Monthly State Let Maintenance Report For Childress District As Of Nov 12, 2021 Page 1 Of 2

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARDEMAN
HighwayUS0287
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-04-001
Proj IDRMC - 621004001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001247718.56508976.4499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-11-10
Work Began10-12-10
Work Completed
Time Computed10-18-10
Contract Working Days56
Addl Days Granted76
Working Days Charged123
Percent Time Used93
Contractor(s)
B & M SERVICE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6210-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104017
Totals247718.560.00508976.4499.9

CountyDICKENS
HighwayUS0082
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-05-001
Proj IDRMC - 621005001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001138303.72316878.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-10
Work Began10-25-10
Work Completed
Time Computed11-01-10
Contract Working Days56
Addl Days Granted71
Working Days Charged69
Percent Time Used54
Contractor(s)
KENNETH THOMASON
SUBCONTRACTOR(S) FOR CCSJ: 6210-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104018
Totals138303.720.00316878.1099.9

CountyWHEELER
HighwayIH0040
FromSEE PLAN SHEETS
ToSEE PLAN SHEETS
CSJ6210-06-001
Proj IDRMC - 621006001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.001241876.20547568.5799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-08-10
Work Began10-18-10
Work Completed
Time Computed10-18-10
Contract Working Days80
Addl Days Granted74
Working Days Charged88
Percent Time Used57
Contractor(s)
JAMESON MOWING INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07104009
Totals241876.200.00547568.5799.9

CountyCHILDRESS
HighwayUS0287
FromDISTRICT WIDE
ToDISTRICT WIDE
CSJ6219-18-001
Proj IDRMC - 621918001
Work TypeON-CALL STRIPING
 
0.0011328306.591503368.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-20-11
Work Began06-20-11
Work Completed
Time Computed06-20-11
Contract Working Days100
Addl Days Granted0
Working Days Charged50
Percent Time Used50
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6219-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04114034
Totals1328306.590.001503368.2099.9

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
To.
CSJ6313-02-001
Proj IDRMC - 631302001
Work TypeGUARDRAIL REPAIR
 
1.000435725.00719546.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-16-17
Work Completed04-14-21
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged71
Percent Time Used14
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6313-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03174016
Totals435725.0061230.00719546.50100.0

CountyWHEELER
HighwayIH0040
FromDISTRICT WIDE
To.
CSJ6323-04-001
Proj IDRMC - 632304001
Work TypeCONCRETE PAVEMENT REPAIRS
 
0.001975435.001415429.3499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-18
Work Completed
Time Computed00-00-00
Contract Working Days720
Addl Days Granted720
Working Days Charged43
Percent Time Used2
Contractor(s)
SILVER CREEK CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184218
Totals975435.000.001415429.3499.9

CountyCHILDRESS
HighwayUS0287
FromCHILDRESS, HALL, BRISCOE COUNTIES
To.
CSJ6329-41-001
Proj IDRMC - 632941001
Work TypeMOWING RIGHT OF WAY
 
0.001364431.60536835.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-18
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted112
Working Days Charged64
Percent Time Used28
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184215
Totals364431.6032166.30536835.4899.9

CountyDONLEY
HighwayUS0287
FromDONLEY, COLLINGSWORTH, WHEELER COUNTIES
To.
CSJ6329-42-001
Proj IDRMC - 632942001
Work TypeMOWING OF RIGHT WAY
 
0.001497840.88715341.3199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-09-18
Work Completed
Time Computed00-00-00
Contract Working Days144
Addl Days Granted144
Working Days Charged271
Percent Time Used94
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184216
Totals497840.8819569.33715341.3199.9

CountyDICKENS
HighwayUS0082
FromDICKENS, MOTLEY, COTTLE, KING COUNTIES
To.
CSJ6329-43-001
Proj IDRMC - 632943001
Work TypeMOWING OF RIGHT WAY
 
0.001577497.80902996.0899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-18
Work Completed
Time Computed00-00-00
Contract Working Days124
Addl Days Granted124
Working Days Charged227
Percent Time Used91
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6329-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184015
Totals577497.8059013.04902996.0899.9

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
ToVARIOUS
CSJ6353-93-001
Proj IDMMC - 635393001
Work TypeSUPPLY EMULSION FOR DISTRICT
 
0.1001875864.001953201.1499.9
Work Order00-00-00
Work Began12-31-20
Work Completed
Time Computed12-31-20
Contract Working Days120
Addl Days Granted240
Working Days Charged300
Percent Time Used83
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6353-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204212
Totals1875864.000.001953201.1499.9

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6363-97-001
Proj IDMMC - 636397001
Work TypeSUPPLY ANTI-ICING/DE-ICING SALT
 
0.100678500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6363-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204008
Totals678500.000.000.000.0

CountyCHILDRESS
HighwayUS0287
FromVA
To.
CSJ6365-25-001
Proj IDMMC - 636525001
Work TypePROVIDE AGGREGATE (MATERIAL ONLY)
 
0.1001945211.001769550.3790.9
Work Order00-00-00
Work Began11-12-20
Work Completed
Time Computed11-12-20
Contract Working Days120
Addl Days Granted240
Working Days Charged348
Percent Time Used96
Contractor(s)
VOLCANIC STONE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6365-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09204002
Totals1945211.0094897.971769550.3790.9

CountyCHILDRESS
HighwayUS0287
FromVARIOUS
To.
CSJ6365-67-001
Proj IDRMC - 636567001
Work TypeCALL-OUT STRIPING CONTRACT FOR DISTRICT
 
0.1002299636.781220386.2653.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-09-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged106
Percent Time Used14
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6365-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08204206
Totals2299636.7821832.931220386.2653.0

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6366-61-001
Proj IDRMC - 636661001
Work Type2021 DISTRICT CRACK SEAL
 
403.000606580.00663542.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-21
Work Completed
Time Computed00-00-00
Contract Working Days23
Addl Days Granted25
Working Days Charged9
Percent Time Used18
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6366-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204213
Totals606580.000.00663542.6099.9

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6367-29-001
Proj IDMMC - 636729001
Work TypeSUPPLY FLEXIBLE BASE (MATERIAL ONLY)
 
0.100344290.00232563.9567.5
Work Order00-00-00
Work Began01-15-21
Work Completed
Time Computed01-15-21
Contract Working Days120
Addl Days Granted240
Working Days Charged290
Percent Time Used80
Contractor(s)
B & G ELECTRIC
SUBCONTRACTOR(S) FOR CCSJ: 6367-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204206
Totals344290.0022286.17232563.9567.5

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6367-30-001
Proj IDMMC - 636730001
Work TypeSUPPLY LRA (MATERIAL ONLY)
 
0.100877565.001728034.8199.9
Work Order00-00-00
Work Began12-04-20
Work Completed
Time Computed12-04-20
Contract Working Days120
Addl Days Granted240
Working Days Charged332
Percent Time Used92
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6367-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204214
Totals877565.0056591.931728034.8199.9

CountyCHILDRESS
HighwayUS0287
FromVA
ToVA
CSJ6367-31-001
Proj IDMMC - 636731001
Work TypeSUPPLY ASPPM (MATERIAL ONLY)
 
0.100304687.50492696.6999.9
Work Order00-00-00
Work Began02-05-21
Work Completed
Time Computed12-09-20
Contract Working Days120
Addl Days Granted240
Working Days Charged273
Percent Time Used75
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6367-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10204205
Totals304687.5047567.41492696.6999.9

CountyHARDEMAN
HighwayUS0287
FromVA
To.
CSJ6371-12-001
Proj IDRMC - 637112001
Work TypeMOWING
 
0.001560217.56280418.2850.0
Work Order00-00-00
Work Began04-06-21
Work Completed
Time Computed04-06-21
Contract Working Days115
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS BLACKTOPS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6371-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12204207
Totals560217.56140054.39280418.2850.0

CountyCHILDRESS
HighwayUS0287
FromVA
To.
CSJ6371-20-001
Proj IDRMC - 637120001
Work Type2021-2022 GUARDRAIL REPAIR
 
0.001339775.0049700.0014.6
Work Order00-00-00
Work Began04-01-21
Work Completed
Time Computed03-25-21
Contract Working Days730
Addl Days Granted0
Working Days Charged119
Percent Time Used16
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6371-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01214206
Totals339775.000.0049700.0014.6

CountyCHILDRESS
HighwayUS0287
FromDISTRICTWIDE 2022 BPM
To.
CSJ6375-92-001
Proj IDBPM - 637592001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010397750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6375-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214208
Totals397750.000.000.000.0

page 1 | page 2