Monthly State Let Construction Report For Childress District As Of Aug 23, 2019 Page 1 Of 2

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDONLEY
HighwayUS 287
From500 FT E OF CLARENDON ECL, E
To1025 FT E OF HEDLEY WCL(NBL)
CSJ0042-07-066
Proj IDNH 2019(592)
Work TypeASPHALTIC CONCRETE OVERLAY
 
12.7144527707.0226214.000.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-19-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-07-066
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02193234
Totals4527707.020.0026214.000.5

CountyDONLEY
HighwayUS 287
FromHEDLEY NCL, SOUTH
To5,216.32 FT
CSJ0042-07-067
Proj IDC 42-7-67
Work TypeREHABILITATION OF EXISTING ROAD
 
1.1407991425.562792865.4334.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-18
Work Began02-04-19
Work Completed
Time Computed00-00-00
Contract Working Days162
Addl Days Granted2
Working Days Charged91
Percent Time Used55
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-07-067
BARRICADES UNLIMITED (4.07)
SIGNAL SERVICES GROUP INC. (1.56)
WOLFE CONSTRUCTION GROUP, INC. (0.18)
WEST TEXAS UTILITY CONTRACTORS, INC. (0.62)
PRIMATE CONSTRUCTION, LP (1.22)
BOWMAN ENGINEERING & CONSULTING, INC. (1.40)
Contract #06183220
Totals7991425.56551311.152792865.4334.9

CountyHARDEMAN
HighwaySH 6
FromRED RIVER BRIDGE, S
ToRANDOLPH ROAD
CSJ0097-02-039
Proj IDSTP 2019(589)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.7903994436.142205063.7355.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-16-19
Work Began06-10-19
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged36
Percent Time Used40
Contractor(s)
JCCC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0097-02-039
TEXAS PANHANDLE CONSTRUCTION, INC. (1.66)
DIRECT TRAFFIC CONTROL, INC. (1.59)
WEST TEXAS ROCK RESOURCES, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INC. (0.32)
Contract #03193214
Totals3994436.141542700.372205063.7355.2

CountyDICKENS
HighwaySH 70
FromSH 70 @ DUCK CREEK
To.
CSJ0106-01-039
Proj IDBR 2019(015)
Work TypeREPLACEMENT OF EXISTING BRIDGE
 
0.1281626092.361473484.3090.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-18
Work Began12-17-18
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged126
Percent Time Used94
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0106-01-039
WOLFE CONSTRUCTION GROUP, INC. (0.23)
CONTRACTORS SERVICE COMPANY (0.89)
BARRICADES UNLIMITED (0.51)
TEXOP CONSTRUCTION (0.44)
DUSTIN ALLEN, INC. (1.30)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.20)
BOWMAN ENGINEERING & CONSULTING, INC. (0.31)
PENHALL COMPANY (0.26)
Contract #09183022
Totals1626092.3659796.551473484.3090.6

CountyDICKENS
HighwayUS 82
From0.2 MI EAST OF DICKENS ECL, E
To8.236 MI (EBL)
CSJ0132-01-048
Proj IDNH 2019(113)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
8.2362969974.513081888.1799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-18
Work Began05-10-19
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged48
Percent Time Used71
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0132-01-048
BARRICADES UNLIMITED (0.56)
WOLFE CONSTRUCTION GROUP, INC. (0.24)
WEST TEXAS ROCK RESOURCES, LLC (0.52)
DUSTROL, INC. (0.06)
DIIBS SPECIALISTS (2.97)
FLAT LINE, INC. (1.03)
Contract #10183214
Totals2969974.5148021.723081888.1799.9

CountyKNOX
HighwayUS 82
FromKING C/L, EAST
To500' WEST OF SH 6
CSJ0133-02-025
Proj IDNH 2019(590)
Work TypeSUPER 2
 
11.50311182988.2235554.050.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-06-19
Work Began07-16-19
Work Completed
Time Computed00-00-00
Contract Working Days204
Addl Days Granted0
Working Days Charged13
Percent Time Used6
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-02-025
W. S. CONSTRUCTION COMPANY (5.54)
A. L. CONSTRUCTION, LLC (3.64)
CONTRACTORS SERVICE COMPANY (0.23)
HJC FARMS, INC. (0.96)
LANCO TURF & SEEDING, INC. (0.38)
MARCOM"S MOWING SERVICE, LLC (0.22)
NIXON ENGINEERING (0.24)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
ZACK BURKETT CO. (50.34)
Contract #04193208
Totals11182988.2227554.0535554.050.3

CountyKNOX
HighwayUS 82
FromSTEWART STREET, EAST
ToCHURCH STREET
CSJ0133-02-027
Proj IDSTP 2019(366)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.064225131.000.000.0
CountyKNOX
HighwayUS 82
FromSH 6, EAST
To578' WEST OF FM267 (N INTERSECTION)
CSJ0133-03-046
Proj IDNH 2019(833)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.2146356476.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days274
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-02-027
A. L. CONSTRUCTION, LLC (3.99)
BARRICADES UNLIMITED (2.80)
CONTRACTORS SERVICE COMPANY (0.95)
LANCO TURF & SEEDING, INC. (0.27)
WEST TEXAS ROCK RESOURCES, LLC (0.42)
ZACK BURKETT CO. (36.10)
Contract #05193221
Totals6581607.800.000.000.0

CountyKNOX
HighwayUS 82
FromWESTBOUND, EAST OF BENJAMIN
To.
CSJ0133-03-047
Proj IDSTP 2019(772)
Work TypeSAFETY REST AREA
 
0.1012268300.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-03-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05193025
Totals2268300.000.000.000.0

CountyMOTLEY
HighwayUS 62
From@ HACKBERRY CREEK
To.___________________________7
CSJ0146-01-051
Proj IDBR 1802(481)
Work TypeREPLACEMENT OF EXISTING BRIDGE FAC
 
0.7722119655.502227993.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-18
Work Began10-19-18
Work Completed
Time Computed00-00-00
Contract Working Days158
Addl Days Granted30
Working Days Charged141
Percent Time Used75
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-01-051
BARRICADES UNLIMITED (1.48)
COMEN ENTERPRISE LLC (1.71)
CONTRACTORS SERVICE COMPANY (1.13)
PEACHTREE CONSTRUCTION, LTD. (20.81)
PENHALL COMPANY (0.54)
WOLFE CONSTRUCTION GROUP, INC. (0.37)
BOWMAN ENGINEERING & CONSULTING, INC. (0.37)
DUSTROL, INC. (0.45)
Contract #08183256
Totals2119655.5036752.002227993.4699.9

CountyFOARD
HighwayUS 70
FromCR 195, EAST
ToWILBARGER C/L
CSJ0146-06-030
Proj IDSTP 2019(404)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
3.2754375237.33515537.5811.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-20-19
Work Began07-08-19
Work Completed
Time Computed00-00-00
Contract Working Days79
Addl Days Granted0
Working Days Charged18
Percent Time Used22
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-06-030
ANTIGO CONSTRUCTION, INC. (0.91)
BARRICADES UNLIMITED (1.29)
TEXOP CONSTRUCTION (1.83)
CONTRACTORS SERVICE COMPANY (0.53)
WEST TEXAS ROCK RESOURCES, LLC (0.33)
WOLFE CONSTRUCTION GROUP, INC. (0.04)
SAENZ TRANSPORT, LLC (0.19)
Contract #01193214
Totals4375237.33515537.58515537.5811.7

CountyCOTTLE
HighwayFM 1037
From8TH STREET, WEST
ToUS 62/83
CSJ0146-08-053
Proj IDC 146-8-53
Work TypeREPAIR SIDEWALK/INSTALL ILLUMINATIO
 
0.062229715.00215387.9898.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began07-09-18
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted7
Working Days Charged60
Percent Time Used139
Contractor(s)
INSURORS INDEMNITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0146-08-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183032
Totals229715.000.00215387.9898.1

CountyKNOX
HighwayUS 277
FromBAYLOR C/L, SOUTH
To2.330 MILES
CSJ0157-02-047
Proj IDNH 2018(624)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
12.3906559485.056486761.0998.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-07-18
Work Began03-07-19
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged86
Percent Time Used95
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-02-047
BARRICADES UNLIMITED (1.63)
CONTRACTORS SERVICE COMPANY (0.25)
DOUBLE A CONTRACTING (0.53)
HJC FARMS, INC. (8.34)
WOLFE CONSTRUCTION GROUP, INC. (0.31)
Contract #02183202
Totals6559485.05371017.306486761.0998.8

CountyWHEELER ETC
HighwayIH 40 ETC
From@ COUNTY LINE ROAD
To.
CSJ0275-12-074
Proj IDBR 2019(644)
Work TypeBRIDGE MAINTENANCE
 
0.0075409042.32636500.0011.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-08-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days208
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-074
ALAMO BROTHERS CONCRETE INC (3.10)
DUSTY ALLEN, INC. (4.10)
SOUTH TEXAS PAINTING COMPANY (0.81)
TOTAL HIGHWAY MAINTENANCE, LLC (1.03)
VENTURE CONSTRUCTION, INC (2.94)
Contract #03193014
Totals5409042.32636500.00636500.0011.7

CountyWHEELER
HighwaySH 152
From0.065 MILES EAST OF US 83
ToOKLAHOMA STATE LINE
CSJ0486-01-032
Proj IDSTP 2019(591)
Work TypeSUPER 2
 
15.4709862939.510.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-14-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days119
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JCCC, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0486-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04193008
Totals9862939.510.000.000.0

CountyBRISCOE
HighwaySH 256
From@ SH 86
To.
CSJ0541-01-028
Proj IDSTP 2019(316)HES
Work TypeMISCELLANEOUS WORK
 
0.147113928.0857175.0050.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-11-19
Work Began04-29-19
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged48
Percent Time Used88
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0541-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12183022
Totals113928.0829545.0057175.0050.1

CountyMOTLEY
HighwayFM 94
FromMIDDLE PEASE RIVER, NE
To7.357 MILES S OF NORTHFIELD
CSJ0704-05-022
Proj IDC 704-5-22
Work TypeWIDENING OF NON-FREEWAY FACILITY
 
10.2407493681.152642366.0935.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-09-18
Work Began08-09-18
Work Completed
Time Computed00-00-00
Contract Working Days242
Addl Days Granted0
Working Days Charged151
Percent Time Used62
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0704-05-022
BARRICADES UNLIMITED (0.89)
ROSS GRAHAM (2.19)
WEST TEXAS RUMBLE STRIP (0.06)
WOLFE CONSTRUCTION GROUP, INC. (1.35)
G.B. & G. TRANSPORT, LLP (2.97)
Contract #06183251
Totals7493681.15222232.002642366.0935.2

CountyCHILDRESS
HighwayCR
FromCR 22 @ SAND CREEK
To.
CSJ0925-08-019
Proj IDBR 1702(581)
Work TypeREPLACEMENT OF EXISTING BRIDGE FACI
 
0.100391117.50385037.5099.1
CountyWHEELER
HighwayCR
FromCR 28 @ SWEETWATER CREEK
To.
CSJ0925-11-013
Proj IDBR 1702(580)
Work TypeREPLACEMENT OF EXISTING BRIDGE FAC
 
0.100915600.25874142.2595.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-09-18
Work Began10-29-18
Work Completed
Time Computed00-00-00
Contract Working Days87
Addl Days Granted36
Working Days Charged127
Percent Time Used103
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-08-019
DUSTIN ALLEN, INC. (4.31)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.00)
PENHALL COMPANY (0.29)
SHINN AND GREGORY, INC. (7.62)
WOLFE CONSTRUCTION GROUP, INC. (0.57)
CONTRACTORS SERVICE COMPANY (1.37)
BOWMAN ENGINEERING & CONSULTING, INC. (0.25)
Contract #07183256
Totals1306717.7525945.751259179.7596.5

CountyWHEELER
HighwayCR
FromCR P @ SALT CREEK
To.
CSJ0925-11-014
Proj IDBR 1802(174)
Work TypeBR
 
0.081690990.200.000.0
CountyCOLLINGSWORTH
HighwayCR
FromCR 270 @ ELM CREEK
To.
CSJ0925-13-018
Proj IDBR 2018(496)
Work TypeBR
 
0.118854687.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days186
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-11-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193037
Totals1545677.400.000.000.0

CountyCOTTLE
HighwayCR
FromCR 460 @ DRAW
To.
CSJ0925-14-009
Proj IDBR 2018(497)
Work TypeBR
 
0.104394920.000.000.0
CountyMOTLEY
HighwayCR
FromCR 404 @ TEE PEE CREEK
To.
CSJ0925-18-013
Proj IDBR 2018(789)
Work TypeBR
 
0.063423510.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0925-14-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07193217
Totals818430.000.000.000.0

CountyHALL
HighwayFM 658
FromUS 287, SOUTH
ToFM 94
CSJ1053-01-016
Proj IDSTP 2019(144)
Work TypeMISCELLANEOUS
 
11.135774679.70188983.1124.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-18
Work Began03-22-19
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged66
Percent Time Used42
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1053-01-016
BARRICADES PLUS, LLC (1.19)
WOLFE CONSTRUCTION GROUP, INC. (0.64)
Contract #11183210
Totals774679.7018275.50188983.1124.3

page 1 | page 2