Monthly State Let Maintenance Report For Childress District As Of Jan 16, 2020 Page 1 Of 1

Last Update: Friday, January 17, 2020
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARDEMAN
HighwayUS0287
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-04-001
Proj IDRMC - 621004001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001247718.56508976.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-11-10
Work Began10-12-10
Work Completed
Time Computed10-18-10
Contract Working Days56
Addl Days Granted76
Working Days Charged123
Percent Time Used93
Contractor(s)
B & M SERVICE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6210-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104017
Totals247718.560.00508976.4499.9

CountyDICKENS
HighwayUS0082
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-05-001
Proj IDRMC - 621005001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001138303.72316878.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-10
Work Began10-25-10
Work Completed
Time Computed11-01-10
Contract Working Days56
Addl Days Granted71
Working Days Charged69
Percent Time Used54
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6210-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104018
Totals138303.720.00316878.1099.9

CountyWHEELER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-06-001
Proj IDRMC - 621006001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001241876.20547568.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-08-10
Work Began10-18-10
Work Completed
Time Computed10-18-10
Contract Working Days80
Addl Days Granted74
Working Days Charged88
Percent Time Used57
Contractor(s)
JAMESON MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104009
Totals241876.200.00547568.5799.9

CountyCHILDRESS
HighwayUS0287
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6219-18-001
Proj IDRMC - 621918001
Work TypeON-CALL STRIPING
 
0.0011328306.591503368.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-11
Work Began06-20-11
Work Completed
Time Computed06-20-11
Contract Working Days100
Addl Days Granted0
Working Days Charged50
Percent Time Used50
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6219-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04114034
Totals1328306.590.001503368.2099.9

CountyCHILDRESS
HighwayUS0287
FromVAROUS
To.
CSJ6304-47-001
Proj IDRMC - 630447001
Work TypeSTRIPING
 
0.1001651901.593666153.7399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted720
Working Days Charged168
Percent Time Used11
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164216
Totals1651901.5942459.623666153.7399.9

CountyWHEELER
HighwayIH0040
FromGREY C/L & ARMSTRONG C/L
To.
CSJ6304-53-001
Proj IDRMC - 630453001
Work TypeINSTALL NEW DMS BOARDS
 
0.001317987.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204208
Totals317987.940.000.000.0

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
To.
CSJ6306-25-001
Proj IDRMC - 630625001
Work TypeFULL WIDTH MOWING
 
0.001639985.92958838.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days115
Addl Days Granted0
Working Days Charged75
Percent Time Used65
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164212
Totals639985.920.00958838.6499.9

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
To.
CSJ6313-02-001
Proj IDRMC - 631302001
Work TypeGUARDRAIL REPAIR
 
1.000435725.00459486.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged48
Percent Time Used10
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174016
Totals435725.0025980.00459486.5099.9

CountyWHEELER
HighwayIH0040
FromDISTRICT WIDE
To.
CSJ6323-04-001
Proj IDRMC - 632304001
Work TypeCONCRETE PAVEMENT REPAIRS
 
0.001975435.00590581.9560.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days720
Addl Days Granted0
Working Days Charged23
Percent Time Used3
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184218
Totals975435.000.00590581.9560.5

CountyCHILDRESS
HighwayUS0287
FromCHILDRESS, HALL, BRISCOE COUNTIES
To.
CSJ6329-41-001
Proj IDRMC - 632941001
Work TypeMOWING RIGHT OF WAY
 
0.001364431.60238964.7665.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted0
Working Days Charged25
Percent Time Used22
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184215
Totals364431.6050588.87238964.7665.5

CountyDONLEY
HighwayUS0287
FromDONLEY, COLLINGSWORTH, WHEELER COUNTIES
To.
CSJ6329-42-001
Proj IDRMC - 632942001
Work TypeMOWING OF RIGHT WAY
 
0.001497840.88251132.2950.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted0
Working Days Charged129
Percent Time Used89
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184216
Totals497840.8825480.12251132.2950.4

CountyDICKENS
HighwayUS0082
FromDICKENS, MOTLEY, COTTLE, KING COUNTIES
To.
CSJ6329-43-001
Proj IDRMC - 632943001
Work TypeMOWING OF RIGHT WAY
 
0.001577497.80386844.3166.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days124
Addl Days Granted0
Working Days Charged94
Percent Time Used75
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184015
Totals577497.805853.96386844.3166.9

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
To.
CSJ6337-44-001
Proj IDBPM - 633744001
Work Type2019 BPM PROJECT
 
0.001584840.00664332.7699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted26
Working Days Charged94
Percent Time Used100
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6337-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194205
Totals584840.00113138.90664332.7699.9

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6338-98-001
Proj IDRMC - 633898001
Work TypeUPGRADE SCHOOL ZONES
 
0.100236128.00224429.0095.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-03-19
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged10
Percent Time Used20
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04194202
Totals236128.0033537.00224429.0095.0

CountyWHEELER
HighwayUS0083
FromVA
ToVA
CSJ6349-03-001
Proj IDRMC - 634903001
Work TypeCRACK SEAL
 
0.001458186.00538676.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-03-19
Work Completed12-16-19
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged12
Percent Time Used66
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6349-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10194205
Totals458186.00538676.00538676.00100.0

page 1