Monthly State Let Maintenance Report For Dallas District As Of Jan 10, 2018 Page 3 Of 6

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-01-001
Proj IDRMC - 630201001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001445740.00386326.0586.6
Work Order01-23-17
Work Began01-30-17
Work Completed
Time Computed01-30-17
Contract Working Days365
Addl Days Granted0
Working Days Charged330
Percent Time Used90
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164211
Totals445740.0094602.59386326.0586.6

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-06-001
Proj IDRMC - 630206001
Work TypeGUARD FENCE & CABLE REPAIR
 
0.0011179985.00931857.0778.9
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164213
Totals1179985.0033197.81931857.0778.9

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-13-001
Proj IDRMC - 630213001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011346279.00561266.6041.6
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
PANNELL INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164214
Totals1346279.0044756.65561266.6041.6

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-14-001
Proj IDRMC - 630214001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011672328.40741448.3244.3
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6302-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164014
Totals1672328.4043367.84741448.3244.3

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-16-001
Proj IDRMC - 630216001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.0011773137.00867925.5048.9
Work Order10-21-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged420
Percent Time Used57
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164215
Totals1773137.0068160.25867925.5048.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-84-001
Proj IDRMC - 630284001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001486448.163523614.6099.9
Work Order01-06-17
Work Began01-09-17
Work Completed
Time Computed01-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged351
Percent Time Used96
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164212
Totals486448.160.003523614.6099.9

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6304-32-001
Proj IDRMC - 630432001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001267136.00260472.5397.5
Work Order01-10-17
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted135
Working Days Charged340
Percent Time Used68
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164011
Totals267136.000.00260472.5397.5

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-57-001
Proj IDRMC - 630457001
Work TypeRETRORELECTORIZED PAVEMENT MARKINGS
 
0.001370836.20354464.3495.5
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged309
Percent Time Used84
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164012
Totals370836.2037277.83354464.3495.5

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATIONS IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6305-87-001
Proj IDRMC - 630587001
Work TypeVEGETATION MANAGEMENT
 
0.001477882.00293839.5061.4
Work Order11-21-16
Work Began11-30-16
Work Completed
Time Computed11-30-16
Contract Working Days115
Addl Days Granted26
Working Days Charged45
Percent Time Used31
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6305-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164017
Totals477882.0017272.50293839.5061.4

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6305-96-001
Proj IDRMC - 630596001
Work TypeVEGETATION MANAGEMENT
 
0.001661844.92329702.4849.8
Work Order06-14-17
Work Began05-30-17
Work Completed
Time Computed06-21-17
Contract Working Days124
Addl Days Granted0
Working Days Charged38
Percent Time Used30
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6305-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164013
Totals661844.920.00329702.4849.8

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6306-13-001
Proj IDRMC - 630613001
Work TypeCALLOUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001599350.0012525.002.0
Work Order03-09-17
Work Began03-15-17
Work Completed
Time Computed03-16-17
Contract Working Days730
Addl Days Granted0
Working Days Charged279
Percent Time Used38
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6306-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164014
Totals599350.000.0012525.002.0

CountyKAUFMAN
HighwayIH0020
FromIH, US, SH, FM, AND SP ROADWAYS IN THE
ToKAUFMAN MAINTENANCE SECTION
CSJ6306-20-001
Proj IDRMC - 630620001
Work TypeVEGETATION MANAGEMENT (NORTH SIDE)
 
0.001672502.90340533.5950.0
Work Order03-07-17
Work Began03-14-17
Work Completed
Time Computed03-14-17
Contract Working Days122
Addl Days Granted32
Working Days Charged42
Percent Time Used27
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6306-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164016
Totals672502.900.00340533.5950.0

CountyKAUFMAN
HighwayUS0175
FromUS, SH, FM, AND BU ROADWAYS TH THE
ToKAUFMAN-ROCKWALL MAINTENANCE SECTION
CSJ6306-21-001
Proj IDRMC - 630621001
Work TypeVEGETATION MANAGEMENT (SOUTH SIDE)
 
0.001596370.00281404.0047.1
Work Order03-16-17
Work Began03-24-17
Work Completed
Time Computed03-23-17
Contract Working Days114
Addl Days Granted18
Working Days Charged44
Percent Time Used33
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6306-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174015
Totals596370.000.00281404.0047.1

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6306-46-001
Proj IDRMC - 630646001
Work TypeVEGETATION MANAGEMENT
 
0.001331546.00158780.9047.8
Work Order12-13-16
Work Began12-13-16
Work Completed
Time Computed12-13-16
Contract Working Days108
Addl Days Granted15
Working Days Charged46
Percent Time Used37
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164215
Totals331546.000.00158780.9047.8

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATION IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6306-86-001
Proj IDRMC - 630686001
Work TypeRETROREFLECTROZIED PAVEMENT MARKINGS
 
0.001393699.99392697.8199.7
Work Order04-19-17
Work Began04-26-17
Work Completed
Time Computed04-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged244
Percent Time Used66
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164011
Totals393699.9917499.90392697.8199.7

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6307-77-001
Proj IDRMC - 630777001
Work TypeRETROREFLECTORIZED PAVEMENT MARKINGS
 
0.001397990.00382878.1896.2
Work Order04-10-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164214
Totals397990.0045566.18382878.1896.2

CountyDALLAS
HighwaySH0352
FromVARIOUS LOCATIONS IN SOUTHEAST
ToDALLAS COOUNTY MAINTENANCE SECTION
CSJ6307-78-001
Proj IDRMC - 630778001
Work TypeRETROREFLECTORIZED PAVEMENT MARKINGS
 
0.100421489.28391884.3992.9
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164216
Totals421489.2811856.37391884.3992.9

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-59-001
Proj IDRMC - 630859001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001411860.00735322.7299.9
Work Order02-07-17
Work Began01-17-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged309
Percent Time Used84
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164215
Totals411860.000.00735322.7299.9

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-60-001
Proj IDRMC - 630860001
Work TypeFULL DEPTH CONCRETE REPAIR
 
0.001424880.00849921.7899.9
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164012
Totals424880.000.00849921.7899.9

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-88-001
Proj IDRMC - 630888001
Work TypePOTHOLE REPAIR
 
0.001446225.00249675.0055.9
Work Order01-03-17
Work Began01-10-17
Work Completed
Time Computed01-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged350
Percent Time Used47
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164015
Totals446225.00113550.00249675.0055.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6