Monthly Local Let Maintenance Report For Dallas District As Of Aug 23, 2019 Page 1 Of 4

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed06-10-15
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.00100.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-58-001
Proj IDRMC - 630458001
Work TypeVEGETATION MANAGEMENT
 
0.001245175.00129936.3252.9
Work Order11-22-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days68
Addl Days Granted9
Working Days Charged36
Percent Time Used46
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6304-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161803
Totals245175.000.00129936.3252.9

CountyNAVARRO
HighwayBI0045F
FromVARIOUS ROADWAYS IN THE NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6310-24-001
Proj IDSUP - 631024001
Work TypePICNIC AREA MAINTENANCE
 
0.00127280.0021600.0079.1
Work Order11-22-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged602
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6310-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171831
Totals27280.001020.0021600.0079.1

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6315-43-001
Proj IDRMC - 631543001
Work TypeRAISED PAVEMENT MARKERS
 
0.001119011.7574100.7962.2
Work Order05-03-19
Work Began05-06-19
Work Completed
Time Computed05-13-19
Contract Working Days365
Addl Days Granted0
Working Days Charged81
Percent Time Used22
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12181801
Totals119011.752163.3574100.7962.2

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT
ToCOMPLEX
CSJ6317-55-001
Proj IDSUP - 631755001
Work TypeGROUNDS MAINTENANCE
 
0.001203437.4441382.9620.3
Work Order12-19-18
Work Began01-01-19
Work Completed
Time Computed01-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged206
Percent Time Used28
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6317-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10181830
Totals203437.449655.2441382.9620.3

CountyDALLAS
HighwayIH0045
FromSOUTHEAST DALLAS COUNTY
ToMAINTENANCE FACILITY
CSJ6319-83-001
Proj IDSUP - 631983001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00169340.0038873.00100.0
Work Order07-31-17
Work Began08-01-17
Work Completed07-31-19
Time Computed08-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged724
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6319-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171832
Totals69340.002349.0038873.00100.0

CountyELLIS
HighwayIH0045
FromDALLAS COUNTY LINE
ToTO NAVARRO COUNTY LINE
CSJ6320-79-001
Proj IDRMC - 632079001
Work TypeCABLE MEDIAN BARRIER SYSTEM REPAIR
 
0.001257500.00171995.0066.7
Work Order04-25-18
Work Began04-27-18
Work Completed
Time Computed05-02-18
Contract Working Days730
Addl Days Granted0
Working Days Charged455
Percent Time Used62
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6320-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12171803
Totals257500.006190.00171995.0066.7

CountyCOLLIN
HighwaySH0078
FromPICNIC ON SH78
ToLANDSCAPE ON SP399
CSJ6321-00-001
Proj IDSUP - 632100001
Work TypePICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.00188682.2871036.5280.1
Work Order07-20-17
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged724
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6321-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171833
Totals88682.283276.7371036.5280.1

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY AREA OFFICE
ToAND MAINTENANCE OFFICE
CSJ6321-02-001
Proj IDSUP - 632102001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00157490.6443910.6476.3
Work Order07-31-17
Work Began08-01-17
Work Completed
Time Computed08-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged725
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6321-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07171834
Totals57490.641829.6143910.6476.3

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT COMPLEX - 4777 E. HWY 80
ToMESQUITE, TEXAS 75150 AT SITES A THRU E
CSJ6326-32-001
Proj IDRMC - 632632001
Work TypeDISTRICT GROUNDS TREE TRIMMING & REMOVAL
 
0.00180890.0071425.00100.0
Work Order07-24-18
Work Began07-28-18
Work Completed07-26-19
Time Computed07-31-18
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
ALARCON CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6326-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06181801
Totals80890.000.0071425.00100.0

CountyNAVARRO
HighwaySH0031
FromNAVARRO AREA AND
ToMAINTENANCE FACILITY
CSJ6326-51-001
Proj IDSUP - 632651001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00122073.9216445.6074.5
Work Order11-22-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged602
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6326-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171832
Totals22073.92805.0816445.6074.5

CountyELLIS
HighwayFM0876
FromELLIS COUNTY MAINTENANCE AND
ToAREA OFFICE FACILITIES
CSJ6326-52-001
Proj IDSUP - 632652001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.001109038.0072669.0066.6
Work Order11-28-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged602
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6326-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171833
Totals109038.003850.0072669.0066.6