Monthly State Let Construction Report For Fort Worth District As Of Mar 13, 2024 Page 5 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
To.
CSJ0902-00-340
Proj IDF 2023(615)
Work TypeBRIDGE MAINTENANCE
 
1689803.50596269.0535.2
CountyTARRANT
HighwayIH 20
FromGREEN OAKS BLVD
ToKELLY ELLIOTT RD
CSJ2374-05-097
Proj IDF 2023(672)
Work TypeCULVERT & STORM DRAINAGE WORK
 
724372.506200.000.8
Work Order10-06-23
Work Began11-14-23
Work Completed
Time Computed11-06-23
Contract Working Days342
Addl Days Granted0
Working Days Charged70
Percent Time Used20
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-340
FC TRAFFIC CONTROL, INC. (0.00)
S&S BRIDGE PAINTING (0.00)
TEXOP CONSTRUCTION (0.00)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.00)
IMPACT CONTRACTORS, LLC (0.00)
FORTSON CONTRACTING, INC. (1.76)
MOBILE ASSET MANAGEMENT LLC (1.98)
Contract #04233026
Totals2414176.00352832.87602469.0524.9

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToWITHIN THE FORT WORTH DISTRICT
CSJ0902-00-357
Proj IDF 2023(970)
Work TypeREHABILITATION OF EXISTING ROAD
 
4647055.002648516.4556.9
Work Order07-26-23
Work Began08-28-23
Work Completed
Time Computed08-26-23
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-00-357
ACT SAW CUTTING & REMOVAL (5.10)
BRENDA PRICE TRUCKING (1.07)
NORTEX CONCRETE LIFT & STABILIZATION, INC. (1.04)
Contract #06233425
Totals4647055.00687131.952648516.4556.9

CountyWISE
HighwayCR
FromCR 1590 AT BIG SANDY CREEK
To.
CSJ0902-20-102
Proj IDBR 1502(024)
Work TypeBRIDGE REPLACEMENT
 
883443.000.000.0
Work Order09-21-22
Work Began00-00-00
Work Completed
Time Computed10-22-22
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESSON CONSTRUCTION SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-20-102
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (6.27)
BARRICADES UNLIMITED (1.29)
HODGES AND SON CONSTRUCTION COMPANY, INC. (9.67)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (11.30)
SOUTHERN CROSS CONTRACTORS, LLC (4.98)
TORO BRAVO CONSTRUCTION, LLC (0.77)
DUSTROL, INC. (0.93)
Contract #08223042
Totals883443.000.000.000.0

CountyPARKER
HighwayCS
FromPINE ST. @ GRASSY BRANCH
To.
CSJ0902-38-131
Proj IDBR 2021(491)
Work TypeBRIDGE REPLACEMENT
 
0.100462918.65451044.3097.4
CountyPARKER
HighwayCS
FromCHERRY ST AT GRASSY BRANCH
To.
CSJ0902-38-133
Proj IDBR 2021(445)
Work TypeBRIDGE REPLACEMENT
 
0.100528026.90398295.6796.8
Work Order07-20-22
Work Began09-21-22
Work Completed
Time Computed08-20-22
Contract Working Days118
Addl Days Granted0
Working Days Charged303
Percent Time Used256
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-38-131
HODGES AND SON CONSTRUCTION COMPANY, INC. (7.18)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.08)
PEACHTREE CONSTRUCTION, LTD. (5.74)
TEX OP CONSTRUCTION, LP (0.80)
LINEAR TRAFFIC MARKINGS LLC (0.44)
TOTAL HIGHWAY MAINTENANCE, LLC (1.15)
WOLFE CONSTRUCTION GROUP, INCORPORATED (2.95)
TORO BRAVO CONSTRUCTION, LLC (0.35)
A-CORE CONCRETE CUTTING, INC. (0.75)
Contract #06223235
Totals990945.550.00849339.9797.0

CountyPARKER
HighwayCS
FromON BAILEY RANCH FROM HS
ToFM 1187
CSJ0902-38-145
Proj IDSTP 2023(142)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
469260.410.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-38-145
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243036
Totals469260.410.000.000.0

CountyPALO PINTO
HighwayCR
FromNEW HOPE ROAD AT WARD BRANCH
To.
CSJ0902-39-029
Proj IDBR 2022(022)
Work TypeBRIDGE REPLACEMENT
 
724492.00510111.8571.2
Work Order09-06-23
Work Began11-03-23
Work Completed
Time Computed10-07-23
Contract Working Days64
Addl Days Granted0
Working Days Charged74
Percent Time Used115
Contractor(s)
PMCO CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-029
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.00)
AWP SAFETY (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.00)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.00)
PEACHTREE CONSTRUCTION, LTD. (0.00)
STRIPE-A-ZONE, LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
Contract #08233270
Totals724492.00133647.50510111.8571.2

CountyPALO PINTO
HighwayVA
FromVARIOUS LOCATIONS @ PALO PINTO_MTNS
ToSTATE PARK OFF OF FM 2372
CSJ0902-39-040
Proj IDC 902-39-40
Work TypeNEW LOCATION NON-FREEWAY
 
0.10011699665.1613367442.6699.9
Work Order09-16-21
Work Began05-17-22
Work Completed
Time Computed10-17-21
Contract Working Days254
Addl Days Granted254
Working Days Charged445
Percent Time Used87
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-39-040
BARRICADES UNLIMITED (0.41)
FARR FOUNDATION, INC. (1.41)
MARCOM"S MOWING SERVICE, LLC (0.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.51)
SLATON BROS, INC. (1.76)
AR ROJAS CONSTRUCTION, INC (0.21)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (13.61)
HARDROCK UTILITY CONTRACTORS, L.L.C. (4.64)
BARRILLEAUX EXPRESS, LLC (0.69)
A.L. CONSTRUCTION LLC (0.86)
TORO BRAVO CONSTRUCTION, LLC (0.33)
Contract #08213019
Totals11699665.16726762.0213367442.6699.9

CountyTARRANT
HighwayCS
FromFOREST HILL DR. AT TRIB. OF VILLAGE
ToCREEK IN FOREST HILL.
CSJ0902-48-659
Proj IDBR 2006(543)
Work TypeREPLACE BRIDGES AND APPROACHES
 
0.1002252080.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CD BUILDERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-659
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08153244
Totals2252080.580.000.000.0

CountyTARRANT
HighwayCS
FromE. LONG AVENUE OVER LITTLE FOSSIL C
ToIN FORT WORTH
CSJ0902-48-894
Proj IDBR 1502(322)
Work TypeBRIDGE REPLACEMENT
 
4807165.350.000.0
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed10-08-23
Contract Working Days320
Addl Days Granted0
Working Days Charged27
Percent Time Used8
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-48-894
BARRICADES UNLIMITED (0.70)
ACT SAW CUTTING & REMOVAL (0.15)
TEX OP CONSTRUCTION, LP (0.37)
BEAN ELECTRICAL, INC. (0.66)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (0.97)
WYLIE DRILLING & DRAINAGE, INC. (3.60)
PRIMATE CONSTRUCTION, LP (0.18)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.19)
FORTSON CONTRACTING, INC. (2.26)
BREDA COMPANY, INC. (0.97)
DFW REBAR, INC. (0.17)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.16)
Contract #08233220
Totals4807165.350.000.000.0

CountyJOHNSON
HighwayVA
FromVARIOUS LOCATIONS IN JOHNSON CO
To.
CSJ0902-50-122
Proj IDC 902-50-122
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.1002237555.89884716.3639.5
Work Order04-19-23
Work Began07-10-23
Work Completed
Time Computed05-20-23
Contract Working Days171
Addl Days Granted66
Working Days Charged157
Percent Time Used66
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0902-50-122
NORTHEASTERN PAVERS, LLC (34.61)
SYNERGY SIGNS & SERVICES LLC (1.37)
J. H. ODEN CONTRACTING COMPANY (1.33)
RAMBO CONTRACTING, INC. (3.64)
TRP CONSTRUCTION GROUP, LLC (3.01)
Contract #03233021
Totals2237555.8982026.31884716.3639.5

CountyJOHNSON
HighwayVA
FromALSBURY BLVD; FROM FM 731
ToIH 35W NB FRONTAGE RD
CSJ0902-50-143
Proj IDSTP 2024(633)VRU
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
730197.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed05-03-24
Contract Working Days108
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-50-143
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243240
Totals730197.550.000.000.0

CountyTARRANT
HighwayCS
FromGLADE RD./WEST 29TH ST
ToAT BIG BEAR CREEK
CSJ0902-90-061
Proj IDBR 2020(440)
Work TypeBRIDGE REPLACEMENT
 
0.1001303926.151269124.1497.3
CountyTARRANT
HighwayCS
FromGLADE RD; NB SH 360 FRONTAGE RD
ToWEST AIRFIELD DR
CSJ0902-90-117
Proj IDSTP 1902(347)MM
Work TypeREHABILITATION OF EXISTING ROAD
 
5035216.645143425.2499.9
Work Order01-10-22
Work Began02-28-22
Work Completed
Time Computed02-10-22
Contract Working Days192
Addl Days Granted106
Working Days Charged297
Percent Time Used99
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-061
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.73)
RAMBO CONTRACTING, INC. (5.21)
FARR FOUNDATION, INC. (1.86)
TEXOP CONSTRUCTION (0.61)
PEACHTREE CONSTRUCTION, LTD. (4.74)
BREDA COMPANY, INC. (0.00)
WG ENGINEERING & CONSTRUCTION, LLC (7.42)
LAUGHLEY BRIDGE & CONSTRUCTION, INC. (2.35)
FORTSON CONTRACTING, INC. (0.93)
ACT SAW CUTTING & REMOVAL (0.28)
TRP CONSTRUCTION GROUP, LLC (0.26)
SOUTHEAST GRINDING AND GROOVING LLC (0.04)
SOUTHERN CROSS CONTRACTORS, LLC (0.17)
Contract #11213209
Totals6339142.790.006412549.3899.9

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS IN TARRANT CO
To.
CSJ0902-90-104
Proj IDC 902-90-104
Work TypeTRAFFIC CONTROL DEVICES
 
0.1001850378.36590880.1331.9
Work Order09-08-20
Work Began07-12-21
Work Completed
Time Computed10-09-20
Contract Working Days250
Addl Days Granted0
Working Days Charged170
Percent Time Used68
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-104
MEDELLIN HDD LLC (0.45)
FC TRAFFIC CONTROL, INC. (0.18)
Contract #08203034
Totals1850378.36139968.50590880.1331.9

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS IN TARRANT CO
To.
CSJ0902-90-105
Proj IDC 902-90-105
Work TypeTRAFFIC CONTROL DEVICES
 
0.1002216191.751663497.7575.0
Work Order09-29-21
Work Began05-09-23
Work Completed
Time Computed12-29-21
Contract Working Days300
Addl Days Granted0
Working Days Charged131
Percent Time Used43
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-105
KHONSU ENTERPRISE LLC (6.13)
Contract #08213251
Totals2216191.7537994.731663497.7575.0

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS IN TARRANT CO
To.
CSJ0902-90-106
Proj IDNH 1902(230)
Work TypeTCD
 
0.1004346466.812270432.8952.2
Work Order10-25-19
Work Began05-04-21
Work Completed
Time Computed01-23-20
Contract Working Days512
Addl Days Granted360
Working Days Charged451
Percent Time Used51
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-106
COLLIER SERVICES LLC (6.97)
FC TRAFFIC CONTROL, INC. (0.25)
Contract #07193228
Totals4346466.81344602.722270432.8952.2

CountyTARRANT
HighwayVA
FromVARIOUS LOCATIONS
ToWITHIN FORT WORTH DISTRICT
CSJ0902-90-108
Proj IDC 902-90-108
Work TypeTRAFFIC CONTROL DEVICES
 
0.1004310784.5738400.000.8
Work Order08-12-21
Work Began00-00-00
Work Completed
Time Computed11-11-21
Contract Working Days768
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-108
FC TRAFFIC CONTROL, INC. (0.22)
J & S DIRECTIONAL BORING INC. (0.43)
Contract #07213216
Totals4310784.570.0038400.000.8

CountyTARRANT
HighwayCS
FromMCCART AT ALTA MESA
To.
CSJ0902-90-119
Proj IDSTP 2022(870)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.2001562142.00551727.0435.3
CountyTARRANT
HighwayCS
FromINTERSECTION OF MCCART AVE.
ToAT ALTAMESA
CSJ0902-90-192
Proj IDCC 902-90-192
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
131284.000.000.0
Work Order09-21-22
Work Began12-18-23
Work Completed
Time Computed10-22-22
Contract Working Days172
Addl Days Granted0
Working Days Charged93
Percent Time Used54
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-119
AWP SAFETY (0.76)
D&G ENERGY CORPORATION (7.89)
FIBERTEL, LLC (2.06)
Contract #08223241
Totals1693426.00126176.78551727.0432.5

CountyTARRANT
HighwayCS
FromWALNUT CREEK DRIVE @ WALNUT CREEK
To.
CSJ0902-90-125
Proj IDBR 2022(252)
Work TypeBRIDGE REPLACEMENT
 
3181088.972125864.9766.8
CountyTARRANT
HighwayCR
FromSTEPHENSON LEVY RD
To@ TRIB. TO VILLAGE CREEK
CSJ0902-90-135
Proj IDBR 2021(123)
Work TypeBRIDGE REPLACEMENT
 
680157.82453877.9866.7
Work Order03-06-23
Work Began05-08-23
Work Completed
Time Computed04-06-23
Contract Working Days217
Addl Days Granted0
Working Days Charged185
Percent Time Used85
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-125
A BROTHERS MILLING, LLC (0.43)
FORTSON CONTRACTING, INC. (0.75)
HERMANOS STEEL, LLC (3.85)
KING & GEORGE, LLC (0.00)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.55)
SOUTHEAST GRINDING AND GROOVING LLC (0.21)
TEXAS SHAFTS, INC. (6.40)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.51)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.01)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.62)
TNT CRANE & RIGGING, INC. (0.31)
FC TRAFFIC CONTROL, INC. (0.25)
C. GREEN SCAPING, L.P. (0.21)
PROFESSIONAL SERVICE INDUSTRIES, INC. (0.00)
HILBASH INVESTMENT LLC (0.00)
DAVIS MOTOR CRANE SERVICE, INC. (0.00)
VISTA RIDGE CONCRETE PUMPING, INC. (0.00)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.54)
Contract #01233212
Totals3861246.7949078.452579742.9566.8

CountyTARRANT
HighwaySS 580
FromALTA MERE DR.
ToLACKLAND ROAD
CSJ0902-90-126
Proj IDF 2023(254)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
438635.00398684.2391.1
Work Order01-04-23
Work Began08-22-23
Work Completed
Time Computed02-04-23
Contract Working Days64
Addl Days Granted0
Working Days Charged66
Percent Time Used103
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-126
LINEAR TRAFFIC MARKINGS LLC (0.00)
WG ENGINEERING & CONSTRUCTION, LLC (0.00)
GOMEZ PROPERTY SOLUTIONS LLC (100.00)
Contract #12223225
Totals438635.0095661.50398684.2391.1

CountyTARRANT
HighwayCS
FromBEDFORD-EULESS RD
To@ LOREAN-MESQUITE BRANCH
CSJ0902-90-130
Proj IDBR 2021(304)
Work TypeBRIDGE REPLACEMENT
 
0.0341513118.100.000.0
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed11-02-23
Contract Working Days192
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MCMAHON CONTRACTING AND CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0902-90-130
TRP CONSTRUCTION GROUP, LLC (2.17)
DUSTROL, INC. (0.55)
PENHALL COMPANY (0.46)
WYLIE DRILLING & DRAINAGE, INC. (7.70)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (2.97)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.08)
Contract #06233631
Totals1513118.100.000.000.0