Monthly State Let Construction Report For Corpus Christi District As Of Nov 12, 2021 Page 1 Of 4

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIVE OAK ETC
HighwayIH 37
FromAT INTERSECTION OF IH37/FM2049
To.
CSJ0073-07-002
Proj IDBR 2021(296)
Work TypeBRIDGE MAINTENANCE
 
1.2403746406.851665180.8544.4
Work Order03-01-21
Work Began04-05-21
Work Completed
Time Computed03-01-21
Contract Working Days340
Addl Days Granted0
Working Days Charged131
Percent Time Used38
Contractor(s)
LUCANIA CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-002
CERTIFIED PLACERS LLC (1.86)
STATEWIDE SAFETY SYSTEMS (1.49)
LONE STAR EROSION CONTROL (4.62)
PAVEMENT MARKINGS INC. (1.34)
Contract #01213218
Totals3746406.85126111.501665180.8544.4

CountyLIVE OAK ETC
HighwayIH 37
FromCONTROL BREAK (.2 MI N OF CR499)
ToATASCOSA COUNTY LINE
CSJ0073-07-062
Proj IDSTP 2020(672)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
106.57910250265.9810063144.3498.1
Work Order05-12-20
Work Began05-21-20
Work Completed
Time Computed05-01-20
Contract Working Days170
Addl Days Granted52
Working Days Charged223
Percent Time Used100
Contractor(s)
ALTUS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0073-07-062
D & C CONCRETE CUTTING, INC. (0.12)
Contract #03203022
Totals10250265.98178951.5910063144.3498.1

CountyLIVE OAK ETC
HighwayIH 37 ETC
FromCONTROL BREAK
ToFM 799 (NORTH)
CSJ0074-01-058
Proj IDF 2022(061)
Work TypeSEAL COAT
 
72.7243738669.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0074-01-058
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213205
Totals3738669.780.000.000.0

CountySAN PATRICIO ETC
HighwayIH 37 ETC
From.4 MI S OF SS459
To.45 MI N OF SS 459
CSJ0074-03-047
Proj IDSTP 2B20(013)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.7781690176.801411266.2083.4
Work Order09-08-20
Work Began01-29-21
Work Completed
Time Computed09-01-20
Contract Working Days170
Addl Days Granted0
Working Days Charged150
Percent Time Used88
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0074-03-047
SPECIALTY DRILLING, LLC (4.77)
MATTHEW GREEN LLC (3.43)
MUNOZ FOUNDATION DRILLING, INC. (4.25)
Contract #07203232
Totals1690176.80130229.181411266.2083.4

CountySAN PATRICIO
HighwayIH 37
FromNUECES RIVER (CB)
ToIH37/US 77 INTERCHANGE
CSJ0074-05-098
Proj IDNH 2B20(014)
Work TypeWIDEN FREEWAY
 
0.52021739732.682558981.3611.7
CountyNUECES
HighwayIH 37
FromREDBIRD LN. (OVERPASS)
ToNUECES RIVER_(CB)
CSJ0074-06-241
Proj IDNH 2B20(015)
Work TypeWIDEN FREEWAY
 
1.76959711872.407492266.6312.5
CountyNUECES
HighwayIH 37
FromRED BIRD LANE
ToNUECES RIVER
CSJ0074-06-249
Proj IDNH 2B20(015)
Work TypeOVERLAY
 
1.7722539142.09123750.004.8
Work Order07-14-21
Work Began09-20-21
Work Completed
Time Computed07-01-21
Contract Working Days1,959
Addl Days Granted0
Working Days Charged39
Percent Time Used1
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0074-05-098
A BROTHERS MILLING, LLC (0.25)
ADCOCK 4 INVESTMENTS, LLC (1.78)
CREACOM, INC. (5.48)
DEPENDABLE FENCE (0.40)
GP7 CONSTRUCTION INC. (3.04)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.07)
SCOTT DERR PAINTING CO, LLC (0.13)
HIGHWAY BARRICADES AND SERVICES, LLC (0.85)
LONE STAR EROSION CONTROL (0.67)
A. H. BECK FOUNDATION CO., INC. (6.29)
FRANK JR REINFORCEMENT LLC (0.55)
BAY LTD. (10.44)
Contract #05213001
Totals83990747.179973792.4110174997.9912.1

CountyNUECES
HighwayIH 37
FromFM 1694_(CALLICOATE RD)
ToRED BIRD LANE
CSJ0074-06-230
Proj IDNH 2020(210)
Work TypeOVERLAY
 
1.2474906044.094622192.1294.2
CountyNUECES
HighwayIH 37
FromAT IH37/I69E INTERCHANGE
ToON EXIT 14A
CSJ0074-06-242
Proj IDNH 2020(210)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.3511936043.342236507.7499.9
Work Order01-14-20
Work Began03-23-20
Work Completed
Time Computed02-01-20
Contract Working Days160
Addl Days Granted9
Working Days Charged262
Percent Time Used155
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-230
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (7.75)
PERFORMANCE EQUIPMENT SERVICE (1.74)
LONE STAR EROSION CONTROL (0.27)
HIGHWAY BARRICADES AND SERVICES, LLC (6.65)
(INACTIVE)D&S TEXAS ICON CONSTRUCTION (1.16)
THE LEVY COMPANY, INC. (15.47)
ANGEL BROTHERS ENTERPRISES, LTD. (6.04)
AARON CONCRETE CONTRACTORS, L.P. (0.00)
MUNOZ FOUNDATION DRILLING, INC. (0.00)
Contract #12193037
Totals6842087.4345106.086858699.8699.9

CountyNUECES
HighwayUS 181
FromTANCHAHUA ST.
ToBREWSTER ST.
CSJ0074-06-253
Proj IDF 2021(550)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.717269165.000.000.0
Work Order05-20-21
Work Began00-00-00
Work Completed
Time Computed06-01-21
Contract Working Days23
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY BARRICADES AND SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0074-06-253
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04213203
Totals269165.000.000.000.0

CountyJIM WELLS ETC
HighwayFM 665 ETC
From.838 MI W OF FM 1931
ToNUECES CO LINE
CSJ0086-19-034
Proj IDSTP 2021(030)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
45.986598051.80560587.0094.7
Work Order10-28-20
Work Began06-07-21
Work Completed
Time Computed11-01-20
Contract Working Days13
Addl Days Granted39
Working Days Charged62
Percent Time Used119
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-19-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09203032
Totals598051.8021564.25560587.0094.7

CountyNUECES
HighwayFM 665
FromCR 107
ToFM 666
CSJ0086-20-023
Proj IDSTP 2021(877)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.5562247833.350.000.0
CountyNUECES
HighwayFM 24
From.189 MI N OF CR 44
ToSH 44
CSJ1556-01-026
Proj IDSTP 2021(877)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.876708567.750.000.0
CountyNUECES
HighwayFM 2292
FromSH 44
ToMCGLOIN RD.
CSJ2142-02-016
Proj IDSTP 2021(877)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.1971552316.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0086-20-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08213033
Totals4508717.900.000.000.0

CountySAN PATRICIO ETC
HighwaySH 359 ETC
FromIH 37
ToBEE COUNTY LINE
CSJ0087-04-041
Proj IDC 87-4-41
Work TypeSEAL COAT
 
47.9394367105.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0087-04-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10213207
Totals4367105.450.000.000.0

CountyBEE ETC
HighwaySH 359 ETC
FromSAN PATRICIO COUNTY LINE
ToUS 181
CSJ0087-05-031
Proj IDC 87-5-31
Work TypeSEAL COAT
 
54.9223762077.323631167.6096.5
Work Order11-19-20
Work Began05-06-21
Work Completed
Time Computed12-01-20
Contract Working Days35
Addl Days Granted0
Working Days Charged30
Percent Time Used85
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0087-05-031
INTERSTATE BARRICADES & MARKINGS, INC. (11.06)
Contract #10203230
Totals3762077.320.003631167.6096.5

CountySAN PATRICIO
HighwayBS 359B
FromON BS 359B FROM NUECES STREET
ToSH 359
CSJ0087-06-030
Proj IDSTP 2019(800)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
0.360870395.25857322.6198.5
Work Order12-16-19
Work Began02-24-20
Work Completed
Time Computed12-01-19
Contract Working Days106
Addl Days Granted37
Working Days Charged144
Percent Time Used100
Contractor(s)
LONE STAR SITEWORK, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0087-06-030
SAFETY FIRST TRAFFIC SOLUTIONS, LLC (4.22)
DIAMOND X CONTRACTING, INC (35.56)
THE LEVY COMPANY, INC. (21.85)
HIGHWAY BARRICADES AND SERVICES, LLC (1.68)
Contract #10193024
Totals870395.254296.19857322.6198.5

CountyBEE
HighwayUS 59
FromUS 181
ToGOLIAD COUNTY LINE
CSJ0088-01-069
Proj IDC 88-1-69
Work TypeOVERLAY
 
11.1534650822.624661115.4399.9
CountyGOLIAD
HighwayUS 59
FromSH 239
ToBEE COUNTY LINE
CSJ0088-02-066
Proj IDC 88-2-66
Work TypeOVERLAY
 
15.0626202015.535279018.6985.1
CountyBEE
HighwayUS 59
FromFM 351
ToLIVE OAK COUNTY LINE
CSJ0447-02-051
Proj IDC 447-2-51
Work TypeOVERLAY
 
10.3495067232.823746727.0373.9
Work Order10-21-20
Work Began11-01-20
Work Completed
Time Computed11-01-20
Contract Working Days204
Addl Days Granted3
Working Days Charged171
Percent Time Used82
Contractor(s)
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-01-069
AREA WIDE PROTECTIVE, INC. (0.18)
BATTERSON, LLP (0.24)
DEPENDABLE FENCE & WELDING CO. INC. (5.90)
HIGHWAY BARRICADES AND SERVICES, LLC (2.22)
STRIPE-A-ZONE, INC. (0.40)
LONE STAR PAVING COMPANY (0.18)
MILLING SERVICES (2.34)
Contract #09203204
Totals15920070.9778242.8813686861.1585.9

CountyKARNES
HighwayUS 181
FromAT SH80/BU 181E INTERSECTION
To.
CSJ0100-05-184
Proj IDNH 2018(781)
Work TypeRECONSTRUCT INTERSECTION
 
0.1006543322.706593873.1599.9
Work Order07-25-18
Work Began01-07-19
Work Completed
Time Computed08-25-18
Contract Working Days210
Addl Days Granted273
Working Days Charged536
Percent Time Used110
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-05-184
BOWMAN ENGINEERING & CONSULTING, INC. (1.16)
F & W ELECTRICAL CONTRACTORS, INC. (2.22)
ROADWAY SPECIALTIES, INC. (1.09)
TEX OP CONSTRUCTION, LP (1.17)
FLASHER LIMITED (1.45)
HIGHWAY BARRICADES AND SERVICES, LLC (0.12)
Contract #06183230
Totals6543322.700.006593873.1599.9

CountyKARNES
HighwayUS 181
FromSH 72
ToBEE COUNTY LINE
CSJ0100-06-065
Proj IDNH 2019(989)
Work TypeOVERLAY
 
10.5956857158.428983555.4999.9
CountyBEE
HighwayUS 181
FromKARNES COUNTY LINE
To0.3 MI S OF W KING LN (CB)
CSJ0100-07-050
Proj IDNH 2019(989)
Work TypeOVERLAY
 
8.5005373993.375924210.6799.9
CountyBEE
HighwayUS 181
From0.3 MI S OF W KING LN (CB)
ToBU 181J (NORTH Y)
CSJ0100-08-098
Proj IDNH 2019(989)
Work TypeOVERLAY
 
5.4473507790.673688244.8199.9
Work Order07-17-19
Work Began05-18-20
Work Completed
Time Computed09-02-19
Contract Working Days204
Addl Days Granted27
Working Days Charged260
Percent Time Used112
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-06-065
D&S TEXAS ICON CONSTRUCTION (1.78)
HIGHWAY BARRICADES AND SERVICES, LLC (2.17)
PRIMATE CONSTRUCTION, LP (0.15)
STRIPE-A-ZONE, INC. (0.34)
TEXAS R & G CONSTRUCTION SERVICES LLC (1.60)
TRAF-TEX, INC. (0.30)
CLARK CONSTRUCTION OF TEXAS, INC. (5.12)
Contract #06193008
Totals15738942.467767.4618596010.9799.9

CountyBEE
HighwayUS 181
From.3 MI N. OF BU 1810J
ToBU 181-J INTERSECTION_(SOUTH Y)
CSJ0100-08-095
Proj IDC 100-8-95
Work TypeOVERLAY
 
9.6167771037.184129547.2753.1
CountyBEE
HighwayUS 181
FromBU 181J
To.1 MI S OF RIDGEWAY LN. (CB)
CSJ0100-08-097
Proj IDC 100-8-97
Work TypeOVERLAY
 
0.5081001106.86636100.7063.5
CountyBEE
HighwayUS 181
From0.1 MI S OF RIDGEWAY LN. (CB)
ToSH 359
CSJ0101-01-067
Proj IDC 101-1-67
Work TypeOVERLAY
 
7.8665967594.003306142.2755.4
Work Order08-20-20
Work Began02-02-21
Work Completed
Time Computed09-01-20
Contract Working Days184
Addl Days Granted0
Working Days Charged158
Percent Time Used85
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0100-08-095
CHEROKEE SERVICES (0.15)
DEPENDABLE FENCE & WELDING CO. INC. (2.53)
FLASHER EQUIPMENT COMPANY (1.63)
HIGHWAY BARRICADES AND SERVICES, LLC (0.50)
LONE STAR EROSION CONTROL (0.22)
RELMCO, INC. (4.14)
PRIMATE CONSTRUCTION, LP (0.05)
DEPENDABLE FENCE (2.53)
Contract #07203013
Totals14739738.04573106.358071790.2454.7

CountyBEE
HighwayBU 181J
From.1 MI N OF HUNTINGTON ST.
To.48 MI N OF US 59
CSJ0100-13-027
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
563119.90310766.0055.1
CountyBEE
HighwayBU 181J
From.48 MI N OF US 59
To.1 MI S OF SH 202
CSJ0101-07-024
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
192517.450.000.0
CountyJIM WELLS
HighwayUS 281
From.2 MI N OF FM 716
To.2 MI S OF FM 716
CSJ0255-02-060
Proj IDF 2021(568)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
86124.250.000.0
Work Order06-10-21
Work Began00-00-00
Work Completed
Time Computed07-01-21
Contract Working Days195
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0100-13-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05213214
Totals841761.6040846.00310766.0036.9

CountySAN PATRICIO
HighwayUS 181
FromSUNSET ROAD
ToFM 3239 (BUDDY GANEM)
CSJ0101-04-097
Proj IDNH 1702(490)
Work TypeGRAD,STRS,BASE & SURFACING
 
1.72815878549.2318602384.8199.9
CountySAN PATRICIO
HighwayUS 181
FromON US 181 AT SH 35 INTERSECTION
To.
CSJ0101-04-112
Proj IDNH 1802(558)
Work TypeGRADE,BASE,SURF,STRS
 
1.80027270596.5618372569.7867.3
Work Order10-22-18
Work Began01-07-19
Work Completed
Time Computed11-22-18
Contract Working Days500
Addl Days Granted522
Working Days Charged762
Percent Time Used74
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-04-097
D&S TEXAS ICON CONSTRUCTION (1.15)
HIGHWAY BARRICADES AND SERVICES, LLC (1.40)
A. H. BECK FOUNDATION CO., INC. (1.45)
A.Z. REBAR CONSTRUCTION, INC. (0.59)
THE LEVY COMPANY, INC. (5.06)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.03)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.62)
JHABORES CONSTRUCTION CO, INC. (0.27)
KLP COMMERCIAL, L.L.C. (2.51)
D & C CONCRETE CUTTING, INC. (0.08)
GREGORY PILE DRIVING, INC. (2.76)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09)
MUNOZ FOUNDATION DRILLING, INC. (0.78)
TAHOE TRUCKING, INC. (2.80)
WEBBER, LLC (1.75)
MUNOZ ENGINEERING (0.35)
SOUTH TEXAS PAINTING COMPANY (0.22)
TAHOE TRUCKING LLC (2.80)
GDC GRIFFIN DEWATERING, LLC (0.69)
GP TRANSPORT (0.11)
Contract #08183003
Totals43149145.791099498.7436974954.5984.8

CountySAN PATRICIO ETC
HighwayUS 181 ETC
From0.25 MI N OF FM 3239
To0.25 MI S OF FM 893
CSJ0101-04-113
Proj IDSTP 1902(301)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
13.3582780023.752548393.3092.3
Work Order09-16-19
Work Began01-23-20
Work Completed
Time Computed10-01-19
Contract Working Days224
Addl Days Granted0
Working Days Charged247
Percent Time Used110
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0101-04-113
G & E ESCOBEDO CONSTRUCTION, INC. (1.22)
TRIPLE H FIELD SERVICES, LLC (1.75)
Contract #08193015
Totals2780023.750.002548393.3092.3

CountySAN PATRICIO
HighwayUS 181
FromFM 3239 (BUDDY GANEM DR.)
ToFM 2986 (WILDCAT DR.)
CSJ0101-04-114
Proj IDC 101-4-114
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1022754.22807388.8578.9
CountySAN PATRICIO
HighwayUS 181
FromWILDCAT RD
ToCONTROL BREAK
CSJ0101-04-117
Proj IDC 101-4-117
Work TypeOVERLAY
 
1287447.500.000.0
CountySAN PATRICIO
HighwayUS 181
FromFM3239 (BUDDY GANEM DR.)
ToFM2986 (WILDCAT DR.)
CSJ0101-04-120
Proj IDC 101-4-120
Work TypeWIDEN FREEWAY
 
1.34020495891.411134555.455.5
Work Order12-15-20
Work Began00-00-00
Work Completed
Time Computed01-01-21
Contract Working Days278
Addl Days Granted0
Working Days Charged30
Percent Time Used10
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0101-04-114
A. H. BECK FOUNDATION CO., INC. (2.39)
TRAF-TEX, INC. (4.25)
HIGHWAY BARRICADES AND SERVICES, LLC (3.85)
PERFORMANCE EQUIPMENT SERVICE (0.91)
SOIL TECH ADVANCE INC. (0.76)
TRAF-TEX, INC. (0.00)
Contract #11203203
Totals22806093.131059316.851941944.308.5