Monthly Local Let Maintenance Report For El Paso District As Of Nov 12, 2021 Page 1 Of 4

Last Update: Friday, November 12, 2021
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6192-77-001
Proj IDRMC - 619277001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
300.00023200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SUGARLAND PROFESSIONAL LANDSCAPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092405
Totals23200.000.000.000.0

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS ALONG IH 0010
ToVARIOUS LOCATIONS ALONG IH 0010
CSJ6205-10-001
Proj IDRMC - 620510001
Work TypeJANITORIAL/GROUND MAINTENANCE(PICNIC)
 
200.00035940.0032100.0089.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-10
Work Began02-01-10
Work Completed
Time Computed02-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
GUERRERO STAR CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6205-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12092405
Totals35940.000.0032100.0089.3

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6207-50-001
Proj IDRMC - 620750001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
270.00058002.5456085.9196.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-11-10
Work Began08-18-10
Work Completed
Time Computed08-18-10
Contract Working Days28
Addl Days Granted0
Working Days Charged26
Percent Time Used92
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6207-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07102407
Totals58002.540.0056085.9196.6

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6218-16-001
Proj IDRMC - 621816001
Work TypeCULVERT AND STORM SEWER CLEANING
 
400.000195300.0042832.8421.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-30-10
Work Began01-07-11
Work Completed
Time Computed01-07-11
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
LOMELI AND SONS LANDSCAPING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6218-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11102402
Totals195300.000.0042832.8421.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6218-93-001
Proj IDRMC - 621893001
Work TypeJANITORIAL/GROUND MAINTENANCE
 
200.00037165.0037165.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-11
Work Began02-01-11
Work Completed
Time Computed02-01-11
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
GUERRERO STAR CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6218-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12102404
Totals37165.000.0037165.0099.9

CountyJEFF DAVIS
HighwaySH0017
FromREEVES COUNTY LINE
ToPRESIDIO COUNTY LINE
CSJ6221-61-001
Proj IDRMC - 622161001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
177.27039678.0019839.0050.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-19-11
Work Began12-22-11
Work Completed
Time Computed12-22-11
Contract Working Days24
Addl Days Granted0
Working Days Charged15
Percent Time Used62
Contractor(s)
PHIL PARKS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02112405
Totals39678.000.0019839.0050.0

CountyBREWSTER
HighwayUS0067
FromPECOS COUNTY LINE
ToPRESIDIO COUNTY LINE
CSJ6221-62-001
Proj IDRMC - 622162001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
177.27060804.0031572.0051.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-16-11
Work Began01-16-12
Work Completed
Time Computed12-27-11
Contract Working Days22
Addl Days Granted0
Working Days Charged14
Percent Time Used63
Contractor(s)
PHIL PARKS CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02112406
Totals60804.000.0031572.0051.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6221-64-001
Proj IDRMC - 622164001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
149.0000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK VINING ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6221-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02112408
Totals0.000.000.000.0

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6223-49-001
Proj IDSUP - 622349001
Work TypeJANITORIAL SERVICES
 
0.001182980.80198229.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-25-11
Work Began08-01-11
Work Completed
Time Computed08-01-11
Contract Working Days730
Addl Days Granted92
Working Days Charged792
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
PROFESSIONAL CONTRACT SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6223-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07112430
Totals182980.800.00198229.2099.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS IN HUDSPETH COUNTY
ToVARIOUS LOCATIONS IN HUDSPETH COUNTY
CSJ6225-07-001
Proj IDRMC - 622507001
Work TypeMILLING AND PLANING
 
2.50070300.00100143.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-16-11
Work Began07-25-11
Work Completed
Time Computed07-25-11
Contract Working Days30
Addl Days Granted0
Working Days Charged30
Percent Time Used100
Contractor(s)
DUSTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6225-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05112403
Totals70300.000.00100143.9699.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6240-04-001
Proj IDRMC - 624004001
Work TypePAVEMENT MARKINGS
 
150.000252924.03254618.6499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-23-12
Work Began07-23-12
Work Completed
Time Computed07-23-12
Contract Working Days40
Addl Days Granted0
Working Days Charged29
Percent Time Used72
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6240-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04122401
Totals252924.030.00254618.6499.9

CountyEL PASO
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUSLOCATIONS
CSJ6249-98-001
Proj IDRMC - 624998001
Work TypeILLUMINATION MAINTENANCE REPAIR
 
100.000293336.00370379.0699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-13
Work Began02-01-13
Work Completed
Time Computed02-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6249-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01132401
Totals293336.000.00370379.0699.9

CountyEL PASO
HighwayIH0010
FromTRAVEL INFORMATION CENTER - ANTHONY, TX
ToTRAVEL INFORMATION CENTER
CSJ6251-54-001
Proj IDSUP - 625154001
Work TypeJANITORIAL SERVICES
 
0.010142063.12142291.0199.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-29-12
Work Began11-01-12
Work Completed
Time Computed11-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6251-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10122430
Totals142063.120.00142291.0199.9

CountyHUDSPETH
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6293-96-001
Proj IDRMC - 629396001
Work TypeROADWAY LEVEL UP
 
1.800421150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162406
Totals421150.000.000.000.0

CountyCULBERSON
HighwayIH0010
FromVARIOUS HIGHWAYS
ToVARIOUS HIGHWAYS
CSJ6344-59-001
Proj IDRMC - 634459001
Work TypePICNIC AREA MAINTENANCE
 
100.00053100.0051125.0096.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-12-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
ABOVE ALL CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6344-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202405
Totals53100.001625.0051125.0096.2

CountyEL PASO
HighwaySL0375
FromTRANSMOUNTAIN
ToTRANSMOUNTAIN
CSJ6346-00-001
Proj IDRMC - 634600001
Work TypePICNIC AREA MAINTENANCE
 
10.00038736.0021699.6056.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged207
Percent Time Used56
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6346-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08202406
Totals38736.001560.0021699.6056.0

CountyEL PASO
HighwayIH0010
FromEL PASO DISTRICT COMPLEX
ToEL PASO DISTRICT COMPLEX
CSJ6347-23-001
Proj IDSUP - 634723001
Work TypeJANITORIAL SERVICES
 
0.001315600.00287985.0091.2
Work Order01-01-20
Work Began01-02-20
Work Completed
Time Computed01-02-20
Contract Working Days730
Addl Days Granted0
Working Days Charged636
Percent Time Used87
Contractor(s)
WORKQUEST
GOODWILL INDUSTRIES OF EL PASO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6347-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12192430
Totals315600.0013150.00287985.0091.2

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6349-85-001
Proj IDRMC - 634985001
Work TypeBARRICADES, SIGNS, TRAFFIC CONTROL
 
200.000240350.00359162.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-12-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged538
Percent Time Used73
Contractor(s)
APACHE BARRICADE & SIGN
SUBCONTRACTOR(S) FOR CCSJ: 6349-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03202407
Totals240350.0029055.00359162.5099.9

CountyCULBERSON
HighwayIH0010
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6349-88-001
Proj IDRMC - 634988001
Work TypeMETAL BEAM GUARDRAIL REPAIR
 
100.000266840.00290947.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-11-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
SYNERGY PROJECT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03202408
Totals266840.0047878.00290947.5099.9

CountyBREWSTER
HighwayUS0090
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6353-30-001
Proj IDRMC - 635330001
Work TypeMETAL BEAM GUARDRAIL REPAIR
 
150.000177500.00281750.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-20
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
MIJELUM, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6353-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04202402
Totals177500.00107615.00281750.0099.9

page 1 | page 2 | page 3 | page 4