Monthly State Let Construction Report For Childress District As Of Apr 12, 2024 Page 1 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWHEELER
HighwayUS 83
From@ SWEETWATER CREEK
To.
CSJ0030-08-038
Proj IDBR 2023(936)
Work TypeBRIDGE REPLACEMENT
 
5746110.50882847.9615.3
CountyWHEELER
HighwayFM 2473
From@ NORTH FORK RED RIVER
To.
CSJ2051-01-013
Proj IDBR 2023(936)
Work TypeBRIDGE REPLACEMENT
 
8517304.00115000.001.3
Work Order08-03-23
Work Began03-18-24
Work Completed
Time Computed09-03-23
Contract Working Days354
Addl Days Granted0
Working Days Charged14
Percent Time Used3
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-038
MORRIS COUNTY CONTRACTORS, L.L.C. (0.60)
FC TRAFFIC CONTROL, INC. (0.19)
JB PINNACLE GROUP, LLC (1.76)
LANCO TURF & SEEDING, INC. (0.02)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.76)
PRIMATE CONSTRUCTION, LP (0.14)
TRP CONSTRUCTION GROUP, LLC (0.77)
JVH4 SERVICES, LLC (0.18)
Contract #06233606
Totals14263414.50917370.00997847.966.9

CountyWHEELER
HighwayUS 83
FromCR 15, SOUTH
ToCOLLINGSWORTH C/L
CSJ0031-01-022
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
2011072.012111755.3999.9
CountyCOLLINGSWORTH
HighwayUS 83
FromWHEELER C/L, SOUTH
To7.551 MILES
CSJ0031-02-029
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
6427152.765619524.5687.4
CountyCOLLINGSWORTH
HighwayUS 83
From7.551 MILES SOUTH OF WHEELER C/L, S
ToFM 1439
CSJ0031-03-044
Proj IDF 2023(283)
Work TypeSUPER-2 HIGHWAY
 
3753664.453742782.4999.7
Work Order01-12-23
Work Began03-13-23
Work Completed
Time Computed03-13-23
Contract Working Days237
Addl Days Granted2
Working Days Charged150
Percent Time Used63
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0031-01-022
FC TRAFFIC CONTROL, INC. (0.40)
H & F TRUCKING (0.41)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.21)
HJC FARMS, INC. (1.87)
JENNINGS TRUCKING SERVICE, INC. (0.41)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.22)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.06)
TEXOP CONSTRUCTION (0.56)
WEST INFRASTRUCTURE CONSTRUCTION, LLC (0.24)
MOBILE ENTERPRISES, INC. (0.11)
Contract #12223209
Totals12191889.222016451.4911474062.4494.1

CountyCHILDRESS
HighwayUS 83
From1440' SOUTH OF US 62, NORTH
To1795' NORTH OF SH 256
CSJ0031-05-046
Proj IDF 2023(052)
Work TypeOVERLAY
 
2152293.052118432.0898.4
CountyCHILDRESS
HighwayUS 62
FromCOTTLE C/L, NORTH
ToFM 164
CSJ0032-01-034
Proj IDF 2023(052)
Work TypeOVERLAY
 
5313966.645907972.1999.9
Work Order10-06-22
Work Began04-27-23
Work Completed
Time Computed04-03-23
Contract Working Days101
Addl Days Granted20
Working Days Charged115
Percent Time Used95
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-046
BAHENA CONSTRUCTION CO.,INC. (2.86)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.15)
CONTRACTORS SERVICE, LTD. (0.19)
TEXOP CONSTRUCTION (0.28)
DUSTIN ALLEN, INC. (4.15)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.88)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.29)
ALAMO BROTHERS CONCRETE INC (0.27)
Contract #09223007
Totals7466259.6917267.258026404.2799.9

CountyDONLEY
HighwayUS 287
FromARMSTRONG C/L, EAST
ToCLARENDON ECL (SBL)
CSJ0042-06-076
Proj IDF 2024(069)
Work TypeOVERLAY
 
6446300.5573326.001.1
Work Order10-23-23
Work Began00-00-00
Work Completed
Time Computed10-23-23
Contract Working Days95
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-076
TRP CONSTRUCTION GROUP, LLC (2.92)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24)
BARRICADES UNLIMITED (0.45)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.33)
Contract #09233036
Totals6446300.5538550.0073326.001.1

CountyHALL
HighwayUS 287
From348' SOUTH OF 2ND STREET, SOUTH
To1.718 MILES
CSJ0042-09-124
Proj IDC 42-9-124
Work TypeNEW LOCATION FREEWAY
 
13478722.7514867047.4999.9
Work Order06-22-21
Work Began08-17-21
Work Completed
Time Computed06-22-21
Contract Working Days420
Addl Days Granted53
Working Days Charged481
Percent Time Used101
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-124
BARRICADES UNLIMITED (0.98)
J. H. ODEN CONTRACTING COMPANY (0.82)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36)
URBAN INFRACONSTRUCTION LLC (3.99)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
WILLIS ELECTRIC CO., LP (0.89)
HOLMES CONSTRUCTION CO., L.P. (0.41)
WILLIAMS ROAD, LLC (0.11)
B&B TRUCKING (0.44)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.78)
TORO BRAVO CONSTRUCTION, LLC (0.08)
TORO BRAVO CONSTRUCTION, LLC (0.37)
MCINTOSH FLOW SERVICE LLC (0.07)
PANHANDLE SWEEPING & MAINTENANCE, LLC (0.02)
A.W. THEIS (0.07)
FUQUAY, INC. (7.35)
TEXAS GUARDRAIL CONTRACTORS LLC (0.27)
POPWELL, INC (0.14)
PINNACLE GRINDING AND GROOVING LLC (0.06)
STRAIGHT LINE SAWING & SEALING, INC. (0.03)
TRP CONSTRUCTION GROUP, LLC (0.55)
RK HALL, LLC (13.85)
GARY A. CRAIN, INC. (0.03)
Contract #05213206
Totals13478722.75211135.0514867047.4999.9

CountyCHILDRESS
HighwayUS 287
From2732' W OF FM 164 (NBL & SBL) (RAMPS), E
ToCHILDRESS WCL
CSJ0042-12-086
Proj IDF 2024(640)
Work TypeREHABILITATION OF EXISTING ROAD
 
15308760.06208800.001.3
Work Order03-14-24
Work Began00-00-00
Work Completed
Time Computed03-14-24
Contract Working Days159
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243212
Totals15308760.06208800.00208800.001.3

CountyCHILDRESS
HighwayUS 287
From335' EAST OF FM 2530, EAST
ToHARDEMAN C/L (NBL)
CSJ0043-01-083
Proj IDBR 2023(360)
Work TypeOVERLAY
 
6175663.876282098.5599.9
Work Order01-04-23
Work Began04-05-23
Work Completed
Time Computed01-04-23
Contract Working Days62
Addl Days Granted60
Working Days Charged127
Percent Time Used104
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-083
FC TRAFFIC CONTROL, INC. (0.40)
TEXOP CONSTRUCTION (0.89)
ALAMO BROTHERS CONCRETE INC (1.90)
HJC FARMS, INC. (5.85)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.78)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.28)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24)
Contract #12223035
Totals6175663.8718144.006282098.5599.9

CountyHARDEMAN
HighwayUS 287
From65' WEST OF FM 2568, EAST
ToWILBARGER C/L
CSJ0043-04-083
Proj IDF 2024(638)
Work TypeOVERLAY
 
8059390.88341157.014.2
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed02-02-24
Contract Working Days79
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-04-083
A BROTHERS MILLING, LLC (0.41)
DUSTIN ALLEN, INC. (1.37)
FC TRAFFIC CONTROL, INC. (0.40)
JENNINGS TRUCKING SERVICE, INC. (0.55)
TRP CONSTRUCTION GROUP, LLC (2.12)
MOBILE ENTERPRISES, INC. (1.10)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.56)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.24)
W. S. CONSTRUCTION COMPANY (0.43)
Contract #01243211
Totals8059390.88341157.01341157.014.2

CountyHARDEMAN
HighwaySS 133
From@ LP 285
To.
CSJ0043-10-007
Proj IDSTP 2023(825)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
34272.0033872.0098.8
CountyHARDEMAN
HighwaySL 285
From@ DRAW
To.
CSJ0043-23-008
Proj IDBR 2023(824)
Work TypeBRIDGE REPLACEMENT
 
0.0351836659.001814100.0098.7
Work Order07-19-23
Work Began08-21-23
Work Completed
Time Computed07-19-23
Contract Working Days134
Addl Days Granted0
Working Days Charged124
Percent Time Used92
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-10-007
FC TRAFFIC CONTROL, INC. (0.54)
TORO BRAVO CONSTRUCTION, LLC (0.75)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.51)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.90)
HOUSTON SAWING & DRILLING (0.41)
Contract #06233028
Totals1870931.00165181.001847972.0098.7

CountyHALL
HighwaySH 86
FromINTERSECTION OF SH 70, NORTH
ToFM 657
CSJ0105-02-023
Proj IDBR 2024(528)
Work TypeOVERLAY
 
8.2706392222.95455493.207.1
CountyHALL
HighwaySH 70
FromTURKEY NCL, NORTH
ToINTERSECTION OF SH 86
CSJ0105-02-026
Proj IDF 2024(410)
Work TypeOVERLAY
 
247566.550.000.0
Work Order11-16-23
Work Began03-18-24
Work Completed
Time Computed11-16-23
Contract Working Days89
Addl Days Granted0
Working Days Charged8
Percent Time Used8
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0105-02-023
SURFACE PREPARATION TECHNOLOGIES, LLC (0.35)
BARRICADES UNLIMITED (0.56)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
TRP CONSTRUCTION GROUP, LLC (2.19)
Contract #10233029
Totals6639789.50413850.20455493.206.8

CountyDICKENS
HighwayUS 82
From1186' EAST OF DICKENS ECL, EAST
To8.23 MILES (WBL)
CSJ0132-01-055
Proj IDC 132-1-55
Work TypeOVERLAY
 
11319017.730.000.0
Work Order01-11-24
Work Began00-00-00
Work Completed
Time Computed01-11-24
Contract Working Days99
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0132-01-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233009
Totals11319017.730.000.000.0

CountyKING
HighwayUS 82
From0.5 MILES WEST OF SH 222, EAST
ToKNOX C/L
CSJ0133-01-049
Proj IDF 2022(352)
Work TypeREHABILITATION OF EXISTING ROAD
 
5768975.826419323.8699.9
Work Order02-16-22
Work Began09-30-22
Work Completed
Time Computed02-16-22
Contract Working Days141
Addl Days Granted3
Working Days Charged184
Percent Time Used127
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-01-049
STRIPING TECHNOLOGY, L.P. (3.44)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18)
WEST TEXAS ROCK RESOURCES, LLC (0.16)
CONTRACTORS SERVICE, LTD. (0.42)
Contract #01223042
Totals5768975.82145830.956419323.8699.9

CountyWHEELER
HighwayIH 40
From2000' WEST OF FM 2474, EAST
ToUS 83
CSJ0275-12-083
Proj IDSTP 2023(511)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1036090.50965012.7693.1
CountyWHEELER
HighwayIH 40
FromUS 83, EAST
ToCR 18
CSJ0275-13-073
Proj IDSTP 2023(511)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
393989.50378800.0196.1
CountyWHEELER
HighwayIH 40
FromCR 18, EAST
ToOKLAHOMA STATE LINE
CSJ0275-13-074
Proj IDSTP 2023(511)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2303739.002294575.2699.6
Work Order04-19-23
Work Began11-06-23
Work Completed
Time Computed05-19-23
Contract Working Days172
Addl Days Granted0
Working Days Charged86
Percent Time Used50
Contractor(s)
GRATIOT CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-083
FC TRAFFIC CONTROL, INC. (0.56)
FOX CONTRACTING KY, INC. (18.01)
Contract #03233010
Totals3733819.00382340.003638388.0397.4

CountyWHEELER
HighwayIH 40
FromGRAY C/L, EAST
ToUS 83
CSJ0275-12-085
Proj IDF 2024(846)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3449940.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days193
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243026
Totals3449940.400.000.000.0

CountyHALL
HighwaySH 70
From@ MULBERRY CREEK
To.
CSJ0311-02-033
Proj IDBR 2023(938)
Work TypeBRIDGE REPLACEMENT
 
0.1919334727.255019931.8853.7
Work Order07-26-23
Work Began11-08-23
Work Completed
Time Computed07-26-23
Contract Working Days468
Addl Days Granted0
Working Days Charged68
Percent Time Used14
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0311-02-033
JB PINNACLE GROUP, LLC (1.60)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.05)
PENHALL COMPANY (0.15)
TRP CONSTRUCTION GROUP, LLC (0.82)
FC TRAFFIC CONTROL, INC. (0.19)
LANCO TURF & SEEDING, INC. (0.46)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.53)
TORO BRAVO CONSTRUCTION, LLC (0.22)
TORO BRAVO CONSTRUCTION, LLC (0.42)
Contract #06233609
Totals9334727.25682266.955019931.8853.7

CountyCHILDRESS
HighwayUS 62
From@ BUCK CREEK
To.
CSJ0381-01-017
Proj IDBR 2024(641)
Work TypeBRIDGE REPLACEMENT
 
6310485.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-24
Work Began00-00-00
Work Completed
Time Computed03-14-24
Contract Working Days249
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0381-01-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243010
Totals6310485.590.000.000.0

CountyCOLLINGSWORTH
HighwayFM 338
FromUS 83, EAST
ToCR Z
CSJ0449-01-022
Proj IDC 449-1-22
Work TypeWIDEN NON-FREEWAY
 
4582258.602311581.6550.4
CountyCOLLINGSWORTH
HighwayFM 338
FromCR Z, EAST
ToCR 270
CSJ0449-01-023
Proj IDF 2023(686)
Work TypeWIDEN NON-FREEWAY
 
2540318.001655760.6865.1
Work Order06-14-23
Work Began08-01-23
Work Completed
Time Computed07-14-23
Contract Working Days182
Addl Days Granted3
Working Days Charged121
Percent Time Used65
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-022
TRP CONSTRUCTION GROUP, LLC (2.20)
HJC FARMS, INC. (4.26)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.30)
FC TRAFFIC CONTROL, INC. (0.37)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.30)
H & F TRUCKING (4.01)
Contract #05233212
Totals7122576.60106365.373967342.3355.7

CountyCOLLINGSWORTH
HighwayFM 338
FromCR 270, EAST
ToOKLAHOMA STATE LINE
CSJ0449-01-024
Proj IDSTP 2024(639)HES
Work TypeWIDEN NON-FREEWAY
 
4695146.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-21-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days109
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0449-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243024
Totals4695146.200.000.000.0

CountyKNOX
HighwayFM 267
FromUS 82, SOUTH
ToSH 222
CSJ0538-01-027
Proj IDSTP 2023(580)HES
Work TypeWIDEN NON-FREEWAY
 
6913833.35921335.0013.3
Work Order05-17-23
Work Began07-17-23
Work Completed
Time Computed05-17-23
Contract Working Days177
Addl Days Granted0
Working Days Charged77
Percent Time Used43
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0538-01-027
CONTRACTORS SERVICE, LTD. (0.48)
DUSTIN ALLEN, INC. (0.59)
LINEAR TRAFFIC MARKINGS LLC (1.24)
WEST TEXAS ROCK RESOURCES, LLC (0.24)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.42)
W. S. CONSTRUCTION COMPANY (5.35)
Contract #04233016
Totals6913833.350.00921335.0013.3

CountyBRISCOE ETC
HighwaySH 256 ETC
FromSH 86, EAST
To10 MILES
CSJ0541-01-033
Proj IDF 2024(074)
Work TypeSEAL COAT
 
7556670.111329895.7517.5
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed11-16-23
Contract Working Days57
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0541-01-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233208
Totals7556670.11194331.711329895.7517.5

page 1 | page 2