Monthly Local Let Maintenance Report For Dallas District As Of Jan 16, 2020 Page 1 Of 4

Last Update: Friday, January 17, 2020
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed06-10-15
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.00100.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6315-43-001
Proj IDRMC - 631543001
Work TypeRAISED PAVEMENT MARKERS
 
0.001119011.7574100.7962.2
Work Order05-03-19
Work Began05-06-19
Work Completed
Time Computed05-13-19
Contract Working Days365
Addl Days Granted0
Working Days Charged229
Percent Time Used62
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181801
Totals119011.750.0074100.7962.2

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT
ToCOMPLEX
CSJ6317-55-001
Proj IDSUP - 631755001
Work TypeGROUNDS MAINTENANCE
 
0.001203437.4479354.7739.0
Work Order12-19-18
Work Began01-01-19
Work Completed
Time Computed01-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged359
Percent Time Used49
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6317-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10181830
Totals203437.444985.7679354.7739.0

CountyELLIS
HighwayIH0045
FromDALLAS COUNTY LINE
ToTO NAVARRO COUNTY LINE
CSJ6320-79-001
Proj IDRMC - 632079001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.001257500.00207285.0080.4
Work Order04-25-18
Work Began04-27-18
Work Completed
Time Computed05-02-18
Contract Working Days730
Addl Days Granted0
Working Days Charged610
Percent Time Used83
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171803
Totals257500.0010815.00207285.0080.4

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6329-82-001
Proj IDRMC - 632982001
Work TypeVEGETATION MANAGEMENT
 
0.001215436.0051630.0023.9
Work Order05-24-19
Work Began06-03-19
Work Completed
Time Computed06-03-19
Contract Working Days60
Addl Days Granted55
Working Days Charged34
Percent Time Used29
Contractor(s)
JF CONSTRUCTION-MANAGEMENT GROUP
SUBCONTRACTOR(S) FOR CCSJ: 6329-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09181802
Totals215436.0010974.0051630.0023.9

CountyDENTON
HighwayUS0380
FromVARIOUS LOCATIONS IN THE DENTON COUNTY
ToMAINTENANCE SECTION
CSJ6330-72-001
Proj IDRMC - 633072001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001206480.0063442.8030.7
Work Order09-04-19
Work Began08-22-19
Work Completed
Time Computed09-11-19
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01191801
Totals206480.000.0063442.8030.7

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE DENTON COUNTY
ToMAINTENANCE SECTION
CSJ6330-77-001
Proj IDRMC - 633077001
Work TypeDELINEATOR AND OBJECT MARKER ASSEMBLIES
 
0.100251102.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SYNERGY SIGNS & SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01201801
Totals251102.000.000.000.0

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6332-44-001
Proj IDRMC - 633244001
Work TypeSPECIALTY MARKINGS
 
0.00163512.0044990.5070.8
Work Order06-28-19
Work Began07-08-19
Work Completed
Time Computed07-08-19
Contract Working Days365
Addl Days Granted0
Working Days Charged158
Percent Time Used43
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6332-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09181804
Totals63512.000.0044990.5070.8

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6333-19-001
Proj IDRMC - 633319001
Work TypeCALLOUT REFLECT PVMT MARKINGS & MARKERS
 
0.001203000.0085875.9542.3
Work Order02-05-19
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days730
Addl Days Granted0
Working Days Charged312
Percent Time Used42
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6333-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10181804
Totals203000.000.0085875.9542.3

CountyKAUFMAN
HighwayFM0548
FromFM 548 AT BIG BRUSHY CREEK RELIEF
ToFM 550 AT HACKBERRY CREEK
CSJ6333-38-001
Proj IDBPM - 633338001
Work TypeBPM - BRIDGE PREVENTATIVE MAINTENANCE
 
0.004182130.4039119.2021.4
Work Order11-26-19
Work Began12-02-19
Work Completed
Time Computed12-03-19
Contract Working Days60
Addl Days Granted0
Working Days Charged6
Percent Time Used10
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6333-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09191801
Totals182130.4039119.2039119.2021.4

CountyKAUFMAN
HighwayFM2578
FromFM2578 UNDERPASS
ToAT IH20
CSJ6333-39-001
Proj IDBPM - 633339001
Work TypeBPM - BRIDGE REPAIR
 
0.05560700.0061400.0099.9
Work Order10-22-19
Work Began10-23-19
Work Completed
Time Computed10-29-19
Contract Working Days30
Addl Days Granted0
Working Days Charged7
Percent Time Used23
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6333-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03191801
Totals60700.000.0061400.0099.9

CountyCOLLIN
HighwaySH0005
FromVARIOUS LOCATIONS IN COLLIN
ToCOUNTY
CSJ6333-63-001
Proj IDRMC - 633363001
Work TypeTREE & BRUSH REMOVAL AND TRIMMING
 
73.810162141.99122415.2375.4
Work Order02-05-19
Work Began02-12-19
Work Completed
Time Computed02-12-19
Contract Working Days365
Addl Days Granted0
Working Days Charged287
Percent Time Used78
Contractor(s)
ROAD SOLUTIONS L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6333-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11181803
Totals162141.990.00122415.2375.4