Monthly State Let Construction Report For Corpus Christi District As Of Nov 12, 2019 Page 1 Of 4

Last Update: Tuesday, November 12, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIVE OAK
HighwayIH 37
FromFM 2049
ToUS 281
CSJ0073-07-064
Proj IDNH 2020(208)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.2306699673.010.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days121
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11193215
Totals6699673.010.000.000.0

CountyLIVE OAK
HighwayIH 37
FromOAKVILLE
ToSH 72
CSJ0074-01-055
Proj IDC 74-1-55
Work TypeREHAB AND WIDEN
 
3.2501839971.961922564.4799.9
Work Order04-03-19
Work Began05-13-19
Work Completed
Time Computed04-28-19
Contract Working Days119
Addl Days Granted0
Working Days Charged117
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-01-055
HIGHWAY BARRICADES AND SERVICES, LLC (1.40)
LONE STAR EROSION CONTROL (1.08)
AREA WIDE PROTECTIVE, INC. (1.23)
DEPENDABLE FENCE & WELDING CO. INC. (0.00)
Contract #03193226
Totals1839971.96251904.641922564.4799.9

CountyNUECES ETC
HighwayIH 37 ETC
FromREDBIRD LN.
ToNUECES RIVER BRIDGE
CSJ0074-06-022
Proj IDNH 2019(490)
Work TypeDISTRICT WIDE HOT RUBBER SEAL
 
47.1813395904.931526297.8644.9
Work Order01-11-19
Work Began10-07-19
Work Completed
Time Computed02-11-19
Contract Working Days31
Addl Days Granted0
Working Days Charged14
Percent Time Used45
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-022
INTERSTATE BARRICADES & MARKINGS, INC. (10.22)
Contract #12183226
Totals3395904.931269538.101526297.8644.9

CountyNUECES
HighwayIH 37
FromN. CLARKWOOD
ToFM 1694
CSJ0074-06-219
Proj IDNH 2019(666)
Work TypeMILL,UNDERSEAL,OVERLAY AND NOVACHIP
 
4.59910228897.303092237.9730.2
Work Order04-16-19
Work Began07-08-19
Work Completed
Time Computed05-16-19
Contract Working Days143
Addl Days Granted0
Working Days Charged74
Percent Time Used51
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-219
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (6.26)
DEPENDABLE FENCE & WELDING CO. INC. (1.25)
PERFORMANCE EQUIPMENT SERVICE (2.29)
HIGHWAY BARRICADES AND SERVICES, LLC (3.44)
PRIMATE CONSTRUCTION, LP (0.35)
ANGEL BROTHERS ENTERPRISES, LTD. (8.49)
SOIL TECH ADVANCE INC. (0.06)
Contract #03193006
Totals10228897.302361011.443092237.9730.2

CountyNUECES
HighwayIH 37
From1.381 MI W OF US 181
To1.224 MI W OF SH 358
CSJ0074-06-228
Proj IDSTP 1702(337)HES
Work TypeIMPROVE TRAFFIC SIGNAL, INTER. SIG.
 
4.100287845.10284561.9098.8
CountyNUECES
HighwayIH 37
From0.203 MI E OF FM 3386
To0.216 MI W OF FM 24
CSJ0074-06-229
Proj IDSTP 1702(338)HES
Work TypeIMPROVE TRAFFIC SIGNALS, INTER.SIGN
 
1.060208601.50198398.5095.1
Work Order07-11-17
Work Began10-26-17
Work Completed
Time Computed09-10-17
Contract Working Days129
Addl Days Granted20
Working Days Charged139
Percent Time Used93
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-228
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06173236
Totals496446.600.00482960.4097.2

CountyJIM WELLS ETC
HighwaySH 44 ETC
FromVENTURA ST.
ToFM 1554
CSJ0086-11-053
Proj IDNH 2020(136)
Work TypeSEAL COAT
 
137.0617771423.480.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0086-11-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10193225
Totals7771423.480.000.000.0

CountyNUECES ETC
HighwayFM 665 ETC
FromJIM WELLS COUNTY LINE
ToFM 666
CSJ0086-20-022
Proj IDSTP 2019(239)
Work TypeDISTRICT WIDE SEAL COAT PROJECT
 
232.2377653200.286650550.6086.8
Work Order11-29-18
Work Began06-25-19
Work Completed
Time Computed12-29-18
Contract Working Days81
Addl Days Granted0
Working Days Charged72
Percent Time Used88
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0086-20-022
BRYDL CONTRACTING, INC. (1.10)
Contract #10183225
Totals7653200.28214722.716650550.6086.8

CountySAN PATRICIO
HighwayBS 359B
FromON BS 359B FROM NUECES STREET
ToSH 359
CSJ0087-06-030
Proj IDSTP 2019(800)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.360870395.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days106
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0087-06-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10193024
Totals870395.250.000.000.0

CountyBEE
HighwayUS 59
FromUS 181
ToBU 181-J
CSJ0088-01-068
Proj IDC 88-1-68
Work TypeSPOT BASE REPAIR AND NOVACHIP RDWY
 
1.3201008152.171027382.1099.9
CountyBEE
HighwayBU 181J
From0.37 MI N OF FM 3355
ToUS 59
CSJ0100-13-026
Proj IDC 100-13-26
Work TypeSPOT BASE REPAIR AND OVERLAY NOVACH
 
2.7501863821.281570922.2684.2
CountyBEE
HighwayBU 181J
FromUS 59
ToSH 202
CSJ0101-07-022
Proj IDC 101-7-22
Work TypeSPOT BASE REPAIR AND OVERLAY NOVACH
 
0.523427198.65383659.4189.8
CountyBEE
HighwayUS 59
FromBU 181-J
ToFM 351 INTERSECTION
CSJ0447-02-050
Proj IDC 447-2-50
Work TypeSPOT BASE REPAIR AND NOVACHIP RDWY
 
1.5691067155.80971218.8691.0
Work Order05-14-19
Work Began07-10-19
Work Completed
Time Computed06-01-19
Contract Working Days98
Addl Days Granted0
Working Days Charged87
Percent Time Used88
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-01-068
AREA WIDE PROTECTIVE, INC. (0.42)
BLACKTOP INDUSTRIES LLC (2.46)
D&S TEXAS ICON CONSTRUCTION (0.14)
FLASHER EQUIPMENT COMPANY (4.09)
MPB, INC. (0.44)
K. L. DURHAM CONSTRUCTION, L.L.C. (4.80)
ECO VACUUM SERVICES, LLC (0.12)
Contract #04193029
Totals4366327.90336771.133953182.6390.5

CountyKARNES
HighwayUS 181
FromAT SH80/BU 181E INTERSECTION
To.
CSJ0100-05-184
Proj IDNH 2018(781)
Work TypeRECONSTRUCT INTERSECTION
 
0.1006543322.701893913.7128.9
Work Order07-25-18
Work Began01-07-19
Work Completed
Time Computed08-25-18
Contract Working Days210
Addl Days Granted0
Working Days Charged169
Percent Time Used80
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-184
BOWMAN ENGINEERING & CONSULTING, INC. (1.16)
F & W ELECTRICAL CONTRACTORS, INC. (2.22)
ROADWAY SPECIALTIES, INC. (1.09)
TEX OP CONSTRUCTION, LP (1.17)
FLASHER LIMITED (1.45)
Contract #06183230
Totals6543322.70286551.621893913.7128.9

CountyKARNES ETC
HighwayUS 181 ETC
From0.46 MILES NORTH OF FM 887
To0.2 MILES SOUTH OF FM 887
CSJ0100-05-185
Proj IDSTP 2019(401)HES
Work TypeSAFETY LIGHTING
 
2.652749585.70630858.9284.1
Work Order02-22-19
Work Began07-08-19
Work Completed
Time Computed03-01-19
Contract Working Days141
Addl Days Granted0
Working Days Charged55
Percent Time Used39
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-185
CONNECT UNDERGROUND LLC (4.18)
Contract #01193019
Totals749585.702200.00630858.9284.1

CountyKARNES
HighwayUS 181
FromSH 72
ToBEE COUNTY LINE
CSJ0100-06-065
Proj IDNH 2019(989)
Work TypeOVERLAY
 
10.5956857158.420.000.0
CountyBEE
HighwayUS 181
FromKARNES COUNTY LINE
To0.3 MI S OF W KING LN (CB)
CSJ0100-07-050
Proj IDNH 2019(989)
Work TypeOVERLAY
 
8.5005373993.370.000.0
CountyBEE
HighwayUS 181
From0.3 MI S OF W KING LN (CB)
ToBU 181J (NORTH Y)
CSJ0100-08-098
Proj IDNH 2019(989)
Work TypeOVERLAY
 
5.4473507790.670.000.0
Work Order07-17-19
Work Began00-00-00
Work Completed
Time Computed09-01-19
Contract Working Days204
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-06-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193008
Totals15738942.460.000.000.0

CountyKARNES
HighwayFM 2509
FromBU 181G
To2 MI S OF US 181G
CSJ0100-12-009
Proj IDSTP 1902(300)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.0001557813.080.000.0
CountyKARNES
HighwayFM 887
From4.717 MI E OF FM 2724
To3.434 MI E OF FM 2724
CSJ1122-02-039
Proj IDSTP 1902(300)HES
Work TypeSFT
 
1.200789083.830.000.0
CountyKARNES
HighwayFM 2985
FromSH 72
ToBEE COUNTY LINE
CSJ3024-01-007
Proj IDSTP 1902(300)HES
Work TypeSFT
 
1.763897214.190.000.0
Work Order09-18-19
Work Began00-00-00
Work Completed
Time Computed10-01-19
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIERRA LEASE SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0100-12-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193229
Totals3244111.100.000.000.0

CountySAN PATRICIO
HighwayUS 181
FromON US 181 AT SH 89 INTERSECTION
To.
CSJ0101-03-088
Proj IDSTP 1802(556)HES
Work TypeGRADE,BASE,SURF,STRS
 
0.5007916889.954474980.4656.5
CountySAN PATRICIO
HighwaySH 89
FromON SH 89 AT US 181 INTERSECTION
To.
CSJ0101-08-004
Proj IDSTP 1802(557)HES
Work TypeGRADE,BASE,SURF,STRS
 
0.5007521002.914789171.5163.6
Work Order09-18-18
Work Began01-14-19
Work Completed
Time Computed10-19-18
Contract Working Days304
Addl Days Granted0
Working Days Charged157
Percent Time Used51
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-03-088
HIGHWAY BARRICADES AND SERVICES, LLC (1.25)
AARON CONCRETE CONTRACTORS, L.P. (2.06)
DEPENDABLE FENCE & WELDING CO. INC. (1.05)
JHABORES CONSTRUCTION CO, INC. (6.13)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.56)
SOUTH TEXAS PAINTING COMPANY (0.17)
MURRAY CONSTRUCTION (0.27)
WEBER-BALKE FOUNDATION COMPANY, INC (0.81)
THE LEVY COMPANY, INC. (1.54)
MCL CONTRACTING, LLC (0.22)
BEAVER CONTRACTORS, LLC (0.84)
Contract #08183211
Totals15437892.86799131.859264151.9760.0

CountySAN PATRICIO
HighwayUS 181
FromSUNSET ROAD
ToFM 3239 (BUDDY GANEM)
CSJ0101-04-097
Proj IDNH 1702(490)
Work TypeGRAD,STRS,BASE & SURFACING
 
1.72815878549.2310682781.8865.1
CountySAN PATRICIO
HighwayUS 181
FromON US 181 AT SH 35 INTERSECTION
To.
CSJ0101-04-112
Proj IDNH 1802(558)
Work TypeGRADE,BASE,SURF,STRS
 
1.80027270596.563204407.7211.7
Work Order10-22-18
Work Began01-07-19
Work Completed
Time Computed11-22-18
Contract Working Days500
Addl Days Granted404
Working Days Charged250
Percent Time Used27
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-04-097
D&S TEXAS ICON CONSTRUCTION (1.15)
HIGHWAY BARRICADES AND SERVICES, LLC (1.40)
A. H. BECK FOUNDATION CO., INC. (1.45)
A.Z. REBAR CONSTRUCTION, INC. (0.59)
THE LEVY COMPANY, INC. (5.06)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.03)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.62)
JHABORES CONSTRUCTION CO, INC. (0.27)
KLP COMMERCIAL, L.L.C. (2.51)
D & C CONCRETE CUTTING, INC. (0.08)
GREGORY PILE DRIVING, INC. (2.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
MUNOZ FOUNDATION DRILLING, INC. (0.78)
TAHOE TRUCKING, INC. (2.80)
Contract #08183003
Totals43149145.79783514.0413887189.6031.3

CountySAN PATRICIO ETC
HighwayUS 181 ETC
From0.25 MI N OF FM 3239
To0.25 MI S OF FM 893
CSJ0101-04-113
Proj IDSTP 1902(301)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
13.3582780023.750.000.0
Work Order09-16-19
Work Began00-00-00
Work Completed
Time Computed10-01-19
Contract Working Days224
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-04-113
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08193015
Totals2780023.750.000.000.0

CountyNUECES
HighwaySH 44
FromWEST OF FM 3386
ToEAST OF FM 1694
CSJ0102-01-088
Proj IDNH 2018(842)
Work TypeGR, BS, SURF, STRUCTS
 
2.29029535168.5013997384.4247.3
CountyNUECES
HighwaySH 44
FromWEST OF FM 3386
ToEAST OF FM 1694
CSJ0102-01-117
Proj IDC 102-1-117
Work TypeMILL AND OVERLAY FRONTAGE ROADS
 
2.2908415689.904723352.2056.1
Work Order06-11-18
Work Began08-08-18
Work Completed
Time Computed07-11-18
Contract Working Days645
Addl Days Granted32
Working Days Charged215
Percent Time Used31
Contractor(s)
HAAS-ANDERSON CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0102-01-088
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.83)
HIGHWAY BARRICADES AND SERVICES, LLC (0.40)
THE LEVY COMPANY, INC. (1.70)
TROUT TRUCKING_COMPANY INC. (3.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.27)
AARON CONCRETE CONTRACTORS, L.P. (1.75)
BEAVER CONTRACTORS, LLC (1.77)
SCOTT DERR PAINTING CO, LLC (0.23)
MURRAY CONSTRUCTION (0.16)
PERFORMANCE EQUIPMENT SERVICE (0.17)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.68)
BOWMAN ENGINEERING & CONSULTING, INC. (0.12)
MCL CONTRACTING, LLC (0.27)
DIAMOND CORE DRILLING (0.01)
Contract #05183203
Totals37950858.401227913.7818720736.6249.3

CountyNUECES ETC
HighwaySH 44 ETC
FromMANNING RD.
To0.919 MI W OF SS544 (INTER. DR.)
CSJ0102-01-114
Proj IDSTP 2019(706)HES
Work TypeINSTALL MEDIAN BARRIER, MILL EDGE
 
50.1752213165.861100168.7749.7
Work Order05-14-19
Work Began08-12-19
Work Completed
Time Computed06-01-19
Contract Working Days102
Addl Days Granted0
Working Days Charged46
Percent Time Used45
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0102-01-114
AREA WIDE PROTECTIVE, INC. (1.03)
D&S TEXAS ICON CONSTRUCTION (0.13)
HIGHWAY BARRICADES AND SERVICES, LLC (35.73)
WEST TEXAS ROCK RESOURCES, LLC (0.77)
Contract #04193025
Totals2213165.86861495.971100168.7749.7

CountyNUECES ETC
HighwayBS 44D ETC
FromSH 44 (GORE)
ToSH 44
CSJ0102-01-116
Proj IDSTP 2018(444)
Work TypeHOT RUBBER SEAL
 
64.2313210192.043760784.1099.9
Work Order06-29-18
Work Began05-15-19
Work Completed
Time Computed07-29-18
Contract Working Days41
Addl Days Granted0
Working Days Charged36
Percent Time Used87
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0102-01-116
INTERSTATE BARRICADES & MARKINGS, INC. (16.52)
D&S TEXAS ICON CONSTRUCTION (0.04)
APEX HIGHWAY SERVICES, LLC (1.35)
STRIPE-A-ZONE, INC. (1.91)
Contract #05183240
Totals3210192.040.003760784.1099.9

CountyNUECES
HighwayUS 77
FromNORTH OF FM 2826
ToSOUTH OF CR 28 (CONTROL BREAK)
CSJ0102-02-101
Proj IDNH 1802(404)
Work TypeGRADE,BASE,SURF,STRS
 
2.42012681345.421657767.0113.0
CountyNUECES
HighwayUS 77
FromCR 16
ToSOUTH OF FM 3354
CSJ0102-03-082
Proj IDNH 1802(404)
Work TypeGRADE,BASE,SURF,STRS
 
2.89023240669.264804457.5320.6
CountyNUECES
HighwayUS 77
FromCR 28
ToCR 16
CSJ0102-16-001
Proj IDSTP 2018(201)
Work TypeGRADE,BASE,SURF,STRS
 
5.09082400883.5429491325.2735.7
Work Order08-15-18
Work Began02-07-19
Work Completed
Time Computed09-15-18
Contract Working Days917
Addl Days Granted0
Working Days Charged182
Percent Time Used19
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0102-02-101
HIGHWAY BARRICADES AND SERVICES, LLC (0.48)
BEAVER CONTRACTORS, LLC (6.29)
ABC EROSION CONTROL, INC. (0.28)
TEXAS HIGHWAY WALLS (6.03)
SOIL-TECH, INC. (0.18)
SOUTH TEXAS PAINTING COMPANY (0.09)
HAYWARD BAKER, INC. (0.17)
A.Z. REBAR CONSTRUCTION, INC. (0.33)
MICA CORPORATION (4.13)
PRIMATE CONSTRUCTION, LP (0.05)
ROADWAY SPECIALTIES, INC. (1.37)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
MATERIAL PRODUCERS CONSTRUCTION SERVICES, LLC (2.11)
PANTHER CREEK TRANSPORTATION, INC. (0.36)
BREDA COMPANY, INC. (0.02)
GUERRA UNDERGROUND, LLC (0.07)
BAY LTD. (16.44)
Contract #07183202
Totals118322898.225194771.1635953549.8130.3