Monthly State Let Construction Report For Childress District As Of Feb 09, 2018 Page 1 Of 1

Last Update: Friday, February 09, 2018
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLINGSWORTH
HighwayUS 83
From865 N OF SALT FORK RR BRIDGE, N
ToEND OF DIVIDED SECTION (NBL)
CSJ0031-03-042
Proj IDSTP 2018(004)
Work TypeREHABILITATION OF EXISTING ROAD
 
4.1864173323.9129045.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0031-03-042
ANTIGO CONSTRUCTION, INC. (0.42)
HJC FARMS, INC. (0.60)
BARRICADES UNLIMITED (3.72)
WOLFE CONSTRUCTION GROUP, INC. (0.04)
Contract #09173006
Totals4173323.9129045.0029045.000.6

CountyKING
HighwayUS 83
From1.5 MILES N OF 5TH ST IN GUTHRIE, S
To5TH STREET
CSJ0032-05-041
Proj IDSTP 2018(478)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
1.500965946.450.000.0
CountyKING
HighwayUS 83
FromNORTH CROTON CREEK, SOUTH
ToSTONEWALL C/L
CSJ0032-06-039
Proj IDSTP 2018(478)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
8.6103220129.770.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0032-05-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173228
Totals4186076.220.000.000.0

CountyDONLEY
HighwayUS 287
FromARMSTRONG C/L, SOUTHEAST
ToCLARENDON ECL
CSJ0042-06-071
Proj IDNH 2018(543)
Work TypeMISCELLANEOUS WORK
 
13.514489937.200.000.0
CountyDONLEY
HighwayUS 287
FromCLARENDON ECL, SOUTHEAST
ToHEDLEY ECL
CSJ0042-07-069
Proj IDNH 2018(543)
Work TypeMISCELLANEOUS WORK
 
13.830695457.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183011
Totals1185394.600.000.000.0

CountyHALL
HighwayUS 287
From1.454 MILES SOUTH OF MEMPHIS SCL
ToRED RIVER BRIDGE (SBL)
CSJ0042-09-123
Proj IDNH 2018(306)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
10.1784165121.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-123
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11173003
Totals4165121.120.000.000.0

CountyHALL
HighwayUS 287
FromDONLEY C/L, SOUTH
To1.659 MILES
CSJ0042-09-126
Proj IDNH 1702(136)
Work TypeMILL & INLAY
 
1.6591199814.318024.000.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-09-126
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05173216
Totals1199814.310.008024.000.6

CountyCHILDRESS
HighwayUS 287
FromDISTRICT WIDE
To.
CSJ0043-01-079
Proj IDNH 2016(310)
Work TypeINSTALL DMS & UPGRADE TRAFFIC SIGNA
 
0.0091893993.412105202.7099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-29-16
Work Began09-05-16
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted71
Working Days Charged217
Percent Time Used98
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-079
BUYERS BARRICADES, INC. (1.81)
ROAD MASTER STRIPING LLC (4.97)
PRECISION DRILLING CO. (1.11)
ATLAS GROUP, LLC (3.63)
TEXAS BOMANITE (0.90)
M & M STRIPING & POWER WASHING, LLC (6.46)
RANSOM DRILLING SERVICES, LLC (0.35)
MEX DRILLING (0.60)
Contract #11153208
Totals1893993.4156299.412105202.7099.9

CountyCHILDRESS ETC
HighwayUS 287 ETC
FromFM 2530, SOUTH
ToHARDEMAN C/L (SBL)
CSJ0043-01-080
Proj IDNH 2018(174)
Work Type2018 DISTRICT WIDE SEALCOAT
 
157.0054151266.70178285.884.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0043-01-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10173206
Totals4151266.70178285.88178285.884.2

CountyDICKENS
HighwayUS 82
From8.359 MILES EAST OF DICKENS
ToKING C/L(EBL)
CSJ0132-02-033
Proj IDNH 2018(344)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.5702645236.160.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-10-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0132-02-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12173208
Totals2645236.160.000.000.0

CountyCOTTLE
HighwayFM 1037
From8TH STREET, WEST
ToUS 62/83
CSJ0146-08-053
Proj IDC 146-8-53
Work TypeREPAIR SIDEWALK/INSTALL ILLUMINATIO
 
0.062229715.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0146-08-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183032
Totals229715.000.000.000.0

CountyKNOX
HighwayUS 277
FromBAYLOR C/L, SOUTH
To2.330 MILES
CSJ0157-02-047
Proj IDNH 2018(624)
Work TypeASPHALTIC CONCRETE PAVEMENT OVERLAY
 
12.3906559485.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-02-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183202
Totals6559485.050.000.000.0

CountyWHEELER
HighwayIH 40
From@ NORTH LONG DRY CREEK (EB)
To.
CSJ0275-12-072
Proj IDBR 2017(870)
Work TypeBRIDGE REPLACEMENT
 
0.1602923330.682857594.3397.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-12-17
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days170
Addl Days Granted0
Working Days Charged133
Percent Time Used78
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-12-072
ALTUS TRAFFIC MANAGEMENT LLC (1.02)
DUININCK, INC. (31.78)
WEST TX RUMBLE STRIP (0.24)
DUSTY ALLEN, INC. (1.49)
BARRICADES UNLIMITED (0.57)
BARRICADES UNLIMITED (1.34)
GARY A. CRAIN, INC. (0.21)
LANCO TURF & SEEDING, INC. (0.26)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.09)
BOWMAN ENGINEERING & CONSULTING, INC (0.22)
PRIMATE CONSTRUCTION, INC. (0.05)
TEXOP CONSTRUCTION (0.47)
LINDAMOOD DEMOLITION, INC. (0.10)
Contract #03173006
Totals2923330.68158932.002857594.3397.7

CountyCOLLINGSWORTH
HighwayFM 1547
From3.72 MILES N OF HALL C/L, N
To1.5 MILES S OF FM 1056
CSJ0844-04-009
Proj IDSTP 1502(379)HES
Work TypeWIDENING OF A NON-FREEWAY FACILITY
 
7.9706114806.404364641.5671.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-31-16
Work Began02-22-17
Work Completed
Time Computed00-00-00
Contract Working Days179
Addl Days Granted0
Working Days Charged157
Percent Time Used87
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0844-04-009
BARRICADES UNLIMITED (1.22)
HJC FARMS, INC. (3.03)
DUSTROL, INC. (0.27)
DALE BROWN, INC. (3.50)
Contract #10153234
Totals6114806.400.004364641.5671.3

CountyCHILDRESS
HighwayVA
FromDISTRICT WIDE STRIPING
To.
CSJ0925-00-067
Proj IDSTP 2018(420)
Work TypeDISTRICT WIDE STRIPING
 
0.100763578.360.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183222
Totals763578.360.000.000.0

CountyHALL
HighwayCR
FromCR P @ DRAW
To.
CSJ0925-09-035
Proj IDBR 1702(005)
Work TypeREPLACEMENT OF EXISTING BRIDGE FAC
 
0.076557176.20327004.9158.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-16-17
Work Began10-01-17
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged58
Percent Time Used68
Contractor(s)
REECE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-09-035
CONTRACTORS SERVICE COMPANY (0.80)
GARY A. CRAIN, INC. (0.50)
JB FARM & RANCH (29.92)
LANCO TURF & SEEDING, INC. (2.04)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (11.83)
MORRIS COUNTY CONTRACTORS, LLC (4.35)
HODGES AND SON CONSTRUCTION COMPANY, INC. (11.83)
Contract #07173046
Totals557176.2085145.67327004.9158.6

page 1