Monthly State Let Maintenance Report For Dallas District As Of Apr 10, 2018 Page 3 Of 6

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATIONS IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6305-87-001
Proj IDRMC - 630587001
Work TypeVEGETATION MANAGEMENT
 
0.001477882.00298599.5062.4
Work Order11-21-16
Work Began11-30-16
Work Completed
Time Computed11-30-16
Contract Working Days115
Addl Days Granted30
Working Days Charged50
Percent Time Used34
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6305-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164017
Totals477882.004760.00298599.5062.4

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6305-96-001
Proj IDRMC - 630596001
Work TypeVEGETATION MANAGEMENT
 
0.001661844.92329702.4849.8
Work Order06-14-17
Work Began05-30-17
Work Completed
Time Computed06-21-17
Contract Working Days124
Addl Days Granted0
Working Days Charged38
Percent Time Used30
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6305-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164013
Totals661844.920.00329702.4849.8

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6306-13-001
Proj IDRMC - 630613001
Work TypeCALLOUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001599350.0097716.1416.3
Work Order03-09-17
Work Began03-15-17
Work Completed
Time Computed03-16-17
Contract Working Days730
Addl Days Granted0
Working Days Charged377
Percent Time Used51
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6306-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164014
Totals599350.0072307.9297716.1416.3

CountyKAUFMAN
HighwayIH0020
FromIH, US, SH, FM, AND SP ROADWAYS IN THE
ToKAUFMAN MAINTENANCE SECTION
CSJ6306-20-001
Proj IDRMC - 630620001
Work TypeVEGETATION MANAGEMENT (NORTH SIDE)
 
0.001672502.90340533.5950.0
Work Order03-07-17
Work Began03-14-17
Work Completed
Time Computed03-14-17
Contract Working Days122
Addl Days Granted32
Working Days Charged42
Percent Time Used27
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6306-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12164016
Totals672502.900.00340533.5950.0

CountyKAUFMAN
HighwayUS0175
FromUS, SH, FM, AND BU ROADWAYS TH THE
ToKAUFMAN-ROCKWALL MAINTENANCE SECTION
CSJ6306-21-001
Proj IDRMC - 630621001
Work TypeVEGETATION MANAGEMENT (SOUTH SIDE)
 
0.001596370.00288784.0048.4
Work Order03-16-17
Work Began03-24-17
Work Completed
Time Computed03-23-17
Contract Working Days114
Addl Days Granted18
Working Days Charged48
Percent Time Used36
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6306-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174015
Totals596370.007380.00288784.0048.4

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6306-46-001
Proj IDRMC - 630646001
Work TypeVEGETATION MANAGEMENT
 
0.001331546.00162425.9048.9
Work Order12-13-16
Work Began12-13-16
Work Completed
Time Computed12-13-16
Contract Working Days108
Addl Days Granted15
Working Days Charged54
Percent Time Used43
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164215
Totals331546.003645.00162425.9048.9

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATION IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6306-86-001
Proj IDRMC - 630686001
Work TypeRETROREFLECTROZIED PAVEMENT MARKINGS
 
0.001393699.99392697.8199.7
Work Order04-19-17
Work Began04-26-17
Work Completed
Time Computed04-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6306-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164011
Totals393699.990.00392697.8199.7

CountyDALLAS
HighwaySH0352
FromVARIOUS LOCATIONS IN SOUTHEAST
ToDALLAS COOUNTY MAINTENANCE SECTION
CSJ6307-78-001
Proj IDRMC - 630778001
Work TypeRETROREFLECTORIZED PAVEMENT MARKINGS
 
0.100421489.28406744.5596.5
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164216
Totals421489.280.00406744.5596.5

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-88-001
Proj IDRMC - 630888001
Work TypePOTHOLE REPAIR
 
0.001446225.00280168.0062.7
Work Order01-03-17
Work Began01-10-17
Work Completed
Time Computed01-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged440
Percent Time Used60
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164015
Totals446225.0026493.00280168.0062.7

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-89-001
Proj IDRMC - 630889001
Work TypePOTHOLE REPAIR
 
0.001427350.00205273.3048.0
Work Order01-03-17
Work Began01-10-17
Work Completed
Time Computed01-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged440
Percent Time Used60
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164217
Totals427350.0011698.40205273.3048.0

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-90-001
Proj IDRMC - 630890001
Work TypePOTHOLE REPAIR
 
0.001453875.00591246.0099.9
Work Order01-03-17
Work Began01-10-17
Work Completed
Time Computed01-10-17
Contract Working Days730
Addl Days Granted0
Working Days Charged440
Percent Time Used60
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164016
Totals453875.0068328.00591246.0099.9

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6308-91-001
Proj IDRMC - 630891001
Work TypePOTHOLE REPAIR
 
0.001418075.00276399.2066.1
Work Order01-06-17
Work Began01-17-17
Work Completed
Time Computed01-13-17
Contract Working Days730
Addl Days Granted0
Working Days Charged433
Percent Time Used59
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164218
Totals418075.0024408.05276399.2066.1

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN ELLIS COUNTY AND
ToIH45 IN NAVARRO COUNTY
CSJ6309-46-001
Proj IDRMC - 630946001
Work TypeVEGETATION MANAGEMENT
 
0.001628617.74525127.4383.5
Work Order04-13-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days240
Addl Days Granted0
Working Days Charged107
Percent Time Used44
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174014
Totals628617.740.00525127.4383.5

CountyDENTON
HighwaySH0114
FromVARIOUS ROADWAYS IN THE DENTON
ToMAINTENANCE SECTION
CSJ6309-58-001
Proj IDRMC - 630958001
Work TypeRETROREFLECTORIZED PAVEMENT MARKINGS
 
0.100235675.25199154.9184.5
Work Order06-02-17
Work Began06-08-17
Work Completed
Time Computed06-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged292
Percent Time Used80
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174227
Totals235675.25911.76199154.9184.5

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN ELLIS COUNTY
ToAND IH 45 IN NAVARRO COUNTY
CSJ6309-80-001
Proj IDRMC - 630980001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001248095.000.000.0
Work Order01-31-18
Work Began02-07-18
Work Completed
Time Computed02-07-18
Contract Working Days365
Addl Days Granted0
Working Days Charged47
Percent Time Used12
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174008
Totals248095.000.000.000.0

CountyDALLAS
HighwayIH0035E
FromMANAGED LANES NORTH OF ROYAL LANE
ToFM 2181 (SWISHER ROAD)
CSJ6309-95-001
Proj IDRMC - 630995001
Work TypePERF BASED OPER & MAINT OF MANAGED LANES
 
0.0011589000.00749100.0047.1
Work Order05-02-17
Work Began05-18-17
Work Completed
Time Computed05-18-17
Contract Working Days730
Addl Days Granted0
Working Days Charged312
Percent Time Used42
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174015
Totals1589000.0060000.00749100.0047.1

CountyELLIS
HighwayFM0984
FromFM 984, FM 985 IN ELLIS COUNTY AND
ToFM 3194 IN NAVARRO COUNTY
CSJ6310-01-001
Proj IDRMC - 631001001
Work TypeREHABILITATION OF EXISTING CULVERTS
 
0.001244090.00168983.4069.2
Work Order10-24-17
Work Began10-23-17
Work Completed
Time Computed10-31-17
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6310-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174215
Totals244090.0021460.00168983.4069.2

CountyDENTON
HighwayIH0035
FromVARIOUS LOCATIONS IN THE DENTON
ToMAINTENANCE SECTION
CSJ6310-26-001
Proj IDRMC - 631026001
Work TypePOTHOLE REPAIR
 
0.001357000.0020030.005.6
Work Order02-23-18
Work Began00-00-00
Work Completed
Time Computed03-02-18
Contract Working Days365
Addl Days Granted0
Working Days Charged26
Percent Time Used7
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174011
Totals357000.0020030.0020030.005.6

CountyDENTON
HighwayFM0407
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6310-27-001
Proj IDRMC - 631027001
Work TypeSPECIALTY MARKINGS
 
0.001592022.61107720.0418.1
Work Order11-06-17
Work Began11-13-17
Work Completed
Time Computed11-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6310-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174012
Totals592022.6165972.00107720.0418.1

CountyELLIS
HighwaySH0034
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY
CSJ6310-30-001
Proj IDRMC - 631030001
Work TypeROADSIDE MOWING
 
0.001325504.36160982.5849.4
Work Order07-10-17
Work Began07-14-17
Work Completed
Time Computed07-17-17
Contract Working Days84
Addl Days Granted0
Working Days Charged37
Percent Time Used44
Contractor(s)
C & C MOWING CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174214
Totals325504.360.00160982.5849.4

page 1 | page 2 | page 3 | page 4 | page 5 | page 6