Monthly Local Let Maintenance Report For Dallas District As Of Sep 10, 2018 Page 1 Of 3

Last Update: Monday, September 10, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.7054110.0040.5
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged624
Percent Time Used85
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.700.0054110.0040.5

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyELLIS
HighwayFM0813
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6296-95-001
Proj IDRMC - 629695001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001274500.00195065.0071.0
Work Order02-22-16
Work Began01-26-16
Work Completed
Time Computed02-29-16
Contract Working Days730
Addl Days Granted189
Working Days Charged885
Percent Time Used96
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161801
Totals274500.0037295.00195065.0071.0

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6297-44-001
Proj IDRMC - 629744001
Work TypeSPECIALTY MARKINGS
 
0.001273952.00139889.0751.0
Work Order06-27-16
Work Began07-06-16
Work Completed
Time Computed07-05-16
Contract Working Days730
Addl Days Granted179
Working Days Charged787
Percent Time Used86
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161805
Totals273952.000.00139889.0751.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT
ToCOMPLEX
CSJ6302-56-001
Proj IDSUP - 630256001
Work TypeGROUNDS MAINTENANCE
 
0.00183010.30190014.7099.9
Work Order04-28-16
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted610
Working Days Charged853
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6302-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161830
Totals83010.3014339.33190014.7099.9

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-58-001
Proj IDRMC - 630458001
Work TypeVEGETATION MANAGEMENT
 
0.001245175.0097665.0039.8
Work Order11-22-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days68
Addl Days Granted9
Working Days Charged27
Percent Time Used35
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6304-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161803
Totals245175.000.0097665.0039.8

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN SOUTHWEST
ToDALLAS CO MAINTENANCE SECTION
CSJ6305-88-001
Proj IDRMC - 630588001
Work TypeVEGETATION MANAGEMENT
 
0.001293635.00213525.0072.7
Work Order11-22-16
Work Began12-06-16
Work Completed
Time Computed12-06-16
Contract Working Days82
Addl Days Granted9
Working Days Charged59
Percent Time Used64
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161804
Totals293635.006195.00213525.0072.7

CountyDENTON
HighwayIH0035E
FromDENTON COUNTY AREA OFFICE
ToAND MAINTENANCE FACILITIES
CSJ6308-43-001
Proj IDSUP - 630843001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00181221.7056511.5569.5
Work Order03-20-17
Work Began04-01-17
Work Completed
Time Computed04-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged518
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6308-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161830
Totals81221.703428.7056511.5569.5

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN THE KAUFMAN
ToROCKWALL MAINTENANCE SECTION
CSJ6309-29-001
Proj IDRMC - 630929001
Work TypeDITCH MAINT, DRIFTWOOD & GUARDRAIL CLEAN
 
0.001274790.00296180.4099.9
Work Order08-15-17
Work Began08-22-17
Work Completed
Time Computed08-22-17
Contract Working Days365
Addl Days Granted71
Working Days Charged368
Percent Time Used84
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171801
Totals274790.000.00296180.4099.9

CountyDENTON
HighwayFM0455
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6309-65-001
Proj IDRMC - 630965001
Work TypeROADSIDE MOWING
 
0.001225025.00168810.9075.0
Work Order06-15-17
Work Began06-19-17
Work Completed
Time Computed06-22-17
Contract Working Days46
Addl Days Granted0
Working Days Charged27
Percent Time Used58
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6309-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02171802
Totals225025.000.00168810.9075.0

CountyNAVARRO
HighwayBI0045F
FromVARIOUS ROADWAYS IN THE NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6310-24-001
Proj IDSUP - 631024001
Work TypePICNIC AREA MAINTENANCE
 
0.00127280.009990.0036.6
Work Order11-22-17
Work Began12-01-17
Work Completed
Time Computed12-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged271
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6310-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11171831
Totals27280.001230.009990.0036.6

CountyDENTON
HighwayFM1173
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6310-25-001
Proj IDRMC - 631025001
Work TypeTREE TRIMMING & TREE AND BRUSH REMOVAL
 
0.10094570.0083140.0087.9
Work Order09-25-17
Work Began09-27-17
Work Completed
Time Computed10-02-17
Contract Working Days365
Addl Days Granted0
Working Days Charged337
Percent Time Used92
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03171802
Totals94570.000.0083140.0087.9

page 1 | page 2 | page 3