Monthly Local Let Maintenance Report For Fort Worth District As Of Aug 23, 2019 Page 1 Of 4

Last Update: Friday, August 23, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayFM0156
FromJANITORIAL MAINTENANCE AT
ToSAGINAW MAINTENANCE OFFICE
CSJ6257-39-001
Proj IDSUP - 625739001
Work TypeJANITIORIAL MAINTENANCE
 
0.01010868.0410868.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-02-13
Work Completed
Time Computed07-08-13
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6257-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06130231
Totals10868.040.0010868.0499.9

CountyWISE
HighwayUS0380
FromVARIOUS ROADWAYS WITHIN
ToWISE & JACK COUNTY
CSJ6263-14-001
Proj IDRMC - 626314001
Work TypeGUARDRAIL INSTALLATION/REPAIR
 
0.01076570.00229914.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-13
Work Began11-11-13
Work Completed12-10-14
Time Computed11-14-13
Contract Working Days365
Addl Days Granted0
Working Days Charged352
Percent Time Used96
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10130201
Totals76570.000.00229914.50100.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6289-88-001
Proj IDRMC - 628988001
Work TypeROADSIDE MOWING & HERBICIDE
 
0.010262978.88238885.52100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-17
Work Began05-05-16
Work Completed01-22-19
Time Computed04-14-16
Contract Working Days68
Addl Days Granted58
Working Days Charged116
Percent Time Used92
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6289-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150202
Totals262978.880.00238885.52100.0

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6291-17-001
Proj IDSUP - 629117001
Work TypeGROUNDS MAINTENANCE
 
0.01063628.1640583.32100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-15
Work Completed12-30-16
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged299
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150237
Totals63628.160.0040583.32100.0

CountyHOOD
HighwayUS0377
FromVARIOUS ROADWAYS IN HOOD AND
ToSOMERVELL COUNTIES
CSJ6294-99-001
Proj IDRMC - 629499001
Work TypeROADSIDE MOWING
 
0.010242961.36221040.10100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-10-18
Time Computed05-23-16
Contract Working Days64
Addl Days Granted44
Working Days Charged102
Percent Time Used94
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150204
Totals242961.360.00221040.10100.0

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToGORDON LOCATION
CSJ6298-59-001
Proj IDSUP - 629859001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01063455.1255225.12100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-16
Work Began02-01-16
Work Completed02-27-17
Time Computed02-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6298-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160231
Totals63455.120.0055225.12100.0

CountyERATH
HighwayBU0377J
FromVARIOUS ROADWAYS IN ERATH, HOOD,
ToAND SOMERVELL COUNTIES
CSJ6299-81-001
Proj IDRMC - 629981001
Work TypeRUMBLE STRIP
 
0.010196000.00122499.42100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-26-18
Work Completed08-01-18
Time Computed02-19-18
Contract Working Days25
Addl Days Granted12
Working Days Charged34
Percent Time Used91
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160201
Totals196000.000.00122499.42100.0

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS IN
ToWISE COUNTY
CSJ6299-91-001
Proj IDRMC - 629991001
Work TypeDEBRIS REMOVAL
 
0.010194817.00179438.4592.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-16
Work Began07-26-16
Work Completed
Time Computed07-27-16
Contract Working Days180
Addl Days Granted0
Working Days Charged129
Percent Time Used71
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6299-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160202
Totals194817.000.00179438.4592.1

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6301-31-001
Proj IDRMC - 630131001
Work TypeCALL OUT REFLEC PAV MRKGS PARKER
 
0.010255737.50418898.40100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began07-17-16
Work Completed08-20-18
Time Computed07-14-16
Contract Working Days89
Addl Days Granted36
Working Days Charged99
Percent Time Used79
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160206
Totals255737.500.00418898.40100.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6301-97-001
Proj IDRMC - 630197001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010136860.80123788.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began12-06-16
Work Completed01-25-18
Time Computed12-06-16
Contract Working Days365
Addl Days Granted31
Working Days Charged387
Percent Time Used97
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6301-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160205
Totals136860.800.00123788.90100.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6304-39-001
Proj IDRMC - 630439001
Work TypeTREE & BRUSH TRIMMING / REMOVAL
 
0.010326665.00334378.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-01-17
Work Began04-05-17
Work Completed
Time Computed04-12-17
Contract Working Days150
Addl Days Granted0
Working Days Charged110
Percent Time Used73
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160202
Totals326665.000.00334378.6099.9

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL
CSJ6304-42-001
Proj IDRMC - 630442001
Work TypeCLEANING AND RESHAPING DITCHES
 
0.10093054.0591144.05100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-19
Work Began02-14-19
Work Completed03-26-19
Time Computed02-14-19
Contract Working Days87
Addl Days Granted0
Working Days Charged32
Percent Time Used36
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12180201
Totals93054.050.0091144.05100.0

CountyTARRANT
HighwayIH0820
FromNORTH TARRANT ENGINEERS AND
ToMAINTENANCE OFFICES
CSJ6311-89-001
Proj IDSUP - 631189001
Work TypeJANITORIAL & GROUNDS MAINTENANCE
 
0.01013081.6811850.9190.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-17
Work Began07-11-17
Work Completed
Time Computed07-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged297
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6311-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170232
Totals13081.680.0011850.9190.5

CountyTARRANT
HighwayIH0035W
FromVARIOUS LOCATIONS
ToWITHIN SOUTH TARRANT COUNTY
CSJ6312-88-001
Proj IDRMC - 631288001
Work TypeCALLOUT REFLECTORIZED PAVEMENT MARKINGS
 
0.010273472.50285662.5599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-04-17
Contract Working Days96
Addl Days Granted0
Working Days Charged64
Percent Time Used66
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170204
Totals273472.500.00285662.5599.9

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE
ToWAGGOMAN STREET
CSJ6315-33-001
Proj IDSUP - 631533001
Work TypeJANITORIAL MAINTENCANCE
 
0.0108526.608526.6099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged389
Percent Time Used106
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6315-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170231
Totals8526.600.008526.6099.9

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATIONS WITHIN
ToNORTH TARRANT COUNTY
CSJ6315-35-001
Proj IDRMC - 631535001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010218354.44206872.8994.7
Work Order03-27-18
Work Began04-16-18
Work Completed
Time Computed04-16-18
Contract Working Days365
Addl Days Granted150
Working Days Charged481
Percent Time Used93
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02180201
Totals218354.4410668.35206872.8994.7

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6315-64-001
Proj IDSUP - 631564001
Work TypeLITTER REMOVAL
 
0.010193333.86243508.90100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-17
Work Began09-25-17
Work Completed08-24-18
Time Computed09-22-17
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170231
Totals193333.860.00243508.90100.0

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE & JACK COUNTIES
CSJ6315-65-001
Proj IDSUP - 631565001
Work TypeLITTER REMOVAL
 
0.010221679.54200985.3090.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-12-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged348
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170232
Totals221679.540.00200985.3090.6

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-66-001
Proj IDSUP - 631566001
Work TypeLITTER REMOVAL
 
0.010482216.16475289.0598.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170233
Totals482216.160.00475289.0598.5

CountySOMERVELL
HighwayUS0067
FromVARIOUS ROADWAYS IN HOOD, SOMERVELL &
ToERATH COUNTIES
CSJ6315-67-001
Proj IDSUP - 631567001
Work TypeLITTER REMOVAL
 
0.010143861.00141461.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-17
Work Began09-26-17
Work Completed08-28-18
Time Computed09-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170234
Totals143861.000.00141461.00100.0