Monthly State Let Construction Report For Childress District As Of Nov 12, 2021 Page 1 Of 1

Last Update: Friday, November 12, 2021
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCHILDRESS ETC
HighwayUS 62 ETC
From@ PRAIRIE DOG TOWN FORK RED RIVER
To.
CSJ0031-05-045
Proj IDBR 2021(604)
Work TypeBRIDGE MAINTENANCE
 
4197227.70728649.0017.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-21
Work Began09-14-21
Work Completed
Time Computed00-00-00
Contract Working Days348
Addl Days Granted0
Working Days Charged33
Percent Time Used9
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0031-05-045
BARRICADES UNLIMITED (5.95)
DUSTROL, INC. (0.24)
HUNTER DEMOLITION & WRECKING CORPORATION (0.78)
S & S BRIDGE PAINTING, INC. (0.60)
GERDAN SLIPFORMING INC (0.60)
SPENCER PIER DRILLING CO (0.66)
Contract #06213021
Totals4197227.70457515.00728649.0017.3

CountyDONLEY
HighwayUS 287
FromARMSTRONG C/L, SOUTH
ToCLARENDON ECL
CSJ0042-06-074
Proj IDC 42-6-74
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3680420.351924390.4952.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-27-20
Work Began10-19-20
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted7
Working Days Charged201
Percent Time Used105
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-074
ALAMO BROTHERS CONCRETE INC (0.82)
BARRICADES UNLIMITED (1.53)
DK CONTRACTING, LLC (1.62)
FC TRAFFIC CONTROL, INC. (0.87)
Contract #06203012
Totals3680420.35238470.221924390.4952.5

CountyDONLEY
HighwayUS 287
FromCONCRETE SECTION IN HEDLEY, SOUTH
ToHALL C/L_(NBL)
CSJ0042-08-058
Proj IDNH 2021(092)
Work TypeOVERLAY
 
3770387.8422125.000.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-19-20
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days98
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-08-058
BARRICADES UNLIMITED (6.86)
FC TRAFFIC CONTROL, INC. (0.35)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.49)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.20)
ALAMO CONCRETE (4.72)
Contract #10203213
Totals3770387.840.0022125.000.5

CountyHALL
HighwayUS 287
From348' SOUTH OF 2ND STREET, SOUTH
To1.718 MILES
CSJ0042-09-124
Proj IDC 42-9-124
Work TypeNEW LOCATION FREEWAY
 
13478722.751849177.2213.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-21
Work Began08-23-21
Work Completed
Time Computed00-00-00
Contract Working Days420
Addl Days Granted0
Working Days Charged44
Percent Time Used10
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-124
BARRICADES UNLIMITED (0.98)
J. H. ODEN CONTRACTING COMPANY (0.82)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.36)
URBAN INFRACONSTRUCTION LLC (3.99)
WEST TEXAS ROCK RESOURCES, LLC (0.02)
WILLIS ELECTRIC CO., LP (0.89)
HOLMES CONSTRUCTION CO., L.P. (0.41)
WILLIAMS ROAD, LLC (0.11)
B&B TRUCKING (0.44)
Contract #05213206
Totals13478722.75614819.601849177.2213.7

CountyCHILDRESS
HighwayUS 287
From@ BAYLOR CREEK
To.
CSJ0042-12-082
Proj IDBR 2021(461)
Work TypeBRIDGE REPLACEMENT
 
1830675.90448338.2124.4
CountyCHILDRESS
HighwayCS
From4TH STREET @ DRAW
To.
CSJ0925-08-021
Proj IDBR 2021(210)
Work TypeBRIDGE REPLACEMENT
 
244176.80102917.5042.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days182
Addl Days Granted0
Working Days Charged33
Percent Time Used18
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-082
FOUTSCO PAVING COMPANY, LLC (18.64)
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.53)
HUNTER DEMOLITION & WRECKING CORPORATION (5.06)
LANCO TURF & SEEDING, INC. (0.42)
LINEAR TRAFFIC MARKINGS LLC (0.95)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.69)
PRIMATE CONSTRUCTION, LP (0.31)
TEXAS TRAFFIC AND BARRICADE, LLC (0.88)
WEST TEXAS ROCK RESOURCES, LLC (0.18)
TORO BRAVO CONSTRUCTION, LLC (0.18)
Contract #06213221
Totals2074852.70286196.96551255.7126.5

CountyFOARD
HighwaySH 6
FromHARDEMAN C/L, SOUTH
ToONE BLOCK NORTH OF US 70
CSJ0098-02-028
Proj IDF 2022(099)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.5413874626.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-02-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213212
Totals3874626.920.000.000.0

CountyKNOX
HighwayUS 82
FromSTEWART STREET, EAST
ToCHURCH STREET
CSJ0133-02-027
Proj IDSTP 2019(366)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.064225131.00243576.6099.9
CountyKNOX
HighwayUS 82
FromSH 6, EAST
To578' WEST OF FM267 (N INTERSECTION)
CSJ0133-03-046
Proj IDNH 2019(833)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.2146356476.806449470.8599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-17-19
Work Began04-15-20
Work Completed
Time Computed00-00-00
Contract Working Days274
Addl Days Granted22
Working Days Charged327
Percent Time Used110
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-02-027
A. L. CONSTRUCTION, LLC (3.99)
BARRICADES UNLIMITED (2.80)
CONTRACTORS SERVICE COMPANY (0.95)
LANCO TURF & SEEDING, INC. (0.27)
WEST TEXAS ROCK RESOURCES, LLC (0.42)
ZACK BURKETT CO. (36.10)
W. S. CONSTRUCTION COMPANY (2.58)
MARCOM"S MOWING SERVICE, LLC (0.18)
Contract #05193221
Totals6581607.8050180.006693047.4599.9

CountyKNOX
HighwayUS 82
From758' WEST OF FM 267 (N INT), EAST
ToBAYLOR C/L
CSJ0133-03-038
Proj IDNH 2020(738)
Work TypeSUPER-2 HIGHWAY
 
11.94112684227.534991520.4639.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-20
Work Began11-04-20
Work Completed
Time Computed00-00-00
Contract Working Days320
Addl Days Granted16
Working Days Charged183
Percent Time Used54
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-03-038
CONTRACTORS SERVICE COMPANY (0.47)
DUSTIN ALLEN, INC. (0.19)
MARCOM"S MOWING SERVICE, LLC (0.24)
W. S. CONSTRUCTION COMPANY (1.44)
BARRICADES UNLIMITED (1.89)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
WILLIS ELECTRIC CO., LP (0.27)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.38)
M.A.R. TRUCKING (0.31)
COLD CREEK CONSTRUCTION, LTD (0.65)
Contract #07203011
Totals12684227.53402316.444991520.4639.3

CountyKNOX
HighwayUS 82
FromWESTBOUND, EAST OF BENJAMIN
To.
CSJ0133-03-047
Proj IDSTP 2019(772)
Work TypeSAFETY REST AREA
 
0.1012268300.002344200.1999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days240
Addl Days Granted146
Working Days Charged381
Percent Time Used98
Contractor(s)
ANTHONY INMAN CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0133-03-047
WILSON CONTRACTING (16.43)
FERGUSON-VERESH, INC. (13.97)
BREEGLE BUILDING PRODUCTS, INC. (1.44)
CHENEY ELECTRIC, LLC (5.36)
ARMORED ROOFING COMPANY, INC. (2.19)
BNR CONCRETE POLISHING, LLC (0.17)
W.P. HOWLE MASONRY CONTRACTOR, INC. (1.60)
COMMERCIAL & INDUSTRIAL ELECTRONICS, INC. (2.32)
RHS CONSTRUCTION SERVICES, LLC (0.70)
WICHITA GLASS AND MIRROR COMPANY (5.04)
Contract #05193025
Totals2268300.0080783.662344200.1999.9

CountyFOARD
HighwayUS 70
FromCOTTLE C/L, EAST
ToFM 654
CSJ0146-04-029
Proj IDSTP 2021(106)
Work TypeOVERLAY
 
5.2005097897.254996241.4198.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-15-20
Work Began08-02-21
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged62
Percent Time Used60
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-04-029
DUSTIN ALLEN, INC. (5.65)
TEXAS PANHANDLE CONSTRUCTION, INC. (1.78)
CONTRACTORS SERVICE COMPANY (0.19)
DUSTROL, INC. (0.12)
PINNACLE GRINDING AND GROOVING LLC (0.62)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
SAENZ TRANSPORT, LLC (5.89)
WEST TEXAS ROCK RESOURCES, LLC (0.45)
Contract #11203213
Totals5097897.25112405.004996241.4198.0

CountyDONLEY
HighwaySH 70
From@ SALT FORK RED RIVER
To.
CSJ0310-01-043
Proj IDBR 2021(054)
Work TypeBRIDGE MAINTENANCE
 
599478.19540833.1292.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-14-21
Work Began05-03-21
Work Completed
Time Computed00-00-00
Contract Working Days108
Addl Days Granted0
Working Days Charged128
Percent Time Used118
Contractor(s)
INTEGRITY SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0310-01-043
BARRICADES UNLIMITED (8.99)
DALEY"S SUPERIOR ASPHALT MANUFACTURING INC (5.00)
HUNTER DEMOLITION & WRECKING CORPORATION (14.67)
CRANE SERVICES, INC. (0.71)
TEJAS CONCRETE PUMPING, LLC (0.76)
PINNACLE GRINDING AND GROOVING LLC (2.00)
Contract #12203217
Totals599478.1939963.33540833.1292.2

CountyCOLLINGSWORTH
HighwayFM 1547
From@ DRAW
To.
CSJ0797-07-032
Proj IDBR 2020(887)
Work TypeBRIDGE REPLACEMENT
 
0.016651386.00219700.0033.7
CountyCOLLINGSWORTH
HighwayFM 1439
From@ WOLF CREEK
To.
CSJ0797-08-011
Proj IDBR 2020(887)
Work TypeBRIDGE REPLACEMENT
 
0.001303133.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-21
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days134
Addl Days Granted0
Working Days Charged10
Percent Time Used7
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0797-07-032
BARRICADES UNLIMITED (1.10)
CONTRACTORS SERVICE COMPANY (0.98)
LANCO TURF & SEEDING, INC. (0.88)
LONE STAR PRODUCTS (WICHITA FALLS) (5.41)
Contract #06213027
Totals954519.00219700.00219700.0023.0

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE
To.
CSJ0925-00-083
Proj IDSTP 2B20(031)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1999216.75395112.8719.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-20
Work Began01-21-21
Work Completed
Time Computed00-00-00
Contract Working Days368
Addl Days Granted25
Working Days Charged113
Percent Time Used28
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08203035
Totals1999216.752500.00395112.8719.7

CountyBRISCOE ETC
HighwayFM 378 ETC
FromSH 86, SOUTH
ToFLOYD C/L
CSJ0970-01-018
Proj IDF 2022(075)
Work TypeSEAL COAT
 
5420379.090.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0970-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213020
Totals5420379.090.000.000.0

page 1