Monthly State Let Maintenance Report For Dallas District As Of Nov 12, 2021 Page 1 Of 7

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL AND
ToCOLLIN COUNTIES
CSJ6179-66-001
Proj IDRMC - 617966001
Work TypeVEGETATION MANAGEMENT
 
0.001138484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABH TREE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6179-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11094014
Totals138484.000.000.000.0

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-98-001
Proj IDRMC - 626398001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001481998.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154005
Totals481998.500.000.000.0

CountyDALLAS
HighwayIH0030
FromNEAR ERVAY ST
ToNORTHWEST DRIVE
CSJ6285-62-001
Proj IDRMC - 628562001
Work TypePERFORM BASE O & M OF HOV LANE & BTM
 
11.10010595000.0015892557.8899.9
Work Order09-23-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days1,460
Addl Days Granted1,461
Working Days Charged2,217
Percent Time Used75
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6285-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154010
Totals10595000.00200690.8815892557.8899.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6317-51-001
Proj IDRMC - 631751001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.0011027494.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174008
Totals1027494.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6317-52-001
Proj IDRMC - 631752001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.0011099347.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6317-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174208
Totals1099347.000.000.000.0

CountyDENTON
HighwayUS0380
FromVARIOUS ROADWYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6322-81-001
Proj IDRMC - 632281001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.100562500.00447167.00100.0
Work Order03-09-18
Work Began03-12-18
Work Completed03-26-20
Time Computed03-16-18
Contract Working Days730
Addl Days Granted0
Working Days Charged685
Percent Time Used93
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6322-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01184207
Totals562500.000.00447167.00100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS MANAGED LANES IN DALLAS AND
ToTARRANT COUNTIES
CSJ6324-43-001
Proj IDRMC - 632443001
Work TypePERF BASED OPER & MAINT OF MANAGED LANES
 
16.5005662048.0010741601.2399.9
Work Order10-31-18
Work Began09-01-18
Work Completed
Time Computed09-01-18
Contract Working Days730
Addl Days Granted731
Working Days Charged1,153
Percent Time Used78
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05184210
Totals5662048.00258486.9710741601.2399.9

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON COUNTY
ToMAINTENANCE SECTION
CSJ6327-47-001
Proj IDRMC - 632747001
Work TypeGUARDRAIL REPAIR
 
0.1005738770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6327-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184007
Totals5738770.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6329-79-001
Proj IDRMC - 632979001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.001431000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6329-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194006
Totals431000.000.000.000.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6330-73-001
Proj IDRMC - 633073001
Work TypeSWEEPING AND DEBRIS
 
0.1002673830.801784400.48100.0
Work Order02-28-19
Work Began03-01-19
Work Completed11-05-21
Time Computed03-01-19
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184021
Totals2673830.800.001784400.48100.0

CountyELLIS
HighwaySH0034
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6333-28-001
Proj IDRMC - 633328001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKER
 
0.001619011.79483503.39100.0
Work Order10-02-19
Work Began10-07-19
Work Completed02-26-21
Time Computed09-26-19
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6333-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194010
Totals619011.790.00483503.39100.0

CountyDENTON
HighwayFM0455
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6336-29-001
Proj IDRMC - 633629001
Work TypeROADSIDE MOWING
 
0.001262790.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days46
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JMT CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6336-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184016
Totals262790.000.000.000.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN DENTON
ToMAINTENANCE SECTION
CSJ6336-77-001
Proj IDRMC - 633677001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001895600.37978664.05100.0
Work Order08-30-19
Work Began09-03-19
Work Completed03-26-21
Time Computed09-06-19
Contract Working Days365
Addl Days Granted120
Working Days Charged485
Percent Time Used100
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6336-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02194009
Totals895600.370.00978664.05100.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6338-26-001
Proj IDRMC - 633826001
Work TypeSTORM SEWER AND INLET CLEANING
 
0.0011042591.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184010
Totals1042591.150.000.000.0

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE EAST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6338-27-001
Proj IDRMC - 633827001
Work TypeSTORM SEWER AND INLET CLEANING
 
0.001871029.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184201
Totals871029.000.000.000.0

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6338-59-001
Proj IDRMC - 633859001
Work TypeVEGETATION MANGAEMENT
 
0.1001034090.00686870.0066.4
Work Order00-00-00
Work Began05-15-20
Work Completed
Time Computed04-29-19
Contract Working Days164
Addl Days Granted0
Working Days Charged117
Percent Time Used71
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6338-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02194010
Totals1034090.00118548.00686870.0066.4

CountyNAVARRO
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6341-43-001
Proj IDRMC - 634143001
Work TypePOTHOLE REPAIR
 
0.001621400.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6341-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194011
Totals621400.000.000.000.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6342-44-001
Proj IDRMC - 634244001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.001773540.001037281.3699.9
Work Order10-02-19
Work Began09-26-19
Work Completed
Time Computed10-08-19
Contract Working Days730
Addl Days Granted90
Working Days Charged753
Percent Time Used91
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6342-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06194211
Totals773540.00190436.841037281.3699.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6343-27-001
Proj IDRMC - 634327001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0013273523.003223760.75100.0
Work Order09-26-19
Work Began10-01-19
Work Completed10-07-21
Time Computed10-03-19
Contract Working Days730
Addl Days Granted0
Working Days Charged726
Percent Time Used99
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07194005
Totals3273523.00122542.503223760.75100.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6343-71-001
Proj IDRMC - 634371001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.100695630.20699101.6299.9
Work Order00-00-00
Work Began07-19-20
Work Completed
Time Computed07-19-19
Contract Working Days365
Addl Days Granted0
Working Days Charged368
Percent Time Used100
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6343-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12194007
Totals695630.200.00699101.6299.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7