09-08-20
Work Completed
Time Computed08-08-20
Contract Working Days368
Addl Days Granted0
Working Days Charged158
Percent Time Used42
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-046
BROCK CONSTRUCTION, LLC (1.32)
CONTRACTORS SERVICE COMPANY (0.37)
D. I. J. CONSTRUCTION, INC. (2.43)
STRIPE-A-ZONE, INC. (0.27)
SOUTHERN CROSS CONTRACTORS, LLC (0.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.37)
W. S. CONSTRUCTION COMPANY (5.68)
DIIBS SPECIALISTS, LLC (2.59)
DALLAS LITE AND BARRICADE, INC. (1.44)
BECK-REIT & SONS, LTD. (0.84)
Contract #04203204
Totals13793112.53353113.214461991.3932.3

CountyCOMANCHE
HighwaySH 16
FromAT SABANNA RIVER
To.
CSJ0288-01-039
Proj IDBR 2022(129)
Work TypeBRIDGE MAINTENANCE
 
114840.870.000.0
CountyBROWN
HighwayVA
FromDISTRICWIDE
To.
CSJ0923-00-064
Proj IDC 923-00-64
Work TypeBRIDGE MAINTENANCE
 
1.0001440758.430.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days204
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0288-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213013
Totals1555599.300.000.000.0

CountyEASTLAND
HighwaySH 16
FromSH 16 AT BEAR CREEK
To.
CSJ0288-03-032
Proj IDBR 2021(588)
Work TypeBRIDGE REPLACEMENT
 
1511011.260.000.0
CountyEASTLAND
HighwayCR
FromCR 136 AT DINNER BRANCH DRAW
To.
CSJ0923-09-064
Proj IDBR 2020(703)
Work TypeBRIDGE REPLACEMENT
 
387878.730.000.0
Work Order07-20-21
Work Began00-00-00
Work Completed
Time Computed10-18-21
Contract Working Days272
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0288-03-032
HODGES AND SON CONSTRUCTION COMPANY, INC. (4.81)
MORRIS COUNTY CONTRACTORS, L.L.C. (3.96)
PEACHTREE CONSTRUCTION, LTD. (8.56)
PENHALL COMPANY (0.31)
STRIPING TECHNOLOGY, L.P. (1.85)
TEXAS TRAFFIC AND BARRICADE, LLC (2.28)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.27)
Contract #06213223
Totals1898889.990.000.000.0

CountyMILLS
HighwaySH 16
FromAT US 84
To.
CSJ0289-02-018
Proj IDF 2021(453)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
75099.4216958.5022.5
CountyCOLEMAN
HighwayFM 3425
FromAT SH 206
To.
CSJ0452-07-008
Proj IDF 2021(453)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
112485.090.000.0
Work Order05-27-21
Work Began10-19-21
Work Completed
Time Computed08-25-21
Contract Working Days51
Addl Days Granted0
Working Days Charged40
Percent Time Used78
Contractor(s)
SEFBO PIPELINE BRIDGE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0289-02-018
SERVICES UNLIMITED (6.66)
WG ENGINEERING & CONSTRUCTION, LLC (31.13)
Contract #04213031
Totals187584.5116958.5016958.509.0

page 1 | page 2