Monthly State Let Construction Report For Corpus Christi District As Of Sep 18, 2019 Page 4 Of 4

Last Update: Thursday, September 19, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyNUECES
HighwayFM 2826
FromFM 666
ToUS 77
CSJ2886-02-017
Proj IDC 2886-2-17
Work TypeREHAB ROADWAY AND WIDEN
 
7.7144689383.97319194.996.8
Work Order06-12-19
Work Began07-29-19
Work Completed
Time Computed06-01-19
Contract Working Days170
Addl Days Granted0
Working Days Charged20
Percent Time Used11
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2886-02-017
BLACKTOP INDUSTRIES LLC (1.87)
D&S TEXAS ICON CONSTRUCTION (1.79)
HIGHWAY BARRICADES AND SERVICES, LLC (1.10)
ROADTRAC INC. (0.12)
Contract #04193016
Totals4689383.97208906.99319194.996.8

CountySAN PATRICIO
HighwayFM 2986
FromUS 181
ToFM 3239 (BUDDY GANEM DR)
CSJ3026-01-026
Proj IDSTP 2018(633)
Work TypeGRADE,BASE,SURF,STRS,C&G,SIDEWALKS
 
2.20016161342.767602018.9747.0
CountySAN PATRICIO
HighwayFM 2986
FromFM 3239
ToMEMORIAL PRKWY
CSJ3026-01-027
Proj IDSTP 2018(634)
Work TypeOVERLAY, PEDESTRIAN BEACON
 
0.100965277.32970027.7799.9
Work Order08-16-18
Work Began12-03-18
Work Completed
Time Computed10-15-18
Contract Working Days476
Addl Days Granted0
Working Days Charged127
Percent Time Used26
Contractor(s)
BAY LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3026-01-026
HIGHWAY BARRICADES AND SERVICES, LLC (1.31)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.80)
THE LEVY COMPANY, INC. (2.86)
TERRY L. ELLIS BACKHOE (0.07)
JHABORES CONSTRUCTION CO, INC. (2.23)
D&S TEXAS ICON CONSTRUCTION (4.99)
K. L. DURHAM CONSTRUCTION, L.L.C. (0.93)
A.Z. REBAR CONSTRUCTION, INC. (0.19)
Contract #07183206
Totals17126620.081765382.738572046.7450.0