Monthly State Let Construction Report For Houston District As Of Nov 22, 2017 Page 5 Of 10

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayIH 45
FromSP 5
ToIH 69
CSJ0500-03-605
Proj IDCM 1402(183)
Work TypeENTRANCE/EXIT RAMPS, REPLACE DCS
 
1.64030330378.0315272552.0050.3
CountyHARRIS
HighwayIH 45
FromSP 5
ToIH 69
CSJ0500-03-611
Proj IDROW 500-3-611
Work TypeUTILITY ADJUSTMENTS
 
1.640123042.7073616.6459.8
Work Order02-02-17
Work Began02-20-17
Work Completed
Time Computed02-20-17
Contract Working Days644
Addl Days Granted0
Working Days Charged203
Percent Time Used31
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-605
EPOXY DESIGN SYSTEMS, INC. (0.06)
SCOTT DERR PAINTING CO, LLC (0.04)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.35)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.12)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.34)
MESA ROD BUSTERS, INC. (7.17)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.28)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.11)
MCA COMMUNICATIONS, INC. (0.32)
IDEAL CONTRACTING SERVICES, L.L.C. (0.02)
MAGNOLIA SERVICES INCORPORATED (0.22)
MERIDIAN FENCE AND SECURITY, L.P. (0.03)
Contract #01173004
Totals30453420.731617402.8715346168.6450.3

CountyHARRIS
HighwayIH 45
FromAT IH 610 E
To.
CSJ0500-03-606
Proj IDCM 2013(984)
Work TypeCONSTRUCT DIRECT CONNECTOR
 
5.56066590610.2530227386.2345.3
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days1,237
Addl Days Granted2
Working Days Charged364
Percent Time Used29
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-03-606
ROYAL REBAR (7.63)
QUALITY TURF FARMS, LC (0.44)
SCOTT DERR PAINTING CO (0.05)
BASE CONSTRUCTION (1.00)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.13)
TRAF-TEX, INC. (4.63)
INTERSTATE BARRICADES & MARKINGS, INC. (0.62)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.75)
BORTUNCO (0.48)
ROADWAY CONSTRUCTION, LLC (0.32)
Contract #08163201
Totals66590610.251527315.8330227386.2345.3

CountyGALVESTON
HighwayIH 45
From0.452 MI S. OF FM 518
ToN OF FM 517
CSJ0500-04-096
Proj IDC 500-4-96
Work TypeGR,WIDEN STRS, BASE & PAVEMENT
 
3.394121744991.3438135386.0931.3
Work Order10-28-16
Work Began11-14-16
Work Completed
Time Computed11-27-16
Contract Working Days1,234
Addl Days Granted0
Working Days Charged265
Percent Time Used21
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-096
A & A CONSTRUCTION (0.23)
BASE CONSTRUCTION (10.83)
ESSARY, HART & MACWILIAM,INC. (0.76)
GEORGE MEEKS LANDPRO, INC. (2.00)
HAYWARD BAKER, INC. (1.18)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.19)
INTERSTATE BARRICADES & MARKINGS, INC. (1.33)
SCOTT DERR PAINTING CO, LLC (0.02)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.74)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.44)
(OLD PRIME)BORING & TUNNELING COMPANY OF AMERICA, INC. (0.38)
Contract #10163201
Totals121744991.341852446.7738135386.0931.3

CountyGALVESTON
HighwayIH 45
FromSH 6
ToGALVESTON/HARRIS COUNTY LINE
CSJ0500-04-134
Proj IDNH 1502(605)
Work TypeLANDSCAPE DEVELOPMENT
 
48.838960543.571217231.7199.9
Work Order10-19-15
Work Began01-19-16
Work Completed
Time Computed01-17-16
Contract Working Days45
Addl Days Granted30
Working Days Charged67
Percent Time Used89
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0500-04-134
G & A BORING (0.90)
Contract #08153221
Totals960543.5711968.631217231.7199.9

CountyHARRIS
HighwaySH 225
FromBW 8
ToTIDAL RD
CSJ0502-01-210
Proj IDNH 2016(060)
Work TypeREHAB BRIDGE
 
3.1602602026.602790327.7099.9
Work Order01-29-16
Work Began04-09-16
Work Completed
Time Computed02-29-16
Contract Working Days45
Addl Days Granted18
Working Days Charged92
Percent Time Used146
Contractor(s)
OHL USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-210
CHERRY CRUSHED CONCRETE (1.87)
PRIMATE CONSTRUCTION, INC. (2.39)
LONE STAR TRAFFIC SERVICE, INC. (0.82)
BATTERSON,LLP (5.53)
BREDA COMPANY, INC. (2.39)
GMJ PAVING CO. (2.15)
WEBBER BARRIER SERVICES, LLC. (0.93)
BOSWELL CONSTRUCTION COMPANY (0.61)
Contract #10153226
Totals2602026.600.002790327.7099.9

CountyHARRIS
HighwaySH 225
FromGOODYEAR
ToBW 8 (ON EB FRONTAGE ROAD ONLY)
CSJ0502-01-212
Proj IDNH 2016(415)
Work TypeDRAINAGE IMPROVEMENTS IN SECTIONS
 
0.571992122.00917429.4892.4
Work Order01-13-17
Work Began03-27-17
Work Completed
Time Computed02-12-17
Contract Working Days75
Addl Days Granted0
Working Days Charged65
Percent Time Used86
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-212
BATTERSON,LLP (2.61)
IPR SOUTH CENTRAL LLC (4.78)
Contract #11163225
Totals992122.00192167.63917429.4892.4

CountyHARRIS
HighwaySH 225
FromEB & WB FRONTAGE ROADS, RED BLUFF
ToBW 8
CSJ0502-01-213
Proj IDNH 2017(821)
Work TypeASPHALT O/L W/PV MKS
 
2.6551494920.901613212.3399.9
Work Order03-10-17
Work Began06-28-17
Work Completed
Time Computed05-09-17
Contract Working Days33
Addl Days Granted9
Working Days Charged42
Percent Time Used100
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-213
MAIN LANE INDUSTRIES LTD. (8.04)
THIRD COAST SERVICES LLC (7.03)
STRIPE LINES, INC. (5.37)
HOLES INCORPORATED (0.73)
Contract #02173221
Totals1494920.9011628.321613212.3399.9

CountyHARRIS
HighwaySH 225
FromIH 610
ToSH 146
CSJ0502-01-220
Proj IDNH 1702(514)
Work TypeLANDSCAPING
 
15.912988674.860.000.0
Work Order08-16-17
Work Began10-24-17
Work Completed
Time Computed09-15-17
Contract Working Days105
Addl Days Granted0
Working Days Charged2
Percent Time Used1
Contractor(s)
TEXAS WALL & LANDSCAPE
SUBCONTRACTOR(S) FOR CCSJ: 0502-01-220
FERTILE EARTH (1.19)
Contract #07173240
Totals988674.860.000.000.0

CountyHARRIS
HighwayIH 10
FromCROSBY-LYNCHBURG ROAD
ToGARTH ROAD
CSJ0508-01-034
Proj IDIM 0107(443)
Work TypeINSTALL CTMS
 
4.7352122122.802320948.1699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-23-14
Work Began03-11-15
Work Completed
Time Computed12-19-14
Contract Working Days312
Addl Days Granted0
Working Days Charged303
Percent Time Used97
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-034
JMHP, INC. (4.78)
BAY CITY TRAFFIC (1.61)
Contract #04143024
Totals2122122.800.002320948.1699.9

CountyHARRIS
HighwayIH 10
FromEB RAMP TO SP 330 AND CONNECTOR
To.
CSJ0508-01-341
Proj IDNH 1602(464)
Work TypeREPLACE RAMP
 
0.5351482325.531500419.4699.9
Work Order10-21-16
Work Began01-12-17
Work Completed
Time Computed12-20-16
Contract Working Days119
Addl Days Granted0
Working Days Charged105
Percent Time Used88
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-341
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.00)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (2.59)
JMHP, INC. (1.68)
Contract #08163024
Totals1482325.530.001500419.4699.9

CountyHARRIS
HighwayIH 10
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-344
Proj IDIM 0107(445)
Work TypeLANDSCAPE DEVELOPMENT
 
0.0011351369.791370236.7399.9
Work Order07-02-14
Work Began09-04-14
Work Completed
Time Computed09-04-14
Contract Working Days90
Addl Days Granted0
Working Days Charged76
Percent Time Used84
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-344
N-LINE TRAFFIC MAINTENANCE, L.P. (0.68)
ENVIRONMENTAL ALLIES, L.P. (1.26)
Contract #04143020
Totals1351369.790.001370236.7399.9

CountyHARRIS
HighwayIH 10
FromFREEPORT ST
ToBW 8
CSJ0508-01-346
Proj IDNH 1702(180)
Work TypeSPALL REP, FULL DEPTH REP, O/L,STRP
 
8.62214771556.142000.000.0
Work Order07-20-17
Work Began00-00-00
Work Completed
Time Computed08-19-17
Contract Working Days201
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-346
BATTERSON,LLP (1.76)
CAPSTONE TRUCKING (1.58)
MAIN LANE INDUSTRIES LTD. (15.55)
SOUTH TEXAS PAINTING COMPANY (0.32)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (13.42)
WILLOW CITY SIGN & RAIL, INC. (1.39)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.13)
Contract #06173004
Totals14771556.142000.002000.000.0

CountyHARRIS
HighwayIH 10
FromON ELYSIAN ST: FROM COMMERCE ST
ToHARRINGTON STREET
CSJ0508-01-351
Proj IDC 508-1-351
Work TypeREPLACE BRIDGE AND APPROACHES
 
1.20435654481.3110801908.9730.2
Work Order08-23-16
Work Began01-20-17
Work Completed
Time Computed11-21-16
Contract Working Days809
Addl Days Granted0
Working Days Charged157
Percent Time Used19
Contractor(s)
BALFOUR BEATTY INFRASTRUCTURE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-351
PROFESSIONAL TRAFFIC CONTROL, LLC (0.10)
YELLOWSTONE LANDSCAPE - CENTRAL, INC. (0.98)
GMJ PAVING CO. (0.48)
THIRD COAST SERVICES LLC (1.32)
ROYAL REBAR (7.84)
RDI FOUNDATION DRILLING (9.30)
WILLOW CITY SIGN & RAIL, INC. (0.16)
SCOTT DERR PAINTING CO, LLC (0.36)
STATEWIDE SERVICES, INC (2.58)
HOUSTON SAWING & DRILLING (0.09)
CHOCTAW ERECTORS, INC. (1.94)
CURB PLANET INC. (0.01)
UNDER CONSTRUCTION INC. (0.40)
MAK FENCING (0.11)
Contract #06163002
Totals35654481.31435499.0010801908.9730.2

CountyHARRIS
HighwayIH 10
FromIH 45
ToCHAMBERS COUNTY LINE
CSJ0508-01-360
Proj IDNH 1702(516)
Work TypeLANDSCAPING
 
31.773593718.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-16-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-01-360
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09173027
Totals593718.070.000.000.0

CountyHARRIS
HighwaySS 330
FromSAN JACINTO AVE/ROLLINGBROOK STREET
ToBAKER ROAD
CSJ0508-07-286
Proj IDCC 508-7-286
Work TypeLEFT TURN LN & UTURN IMPROVEMENTS
 
0.4272251558.842674355.9299.9
Work Order03-20-15
Work Began06-22-15
Work Completed
Time Computed06-19-15
Contract Working Days52
Addl Days Granted60
Working Days Charged100
Percent Time Used89
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0508-07-286
REGIONAL TRAFFIC SERVICES LLC (1.36)
LONE STAR TRAFFIC SERVICE, INC. (0.10)
JASSO"S SAWING & SEALING (0.88)
OSCAR ORDUNO, INC. (16.23)
CENTURY ASPHALT MATERIALS (0.79)
HOLES INCORPORATED (1.19)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (4.82)
MESA ROD BUSTERS, INC. (0.57)
CURB PLANET INC. (0.07)
BATTERSON,LLP (1.11)
Contract #01153024
Totals2251558.840.002674355.9299.9

CountyMONTGOMERY
HighwayFM 1488
FromFM 149
To0.3 MI E OF COMMUNITY RD AT MOSTYN
CSJ0523-10-034
Proj IDC 523-10-34
Work TypeCONSTRUCT RR GRADE SEPARATION
 
2.77927649979.1124840448.3789.8
Work Order10-22-13
Work Began02-16-15
Work Completed
Time Computed07-19-14
Contract Working Days478
Addl Days Granted0
Working Days Charged438
Percent Time Used91
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0523-10-034
PROFESSIONAL TRAFFIC CONTROL, LLC (1.11)
SIGNATURE CONTRACTING SERVICES, L.L.C. (2.67)
EUBANK EXCAVATION, L.L.C. (0.76)
BREDA COMPANY, INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (0.51)
GMJ PAVING CO. (5.71)
RDI FOUNDATION DRILLING (4.28)
HOUSTON SAWING & DRILLING (0.04)
TEX OP CONSTRUCTION, LP (0.60)
SCOTT DERR PAINTING CO (0.13)
NORTHWEST MATERIALS (0.25)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.15)
CREACOM, INC. (1.18)
VALLEY PLACERS, LLC (0.27)
APCON SERVICES, LLC (0.00)
FORDE CONSTRUCTION COMPANY, INC. (0.19)
CEN TEX HYDROSEED, INC. (0.42)
B & R WATER WELL SERVICES, LLC (0.01)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.13)
Contract #07133003
Totals27649979.11382096.1324840448.3789.8

CountyFORT BEND
HighwayFM 359
FromAT US 90A AND UPRR
To.
CSJ0543-02-055
Proj IDSTP 2013(734)RGS
Work TypeRR GRADE SEPARATION
 
0.40827124547.7715813340.54100.0
Work Order07-22-15
Work Began06-13-16
Work Completed10-19-17
Time Computed01-19-16
Contract Working Days482
Addl Days Granted0
Working Days Charged259
Percent Time Used53
Contractor(s)
ZACHRY CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0543-02-055
BUYERS BARRICADES, INC. (0.22)
PROFESSIONAL TRAFFIC CONTROL, LLC (0.95)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (1.36)
PRIMATE CONSTRUCTION, INC. (0.12)
JAMES CONSTRUCTION GROUP, L.L.C. (8.77)
SCOTT DERR PAINTING CO, LLC (0.30)
CHERRY CRUSHED CONCRETE (0.21)
HOUSTON SAWING & DRILLING (0.04)
W. W. FOUNDATION DRILLING, LTD. (4.51)
WILLOW CITY SIGN & RAIL, INC. (1.06)
ROYAL REBAR (4.06)
MTAM CORPORATION (0.05)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
CURB PLANET INC. (0.06)
DAVEY TREE & LAWN CARE (0.21)
Contract #05153205
Totals27124547.77636122.0615813340.54100.0

CountyFORT BEND
HighwayFM 762
From1.524 MI. SOUTH OF BRIDLEWOOD DRIVE
ToFM 1462
CSJ0543-03-072
Proj IDSTP 2017(822)
Work TypeBASE REPAIR AND OVERLAY
 
13.9211849419.981398221.6975.6
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed06-23-17
Contract Working Days75
Addl Days Granted0
Working Days Charged36
Percent Time Used48
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0543-03-072
WEST TEXAS RUMBLE STRIP (0.51)
DUSTROL, INC. (5.60)
WILLOW CITY SIGN & RAIL, INC. (4.92)
ROADSAFE TRAFFIC SYSTEMS, INC. (5.60)
PROFESSIONAL TRAFFIC CONTROL, LLC (5.60)
Contract #03173019
Totals1849419.9826037.511398221.6975.6

CountyBRAZORIA
HighwaySH 332
From0.102 MILES EAST OF LEVEE ROAD
To.
CSJ0586-01-065
Proj IDSTP 2017(823)
Work TypeREMOV & REPL DRAINS STR
 
0.024272166.320.000.0
Work Order04-24-17
Work Began10-30-17
Work Completed
Time Computed05-24-17
Contract Working Days54
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OPPORTUNITY EXCAVATION/CONCRETE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0586-01-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03173020
Totals272166.320.000.000.0

CountyBRAZORIA
HighwaySH 288
FromAT RODEO PALMS PARKWAY
To.
CSJ0598-02-047
Proj IDNH 1702(112)
Work TypeCONST NB EXIT & ENT RAMPS & TIE-IN
 
1.0632336954.31159283.006.8
Work Order07-20-17
Work Began10-16-17
Work Completed
Time Computed09-18-17
Contract Working Days138
Addl Days Granted0
Working Days Charged10
Percent Time Used7
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0598-02-047
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.59)
DURWOOD GREENE CONSTRUCTION CO. (3.99)
TRAF-TEX, INC. (5.81)
MESA ROD BUSTERS, INC. (3.42)
A-1 EROSION CONTROL, LLC (1.36)
HIGHWAY 1, LLC (1.19)
LONESTAR TRAFFIC SAFETY, LLC (0.13)
Contract #06173244
Totals2336954.31159283.00159283.006.8